EPA Air · violations by county and year
High-priority air violations in North Slope County, Alaska, 2018
- 15Violations
A high-priority violation is the most serious class of Clean Air Act non-compliance an agency records against a source; a federally reportable violation is the next step down in severity. Each row below is one violation recorded against a source in North Slope County, Alaska during 2018. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the North Slope County facility page.
North Slope County, Alaska, 2018
- Inspections 171
- Stack tests 39
High-priority air violations in North Slope County, other years
High-priority air violations recorded in North Slope County, Alaska, 2018
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2018-12-19 | HILCORP ALASKA, LLC / PRUDHOE BAY OPERATIONS CENTER / MAIN CO | Earliest FRV determination | State |
| 2018-12-17 | HILCORP ALASKA, LLC / CENTRAL GAS FACILITY (CGF) — high-priority violation on file | Earliest FRV determination | State |
| 2018-12-14 | CONOCOPHILLIPS ALASKA, INC. / KUPARUK RIVER UNIT TRANSPORTABLE DRILLI | Earliest FRV determination | State |
| 2018-12-07 | HILCORP ALASKA, LLC / FLOW STATION #1 (FS 1) — high-priority violation on file | Earliest FRV determination | State |
| 2018-11-09 | HILCORP ALASKA, LLC / LISBURNE PRODUCTION CENTER (LPC) | Earliest FRV determination | State |
| 2018-11-08 | HILCORP ALASKA, LLC / FLOW STATION #2 (FS 2) | Earliest FRV determination | State |
| 2018-10-08 | NORTH SLOPE BOROUGH / WAINWRIGHT POWER PLANT | Earliest FRV determination | State |
| 2018-10-04 | NORTH SLOPE BOROUGH / POINT HOPE POWER PLANT | Earliest FRV determination | State |
| 2018-10-02 | NORTH SLOPE BOROUGH / KAKTOVIK POWER PLANT | Earliest FRV determination | State |
| 2018-08-24 | HILCORP ALASKA, LLC / FLOW STATION #3 (FS 3) — high-priority violation on file | Earliest FRV determination | State |
| 2018-05-10 | CONOCOPHILLIPS ALASKA, INC. / ALPINE CENTRAL PROCESSING FACILITY | Earliest FRV determination | State |
| 2018-05-09 | CONOCOPHILLIPS ALASKA, INC. / CPF 1, KUPARUK CENTRAL PRODUCTION FACIL | Earliest FRV determination | State |
| 2018-04-03 | CONOCOPHILLIPS ALASKA, INC. / CPF 3, KUPARUK CENTRAL PRODUCTION FACIL | Earliest FRV determination | State |
| 2018-03-16 | HILCORP ALASKA, LLC / ENDICOTT PRODUCTION FACILITY (END) | Earliest FRV determination | State |
| 2018-01-23 | HILCORP ALASKA, LLC / OOOGURUK DEVELOPMENT PROJECT | Earliest FRV determination | State |
Dates as filed by the agency that recorded the violation. Figures from EPA’s ICIS-AIR download.