EPA Air · stack tests by state, industry and year
Utilities (NAICS 2211): stack tests in Virginia, 2021
- 21Stack tests
A stack test measures what a source actually emits, at the stack, against the limit in its permit. Each row is one stack test recorded during 2021 at a Virginia source whose primary industry code is NAICS 2211. A facility filing more than one industry code is counted under the first one on its record.
Utilities (NAICS 2211) in Virginia, other years
Other industries in Virginia, 2021
- Pipeline transportation (NAICS 4862) 20
- Data processing and hosting (NAICS 5182) 20
- Utilities (NAICS 2213) 9
- Waste management and remediation (NAICS 5622) 8
- Professional, scientific and technical services (NAICS 5415) 5
- National security and international affairs (NAICS 9281) 4
- Petroleum and coal products manufacturing (NAICS 3241) 4
- Merchant wholesalers, nondurable goods (NAICS 4247) 4
- Paper manufacturing (NAICS 3221) 4
- Furniture and related product manufacturing (NAICS 3371) 4
- Computer and electronic product manufacturing (NAICS 3344) 3
- Plastics and rubber products manufacturing (NAICS 3261) 3
- Wood product manufacturing (NAICS 3219) 3
Air-emissions stack tests recorded in Virginia, 2021
| Date | Facility | Where | Kind | Agency |
|---|---|---|---|---|
| 2021-12-17 | INGENCO - CHESTER PLANT | CHESTER, Chesterfield, VA | Pass | State |
| 2021-12-15 | INGENCO - BRUNSWICK PLANT | LAWRENCEVILLE, Brunswick, VA | Pass | State |
| 2021-12-07 | DOMINION ENERGY - CHESTERFIELD POWER STATION | CHESTER, Chesterfield, VA | Pass | State |
| 2021-12-07 | DOMINION ENERGY - CHESTERFIELD POWER STATION | CHESTER, Chesterfield, VA | Pass | State |
| 2021-11-17 | LES PROJECT HOLDINGS, LLC F/K/A MICHIGAN CONGENERATION SYSTEMS, INC. | LORTON, Fairfax, VA | Pass | State |
| 2021-10-20 | INGENCO - AMELIA | JETERSVILLE, Amelia, VA | Pass | State |
| 2021-09-28 | BEDFORD ELECTRIC DEPARTMENT | BEDFORD, Bedford, VA | Pass | State |
| 2021-08-06 | WOLF HILLS ENERGY | BRISTOL, Washington, VA | Pass | State |
| 2021-08-03 | DOMINION ENERGY - CHESTERFIELD POWER STATION | CHESTER, Chesterfield, VA | Pass | State |
| 2021-07-30 | DOMINION ENERGY - CHESTERFIELD POWER STATION | CHESTER, Chesterfield, VA | Pass | State |
| 2021-07-29 | COMMONWEALTH CHESAPEAKE POWER STATION | NEW CHURCH, Accomack, VA | Pass | State |
| 2021-07-09 | BEDFORD ELECTRIC DEPARTMENT | BEDFORD, Bedford, VA | Pass | State |
| 2021-07-07 | AMERICAN ELECTRIC POWER-CLINCH RIVER PLANT | CLEVELAND, Russell, VA | Pass | State |
| 2021-06-08 | AMERICAN ELECTRIC POWER-CLINCH RIVER PLANT | CLEVELAND, Russell, VA | Fail | State |
| 2021-05-28 | INGENCO - AMELIA | JETERSVILLE, Amelia, VA | Pass | State |
| 2021-03-12 | POTOMAC ENERGY CENTER LLC | LEESBURG, Loudoun, VA | Pass | State |
| 2021-03-05 | DOMINION/ODEC - CLOVER POWER STATION — high-priority violation on file | CLOVER, Halifax, VA | Pass | State |
| 2021-03-03 | NOVEC ENERGY PRODUCTION HALIFAX COUNTY BIOMASS | SOUTH BOSTON, Halifax, VA | Pass | State |
| 2021-02-25 | DOMINION ENERGY - HOPEWELL POWER STATION | HOPEWELL, Hopewell (city), VA | Pass | State |
| 2021-02-17 | DOMINION ENERGY - VIRGINIA CITY HYBRID ENERGY CENTER | ST PAUL, Wise, VA | Pass | State |
| 2021-02-11 | INGENCO WHOLESALE POWER LLC - HENRICO | GLEN ALLEN, Henrico, VA | Pass | State |
Primary NAICS code as filed on the facility record; dates as filed by the agency that recorded the stack test. Figures from EPA’s ICIS-AIR download.