Utilities (NAICS 2211): stack tests in Missouri, 2024
- 61Stack tests
A stack test measures what a source actually emits, at the stack, against the limit in its permit. Each row is one stack test recorded during 2024 at a Missouri source whose primary industry code is NAICS 2211. A facility filing more than one industry code is counted under the first one on its record.
Utilities (NAICS 2211) in Missouri, other years
Other industries in Missouri, 2024
- Mining and quarrying (NAICS 2123) 278
- Electrical equipment and appliance manufacturing (NAICS 3359) 27
- Nonmetallic mineral product manufacturing (NAICS 3273) 21
- Utilities (NAICS 2213) 19
- Primary metal manufacturing (NAICS 3314) 17
- Primary metal manufacturing (NAICS 3313) 14
- Transportation equipment manufacturing (NAICS 3361) 13
- Petroleum and coal products manufacturing (NAICS 3241) 11
- Waste management and remediation (NAICS 5622) 11
- Pipeline transportation (NAICS 4862) 9
- Food manufacturing (NAICS 3111) 7
- Food manufacturing (NAICS 3112) 7
- Paper manufacturing (NAICS 3222) 6
- Fabricated metal product manufacturing (NAICS 3329) 5
- Merchant wholesalers, nondurable goods (NAICS 4245) 5
- Chemical manufacturing (NAICS 3253) 4
- Plastics and rubber products manufacturing (NAICS 3261) 4
- Nonmetallic mineral product manufacturing (NAICS 3279) 3
- Fabricated metal product manufacturing (NAICS 3324) 3
- Beverage and tobacco manufacturing (NAICS 3121) 3
Air-emissions stack tests recorded in Missouri, 2024
| Date | Facility | Where | Kind | Agency |
|---|---|---|---|---|
| 2024-12-20 | AMEREN MISSOURI LABADIE ENERGY CENTER | LABADIE, Franklin, MO | Pass | State |
| 2024-12-20 | AMEREN MISSOURI LABADIE ENERGY CENTER | LABADIE, Franklin, MO | Pass | State |
| 2024-12-20 | AMEREN MISSOURI LABADIE ENERGY CENTER | LABADIE, Franklin, MO | Pass | State |
| 2024-12-18 | LAMAR CITY ELECTRICAL GENERATION | LAMAR, Barton, MO | Pass | State |
| 2024-12-18 | LAMAR CITY ELECTRICAL GENERATION | LAMAR, Barton, MO | Pass | State |
| 2024-12-18 | LAMAR CITY ELECTRICAL GENERATION | LAMAR, Barton, MO | Pass | State |
| 2024-12-18 | LAMAR CITY ELECTRICAL GENERATION | LAMAR, Barton, MO | Pass | State |
| 2024-12-05 | BLACK OAK POWER PRODUCERS LLC | HARTVILLE, Wright, MO | Pass | State |
| 2024-12-05 | BLACK OAK POWER PRODUCERS LLC | HARTVILLE, Wright, MO | Pass | State |
| 2024-10-31 | EVERGY INC -IATAN GENERATING STATION | WESTON, Platte, MO | Pass | State |
| 2024-10-18 | NEW MADRID POWER PLANT-ASSOC ELEC COOP | MARSTON, New Madrid, MO | Pass | State |
| 2024-10-11 | THOMAS HILL ENERGY CENTER - POWER DIVISION | CLIFTON HILL, Randolph, MO | Pass | State |
| 2024-10-11 | THOMAS HILL ENERGY CENTER - POWER DIVISION | CLIFTON HILL, Randolph, MO | Pass | State |
| 2024-09-25 | SIKESTON POWER STATION | SIKESTON, Scott, MO | Pass | State |
| 2024-09-24 | EVERGY-ST. JOSEPH LANDFILL GENERATING STATION | SAINT JOSEPH, Buchanan, MO | Pass | State |
| 2024-08-13 | THOMAS HILL ENERGY CENTER - POWER DIVISION | CLIFTON HILL, Randolph, MO | Pass | State |
| 2024-08-09 | AMEREN MISSOURI LABADIE ENERGY CENTER | LABADIE, Franklin, MO | Pass | State |
| 2024-08-09 | AMEREN MISSOURI LABADIE ENERGY CENTER | LABADIE, Franklin, MO | Pass | State |
| 2024-08-09 | AMEREN MISSOURI LABADIE ENERGY CENTER | LABADIE, Franklin, MO | Pass | State |
| 2024-08-09 | AMEREN MISSOURI LABADIE ENERGY CENTER | LABADIE, Franklin, MO | Pass | State |
| 2024-07-31 | CITY UTILITIES OF SPRINGFIELD MISSOURI JOHN TWITTY ENERGY CENTER — high-priority violation on file | SPRINGFIELD, Greene, MO | Pass | State |
| 2024-07-31 | CITY UTILITIES OF SPRINGFIELD MISSOURI JOHN TWITTY ENERGY CENTER — high-priority violation on file | SPRINGFIELD, Greene, MO | Pending | State |
| 2024-07-26 | THOMAS HILL ENERGY CENTER - POWER DIVISION | CLIFTON HILL, Randolph, MO | Pending | State |
| 2024-07-26 | THOMAS HILL ENERGY CENTER - POWER DIVISION | CLIFTON HILL, Randolph, MO | Pending | State |
| 2024-07-19 | NEW MADRID POWER PLANT-ASSOC ELEC COOP | MARSTON, New Madrid, MO | Pass | State |
| 2024-07-12 | NODAWAY POWER PLANT CONCEPTION JUNCTION | CONCEPTION JUNCTION, Nodaway, MO | Pass | State |
| 2024-07-12 | NODAWAY POWER PLANT CONCEPTION JUNCTION | CONCEPTION JUNCTION, Nodaway, MO | Pass | State |
| 2024-07-12 | NODAWAY POWER PLANT CONCEPTION JUNCTION | CONCEPTION JUNCTION, Nodaway, MO | Pass | State |
| 2024-07-12 | NODAWAY POWER PLANT CONCEPTION JUNCTION | CONCEPTION JUNCTION, Nodaway, MO | Pass | State |
| 2024-07-12 | NODAWAY POWER PLANT CONCEPTION JUNCTION | CONCEPTION JUNCTION, Nodaway, MO | Pass | State |
| 2024-07-12 | NODAWAY POWER PLANT CONCEPTION JUNCTION | CONCEPTION JUNCTION, Nodaway, MO | Pass | State |
| 2024-07-12 | NODAWAY POWER PLANT CONCEPTION JUNCTION | CONCEPTION JUNCTION, Nodaway, MO | Pass | State |
| 2024-07-12 | NODAWAY POWER PLANT CONCEPTION JUNCTION | CONCEPTION JUNCTION, Nodaway, MO | Pass | State |
| 2024-06-27 | NEW MADRID POWER PLANT-ASSOC ELEC COOP | MARSTON, New Madrid, MO | Pass | State |
| 2024-06-26 | EVERGY-HAWTHORN GENERATING STATION | KANSAS CITY, Jackson, MO | Pass | State |
| 2024-06-26 | EVERGY-HAWTHORN GENERATING STATION | KANSAS CITY, Jackson, MO | Pass | State |
| 2024-06-11 | EVERGY INC - SOUTH HARPER GENERATING STATION | PECULIAR, Cass, MO | Pass | State |
| 2024-06-04 | AMEREN MISSOURI-LANDFILL GAS TO ENERGY | MARYLAND HEIGHTS, St. Louis, MO | Pass | State |
| 2024-05-24 | THOMAS HILL ENERGY CENTER - POWER DIVISION | CLIFTON HILL, Randolph, MO | Pass | State |
| 2024-05-09 | AMERESCO JEFFERSON CITY LLC | JEFFERSON CITY, Cole, MO | Pass | State |
| 2024-05-09 | AMERESCO JEFFERSON CITY LLC | JEFFERSON CITY, Cole, MO | Pass | State |
| 2024-05-09 | AMERESCO JEFFERSON CITY LLC | JEFFERSON CITY, Cole, MO | Pass | State |
| 2024-05-09 | AMERESCO JEFFERSON CITY LLC | JEFFERSON CITY, Cole, MO | Pass | State |
| 2024-05-08 | EVERGY-HAWTHORN GENERATING STATION | KANSAS CITY, Jackson, MO | Pass | State |
| 2024-05-03 | AMEREN MISSOURI LABADIE ENERGY CENTER | LABADIE, Franklin, MO | Pass | State |
| 2024-05-03 | AMEREN MISSOURI LABADIE ENERGY CENTER | LABADIE, Franklin, MO | Pass | State |
| 2024-05-03 | AMEREN MISSOURI LABADIE ENERGY CENTER | LABADIE, Franklin, MO | Pass | State |
| 2024-05-03 | AMEREN MISSOURI LABADIE ENERGY CENTER | LABADIE, Franklin, MO | Pass | State |
| 2024-04-26 | EVERGY-HAWTHORN GENERATING STATION | KANSAS CITY, Jackson, MO | Pass | State |
| 2024-03-21 | THOMAS HILL ENERGY CENTER - POWER DIVISION | CLIFTON HILL, Randolph, MO | Pass | State |
| 2024-03-08 | AMEREN MISSOURI LABADIE ENERGY CENTER | LABADIE, Franklin, MO | Pass | State |
| 2024-03-08 | AMEREN MISSOURI LABADIE ENERGY CENTER | LABADIE, Franklin, MO | Pass | State |
| 2024-03-08 | AMEREN MISSOURI LABADIE ENERGY CENTER | LABADIE, Franklin, MO | Pass | State |
| 2024-03-08 | AMEREN MISSOURI LABADIE ENERGY CENTER | LABADIE, Franklin, MO | Pass | State |
| 2024-02-08 | UNIVERSITY OF MISSOURI POWER PLANT | COLUMBIA, Boone, MO | Pass | State |
| 2024-02-08 | UNIVERSITY OF MISSOURI POWER PLANT | COLUMBIA, Boone, MO | Pass | State |
| 2024-01-26 | ST. FRANCIS POWER PLANT | CAMPBELL, Dunklin, MO | Pass | State |
| 2024-01-26 | ST. FRANCIS POWER PLANT | CAMPBELL, Dunklin, MO | Pass | State |
| 2024-01-19 | NEW MADRID POWER PLANT-ASSOC ELEC COOP | MARSTON, New Madrid, MO | Pass | State |
| 2024-01-19 | NEW MADRID POWER PLANT-ASSOC ELEC COOP | MARSTON, New Madrid, MO | Pass | State |
| 2024-01-08 | AMEREN MISSOURI - SIOUX ENERGY CENTER | WEST ALTON, St. Charles, MO | Pass | State |
Primary NAICS code as filed on the facility record; dates as filed by the agency that recorded the stack test. Figures from EPA’s ICIS-AIR download.