- 22Stack tests
A stack test measures what a source actually emits, at the stack, against the limit in its permit. Each row is one stack test recorded during 2025 at a Nebraska source whose primary industry code is NAICS 3112. A facility filing more than one industry code is counted under the first one on its record.
Food manufacturing (NAICS 3112) in Nebraska, other years
Other industries in Nebraska, 2025
- Chemical manufacturing (NAICS 3251) 40
- Utilities (NAICS 2211) 35
- Nonmetallic mineral product manufacturing (NAICS 3273) 12
- Data processing and hosting (NAICS 5182) 12
- Pipeline transportation (NAICS 4862) 7
- Administration of environmental programs (NAICS 9241) 4
Air-emissions stack tests recorded in Nebraska, 2025
| Date | Facility | Where | Kind | Agency |
|---|---|---|---|---|
| 2025-12-16 | ADM CORN PROCESSING — high-priority violation on file | COLUMBUS, Platte, NE | N/A | State |
| 2025-12-16 | ADM CORN PROCESSING — high-priority violation on file | COLUMBUS, Platte, NE | Pass | State |
| 2025-09-24 | CARGILL INC — high-priority violation on file | BLAIR, Washington, NE | Pass | State |
| 2025-09-17 | CARGILL INC — high-priority violation on file | BLAIR, Washington, NE | N/A | State |
| 2025-09-09 | CARGILL INC — high-priority violation on file | BLAIR, Washington, NE | Pass | State |
| 2025-08-21 | ADM CORN PROCESSING — high-priority violation on file | COLUMBUS, Platte, NE | N/A | State |
| 2025-08-21 | ADM CORN PROCESSING — high-priority violation on file | COLUMBUS, Platte, NE | Fail | State |
| 2025-08-21 | CARGILL INC — high-priority violation on file | BLAIR, Washington, NE | Pass | State |
| 2025-08-20 | CARGILL INC — high-priority violation on file | BLAIR, Washington, NE | N/A | State |
| 2025-08-20 | CARGILL INC — high-priority violation on file | BLAIR, Washington, NE | Pass | State |
| 2025-08-19 | ADM CORN PROCESSING — high-priority violation on file | COLUMBUS, Platte, NE | Pass | State |
| 2025-07-29 | ADM SOYBEAN OIL EXTRACTION PLANT | LINCOLN, Lancaster, NE | Pass | Local |
| 2025-07-10 | CARGILL INC — high-priority violation on file | BLAIR, Washington, NE | Pass | State |
| 2025-07-08 | CARGILL INC — high-priority violation on file | BLAIR, Washington, NE | Pass | State |
| 2025-06-03 | ADM CORN PROCESSING — high-priority violation on file | COLUMBUS, Platte, NE | Pass | State |
| 2025-06-03 | ADM CORN PROCESSING — high-priority violation on file | COLUMBUS, Platte, NE | N/A | State |
| 2025-04-03 | NORFOLK CRUSH LLC | NORFOLK, Madison, NE | Pass | State |
| 2025-03-13 | ADM CORN PROCESSING — high-priority violation on file | COLUMBUS, Platte, NE | N/A | State |
| 2025-03-05 | ADM CORN PROCESSING — high-priority violation on file | COLUMBUS, Platte, NE | Pass | State |
| 2025-02-10 | CARGILL INC — high-priority violation on file | BLAIR, Washington, NE | Pass | State |
| 2025-02-07 | CARGILL INC — high-priority violation on file | BLAIR, Washington, NE | Pass | State |
| 2025-01-23 | NORFOLK CRUSH LLC | NORFOLK, Madison, NE | N/A | State |
Primary NAICS code as filed on the facility record; dates as filed by the agency that recorded the stack test. Figures from EPA’s ICIS-AIR download.