EPA Air · violations by county and year
High-priority air violations in Lucas County, Ohio, 2026
- 14Violations
A high-priority violation is the most serious class of Clean Air Act non-compliance an agency records against a source; a federally reportable violation is the next step down in severity. Each row below is one violation recorded against a source in Lucas County, Ohio during 2026. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Lucas County facility page.
Lucas County, Ohio, 2026
- Inspections 27
- Stack tests 100
High-priority air violations in Lucas County, other years
High-priority air violations recorded in Lucas County, Ohio, 2026
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2026-09-14 | HOFFMAN ROAD LANDFILL — high-priority violation on file | HPV day-zero determination | State |
| 2026-09-04 | MONDELEZ GLOBAL LLC - TOLEDO FLOUR MILL — high-priority violation on file | Earliest FRV determination | State |
| 2026-09-04 | HOFFMAN ROAD LANDFILL — high-priority violation on file | Earliest FRV determination | State |
| 2026-09-04 | CROWN CORK & SEAL — high-priority violation on file | Earliest FRV determination | State |
| 2026-06-24 | OHIO REFINING COMPANY LLC — high-priority violation on file | Earliest FRV determination | State |
| 2026-06-24 | OHIO REFINING COMPANY LLC — high-priority violation on file | Earliest FRV determination | State |
| 2026-06-24 | OHIO REFINING COMPANY LLC — high-priority violation on file | Earliest FRV determination | State |
| 2026-06-24 | CROWN CORK & SEAL — high-priority violation on file | Earliest FRV determination | State |
| 2026-06-24 | OHIO REFINING COMPANY LLC — high-priority violation on file | Earliest FRV determination | State |
| 2026-06-24 | TOLEDO TERMINAL HOLDINGS, LLC — high-priority violation on file | Earliest FRV determination | State |
| 2026-06-24 | HA INTERNATIONAL LLC — high-priority violation on file | Earliest FRV determination | State |
| 2026-06-24 | FCA US LLC - TOLEDO CUSTOM SHOP — high-priority violation on file | Earliest FRV determination | State |
| 2026-03-05 | DPI PANELS LLC — high-priority violation on file | Earliest FRV determination | State |
| 2026-02-26 | SHELLY MATERIALS PLANT # 4132 — high-priority violation on file | Earliest FRV determination | State |
Dates as filed by the agency that recorded the violation. Figures from EPA’s ICIS-AIR download.