NPDES ALR10C8BT · Clean Water Act
41ST STREET STREETSCAPE FROM 1ST AVENUE SOUTH TO 5TH AVENUE SOUTH BIRMINGHAM AL, Birmingham, AL: NPDES ALR10C8BT discharge permit, effluent exceedances, inspections, penalties
41ST STREET STREETSCAPE FROM 1ST AVENUE SOUTH TO 5TH AVENUE SOUTH BIRMINGHAM AL, Birmingham, Alabama: General permit coverage ALR10C8BT, held by City of Birmingham; Construction stormwater; Effective; issued July 23, 2026, term to March 31, 2031, by State; Highway, Street, and Bridge Construction.
- August 18, 2026: Evaluation (S).
Alabama holds 7,857 Construction stormwater coverages of this permit type in EPA’s file; 7,646 were issued before ALR10C8BT. City of Birmingham holds 5 permits in Alabama.
Other permits held by City of Birmingham
- EASTERN AREA LANDFILL, Birmingham: AL0055247, issued 2018-11-29
- NEW GEORGIA LANDFILL, Birmingham: ALG160151, issued 2022-02-01
- 40TH STREET DOT - 22346.01, Birmingham: ALR10C608, issued 2024-11-19
- COB SHUTTLESWORTH CONNECTOR TRAIL, Birmingham: ALR10C7BD, issued 2025-10-15
Coverages issued nearest ALR10C8BT
- 2026-07-22: BLACKWATER RIDGE PHASE 3, Robertsdale: ALR10C8BP, held by LOG Construction, LLC
- 2026-07-22: MARYVALE VILLAGE - PHASE II, Mobile: ALR10C8BQ, held by Maryvale Village, Ltd.
- 2026-07-23: AUBURN HIGH SCHOOL #2, Auburn: ALR10C67G, held by Evergreen Sitework, LLC
- 2026-07-23: 953 OPELIKA ROAD DEMOLITION, Auburn: ALR10C8BR, held by Standing Boy Properties, L.L.C.
- 2026-07-23: EP-SP TRAINING FACILITY, Tuskegee: ALR10C8BS, held by Safety Pros, LLC
- 2026-07-23: SAND RIDGE SUBSTATION, Birmingaham: ALR10C8BV, held by CS Beatty Construction, Inc
- 2026-07-23: D.R. HORTON - THE TOWNES ON MAIN, Gardendale: ALR10C8BW, held by D.R. Horton, Inc.
- 2026-07-23: SOUTHERN TECH, Montgomery: ALR10C8BX, held by Southern Technology Professional Consulting Services LLC
- 2026-07-24: ELMORE COUNTY JAIL, Wetumpka: ALR10C8BY, held by Elmore County
- 2026-07-27: BUILDERS GROUP DEVELOPMENT, Northport: ALR10C8BZ, held by Builders Group Development LLC
41ST STREET STREETSCAPE FROM 1ST AVENUE SOUTH TO 5TH AVENUE SOUTH BIRMINGHAM AL among its neighbors
100 discharge permits are in the Upper Village Creek subwatershed (HUC 031601110408); ALR10C8BT is one. Its county: 1,063, 13 major; ALR10C8BT is minor permit.
Other permits in the Upper Village Creek subwatershed (HUC 031601110408)
- 40TH STREET DOT - 22346.01, Birmingham: ALR10C608, minor, term to 2026-03-31
- AAA COOPER TRANSPORTATION - BIRMINGHAM, Birmingham: ALG141211, minor, term to 2027-09-30
- AAP BIRMINGHAM, Birmingham: ALR10C1UJ, minor, term to 2026-03-31
- AASF #2, Birmingham: ALNE00457, minor, term to 2029-02-28
- ABF FREIGHT SYSTEM, INC., Birmingham: ALNE00220, minor, term to 2028-06-26
- ACIMF-I059(383) PS1637, Birmingham: ALR10B692, minor, term to 2016-03-31
- ACIMF-I059(385) PS1668 & ACIMF-I059(394), Birmingham: ALR10BBEW, minor, term to 2021-03-31
- ACIPCO EMPLOYEE AND ADMINISTRATION CAMPUS IMPROVEMENTS, Birmingham: ALR10C606, minor, term to 2026-03-31
- AMFIRST FORESTDALE, Birmingham: ALR10C0MU, minor, term to 2026-03-31
- APD-IM-NHF-BRF-I065 (303), Birmingham: ALR16C601, minor, term to 2008-02-22
What stands out
- Its term runs 4 years and 251 days, July 23, 2026 to March 31, 2031.
- Its newest dated event on file is an inspection on August 18, 2026, 57 days before EPA's file was loaded.
- In the 365 days to October 14, 2026, it was dated 1 inspection.
- EPA's file dates 1 event for it, all in 2026.
- It is one of 13,475 discharge permits on the register in Alabama; 7,857 of them (58%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility | 41ST STREET STREETSCAPE FROM 1ST AVENUE SOUTH TO 5TH AVENUE SOUTH BIRMINGHAM AL |
|---|---|
| Permittee | City of Birmingham |
| NPDES ID | ALR10C8BT |
| Status | Effective |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Construction stormwater |
| Issued | July 23, 2026 |
| Expires | March 31, 2031 |
| Agency | State |
| Address | Birmingham, AL 35222 |
| Subwatershed | Upper Village Creek (HUC 031601110408) |
| NAICS | 237310 – Highway, Street, and Bridge Construction |
| SIC | 1611 – Highway And Street Construction |
NPDES ALR10C8BT: effluent limits and exceedances
41ST STREET STREETSCAPE FROM 1ST AVENUE SOUTH TO 5TH AVENUE SOUTH BIRMINGHAM AL (NPDES ALR10C8BT): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES ALR10C8BT: no pollutant row on file.
NPDES ALR10C8BT: inspections, violations and enforcement
NPDES ALR10C8BT: 1 inspection
| Date | What EPA recorded | Agency |
|---|---|---|
| August 18, 2026 | Evaluation | S |
NPDES ALR10C8BT (41ST STREET STREETSCAPE FROM 1ST AVENUE SOUTH TO 5TH AVENUE SOUTH BIRMINGHAM AL): no single-event violation, formal enforcement action and informal enforcement action on file.
Watch NPDES ALR10C8BT
NPDES ALR10C8BT: one email when its EPA record changes — $99/month.
Permits near NPDES ALR10C8BT
NPDES ALR10C8BT: 0 pollutant rows, 1 dated events; ICIS-NPDES download, loaded October 14, 2026.