EPA Air · violations by county and year
High-priority air violations in Northampton County, Pennsylvania, 2024
- 24Violations
A high-priority violation is the most serious class of Clean Air Act non-compliance an agency records against a source; a federally reportable violation is the next step down in severity. Each row below is one violation recorded against a source in Northampton County, Pennsylvania during 2024. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Northampton County facility page.
Northampton County, Pennsylvania, 2024
- Inspections 260
- Stack tests 10
High-priority air violations in Northampton County, other years
High-priority air violations recorded in Northampton County, Pennsylvania, 2024
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2024-12-19 | HEIDELBERG MATERIALS US CEMENT LLC/NAZARETH | Earliest FRV determination | State |
| 2024-12-11 | TIERPOINT LLC/BETHLEHEM 2 DATA CTR | Earliest FRV determination | State |
| 2024-11-13 | KEYSTONE PORTLAND CEMENT/EAST ALLEN — high-priority violation on file | Earliest FRV determination | State |
| 2024-10-21 | SPRAY TEK INC/BETHLEHEM — high-priority violation on file | Earliest FRV determination | State |
| 2024-10-16 | CAP GLASS ALLENTOWN LLC/GREENSTAR — high-priority violation on file | Earliest FRV determination | State |
| 2024-10-11 | BLDG MATERIALS MFG LLC/WIND GAP | Earliest FRV determination | State |
| 2024-10-03 | SPRAY TEK INC/BETHLEHEM — high-priority violation on file | Earliest FRV determination | State |
| 2024-09-27 | HEIDELBERG MATERIALS US CEMENT LLC/NAZARETH | Earliest FRV determination | State |
| 2024-09-13 | KEYSTONE PORTLAND CEMENT/EAST ALLEN — high-priority violation on file | Earliest FRV determination | State |
| 2024-09-03 | ECOPAX LLC/FORKS TWP | Earliest FRV determination | State |
| 2024-08-20 | SPRAY TEK INC/BETHLEHEM — high-priority violation on file | Earliest FRV determination | State |
| 2024-07-31 | AIRLITE PLASTICS CO/NAZARETH | Earliest FRV determination | State |
| 2024-07-31 | HEIDELBERG MATERIALS US CEMENT LLC/NAZARETH | Earliest FRV determination | State |
| 2024-07-30 | SPRAY TEK INC/BETHLEHEM — high-priority violation on file | Earliest FRV determination | State |
| 2024-06-20 | HERCULES CEMENT CO LLC/STOCKERTOWN | Earliest FRV determination | State |
| 2024-04-30 | KEYSTONE PORTLAND CEMENT/EAST ALLEN — high-priority violation on file | Earliest FRV determination | State |
| 2024-04-30 | KEYSTONE PORTLAND CEMENT/EAST ALLEN — high-priority violation on file | Earliest FRV determination | State |
| 2024-04-30 | KEYSTONE PORTLAND CEMENT/EAST ALLEN — high-priority violation on file | Earliest FRV determination | State |
| 2024-04-02 | MC PROJECT CO LLC/MARTINS CREEK | Earliest FRV determination | State |
| 2024-04-02 | MC PROJECT CO LLC/MARTINS CREEK | Earliest FRV determination | State |
| 2024-03-28 | KEYSTONE PORTLAND CEMENT/EAST ALLEN — high-priority violation on file | HPV day-zero determination | State |
| 2024-03-25 | DELAWARE QUARRIES INC / RIVERTON SAND & GRAVEL-PERMITTED ACT | Earliest FRV determination | State |
| 2024-02-27 | KEYSTONE PORTLAND CEMENT/EAST ALLEN — high-priority violation on file | Earliest FRV determination | State |
| 2024-01-08 | KEYSTONE PORTLAND CEMENT/EAST ALLEN — high-priority violation on file | Earliest FRV determination | State |
Dates as filed by the agency that recorded the violation. Figures from EPA’s ICIS-AIR download.