EPA Air · violations by county and year
High-priority air violations in Grady County, Oklahoma, 2023
- 15Violations
A high-priority violation is the most serious class of Clean Air Act non-compliance an agency records against a source; a federally reportable violation is the next step down in severity. Each row below is one violation recorded against a source in Grady County, Oklahoma during 2023. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Grady County facility page.
Grady County, Oklahoma, 2023
- Inspections 130
- Stack tests 191
High-priority air violations in Grady County, other years
High-priority air violations recorded in Grady County, Oklahoma, 2023
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2023-11-01 | EOG RESOURCES INC / LIVINGSTON CTB | Earliest FRV determination | State |
| 2023-10-10 | EOG RESOURCES INC / DESKINS CTB | HPV day-zero determination | State |
| 2023-10-05 | IRON HORSE MIDSTREAM LLC / IRON HORSE PROCESSING PLANT | Earliest FRV determination | State |
| 2023-08-31 | ET GATHERING PROCESSING LLC / AGAWAM COMPRESSION STATION | Earliest FRV determination | State |
| 2023-07-10 | ET GATHERING PROCESSING LLC / GRADY GAS PLANT | Earliest FRV determination | State |
| 2023-04-19 | ENABLE GAS TRANSMISSION LLC / AMBER JUNCTION COMPRESSOR STATION | Earliest FRV determination | State |
| 2023-04-17 | ET GATHERING PROCESSING LLC / HAYES COMPRESSOR STATION | Earliest FRV determination | State |
| 2023-04-15 | ET GATHERING PROCESSING LLC / GRADY GAS PLANT | HPV day-zero determination | State |
| 2023-04-15 | ET GATHERING PROCESSING LLC / TURKEY TOWER COMPRESSOR FACILITY | Earliest FRV determination | State |
| 2023-04-12 | ONEOK FIELD SERVICES CO LLC / RIDDLE COMPRESSOR STATION | Earliest FRV determination | State |
| 2023-03-16 | MIDWEST COOLING TOWERS INC / FIBERGLASS FABRICATION PROCESSING FACI | HPV day-zero determination | State |
| 2023-03-15 | ET GATHERING PROCESSING LLC / TURKEY TOWER COMPRESSOR FACILITY | Earliest FRV determination | State |
| 2023-02-21 | VALIDUS ENERGY II MIDCON LLC / JESSICA 4 1 12XH 5 1 12XH 6 1 12XH | Earliest FRV determination | State |
| 2023-02-16 | TROY ENERGY / RINKER 1 20 | Earliest FRV determination | State |
| 2023-02-15 | ET GATHERING PROCESSING LLC / ALEX COMPRESSOR STATION | Earliest FRV determination | State |
Dates as filed by the agency that recorded the violation. Figures from EPA’s ICIS-AIR download.