NPDES ALR10C5WW · Clean Water Act
MCDONALD'S SARALAND NEW CONSTRUCTION, Saraland, AL: NPDES ALR10C5WW discharge permit, effluent exceedances, inspections, penalties
MCDONALD'S SARALAND NEW CONSTRUCTION, Saraland, Alabama: General permit coverage ALR10C5WW, held by McDonald’s USA, LLC; Construction stormwater; Administratively continued; issued October 24, 2024, term to March 31, 2026, by State.
- July 23, 2026: Evaluation (S).
- April 9, 2026: Evaluation (S).
Alabama holds 7,857 Construction stormwater coverages of this permit type in EPA’s file; 5,311 were issued before ALR10C5WW. McDonald’s USA, LLC holds 3 permits in Alabama.
Other permits held by McDonald’s USA, LLC
- MCDONALDS - SEMMES, Semmes: ALR10C7AV, issued 2025-10-10
- #10-712 MCDONALD'S TROY, AL, Troy: ALR10C82J, issued 2026-05-26
Coverages issued nearest ALR10C5WW
- 2024-10-22: LOT 12, THE HERITAGE PLAT NO. 3, Alexander City: ALR10C5WM, held by Centennial Homes, LLC
- 2024-10-22: PERRY COUNTY DWSRF, Pinetucky: ALR10C5WN, held by Perry County Water Authority
- 2024-10-22: WALSHWOOD, Semmes: ALR10C5WP, held by Waverly Construction of Alabama, LLC
- 2024-10-23: 272 PINE POINT ECLECTIC, AL, Eclectic: ALR10C5WQ, held by Kane Building, LLC
- 2024-10-23: LOT 3, THE HERITAGE PLAT NO. 2, Alexander City: ALR10C5WR, held by R.L.H. Construction Inc.
- 2024-10-24: SAM'S PROPERTIES MUNFORD, Munford: ALR10C5WX, held by Sam's Properties LLC
- 2024-10-25: GULF SHORE REMEDIES, Fairhope: ALR10C5X0, held by Gulf Shore Remedies, LLC
- 2024-10-25: 16- BED CRISIS RESIDENTIAL UNIT, Decatur: ALR10C5X2, held by Mental Health Center of North Central Alabama, Inc
- 2024-10-25: TRIBUTARIES AT TROTTERS LANDING, Cedar Bluff: ALR10C5X3, held by Fairfield Tributaries II LLC
- 2024-10-25: NEW DAY FULTONDALE, Fultondale: ALR10C5X6, held by Fulton New Day, LLC
MCDONALD'S SARALAND NEW CONSTRUCTION among its neighbors
60 discharge permits are in the Lower Chasaw Creek subwatershed (HUC 031602040305); ALR10C5WW is one. Its county: 1,120, 18 major; ALR10C5WW is minor permit.
Other permits in the Lower Chasaw Creek subwatershed (HUC 031602040305)
- ALABAMA EXPORT RAILROAD - MOBILE YARD, Mobile: AL0004022, minor, term to 2022-04-30
- BERG PIPE MOBILE CORPORATION, Mobile: ALNE00339, minor, term to 2028-03-14
- BWC ALABAMA - CHICKASAW, Chickasaw: ALR108038, minor, term to 2026-03-31
- BWC ALABAMA, LLC - CHICKASAW, Chickasaw: AL0083127, minor, term to 2026-10-31
- C & J AUTOMOTIVE REPAIR, Prichard: ALG180525, minor, term to 2022-09-30
- CENTER POINT TERMINAL CHICKASAW, LLC, Chickasaw: AL0031071, minor, term to 2023-08-31
- CENTER POINT TERMINAL CHICKASAW, LLC, Chickasaw: AL0068942, minor, term to 2023-07-31
- CENTER POINT TERMINAL CHICKASAW, LLC, Chickasaw: ALG340407, minor, term to 2022-01-31
- CHICKASAW LAGOON, Chickasaw: AL0020885, major, term to 2024-09-30
- CITY OF CHICKASAW MS4 PH II, Chickasaw: ALR040044, minor, term to 2021-09-30
What stands out
- Its term runs 1 year and 158 days, October 24, 2024 to March 31, 2026; the term ended 168 days before EPA's file was loaded on September 15, 2026, and the file lists the permit as administratively continued.
- Its newest dated event on file is an inspection on July 23, 2026, 54 days before EPA's file was loaded.
- In the 365 days to September 15, 2026, it was dated 2 inspections.
- EPA's file dates 2 events for it, all in 2026.
- It is one of 13,475 discharge permits on the register in Alabama; 7,857 of them (58%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility | MCDONALD'S SARALAND NEW CONSTRUCTION |
|---|---|
| Permittee | McDonald’s USA, LLC |
| NPDES ID | ALR10C5WW |
| Status | Administratively continued |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Construction stormwater |
| Issued | October 24, 2024 |
| Expires | March 31, 2026 |
| Agency | State |
| Address | Saraland, AL 36571 |
| Subwatershed | Lower Chasaw Creek (HUC 031602040305) |
NPDES ALR10C5WW: effluent limits and exceedances
MCDONALD'S SARALAND NEW CONSTRUCTION (NPDES ALR10C5WW): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES ALR10C5WW: no pollutant row on file.
NPDES ALR10C5WW: inspections, violations and enforcement
NPDES ALR10C5WW: 2 inspections
| Date | What EPA recorded | Agency |
|---|---|---|
| July 23, 2026 | Evaluation | S |
| April 9, 2026 | Evaluation | S |
NPDES ALR10C5WW (MCDONALD'S SARALAND NEW CONSTRUCTION): no single-event violation, formal enforcement action and informal enforcement action on file.
Watch NPDES ALR10C5WW
NPDES ALR10C5WW: one email when its EPA record changes — $99/month.
Permits near NPDES ALR10C5WW
NPDES ALR10C5WW: 0 pollutant rows, 2 dated events; ICIS-NPDES download, loaded September 15, 2026.