NPDES AZC112040 · Clean Water Act
US 60 AT QUEEN CREEK BRIDGE REPLACEMENT, AZ: NPDES AZC112040 discharge permit, effluent exceedances, inspections, penalties
US 60 AT QUEEN CREEK BRIDGE REPLACEMENT, Arizona: General permit coverage AZC112040, held by Ames Construction, Inc.; Effective; issued August 29, 2025, term to August 28, 2030, by ADEQ; discharges to Queen Creek | Headwaters - SUPERIOR WWTP OUTFA.
- Copper, dissolved [as Cu]: 6 limits, 4 violations of any kind, 2 effluent exceedances, latest May 31, 2026, largest 1,478,119% over the limit.
- Lead, total [as Pb]: 8 limits, 4 violations of any kind.
Other permits held by Ames Construction, Inc.
- FLAGSTAFF LONE TREE IMPROVEMENTS: AZC103736, issued 2024-05-14
- FLAGSTAFF LONE TREE IMPROVEMENTS: AZC112066, issued 2025-08-29
- BNSF LPP: AZC115049, issued 2026-02-26
- HOUGHTON ROAD INDUSTRIAL COMPLEX: AZC115518, issued 2026-03-30
- SR96/SYCAMORE ACCESS ROAD INTERSECTION: AZC115578, issued 2026-04-01
- HUDBAY COPPER WORLD FWDS: AZC115619, issued 2026-04-03
- SR-260 LION SPRINGS: AZC116659, issued 2026-06-17
- I-19 IRVINGTON: AZC116840, issued 2026-07-01
US 60 AT QUEEN CREEK BRIDGE REPLACEMENT among its neighbors
14 discharge permits are in the Silver King Wash-Queen Creek subwatershed (HUC 150501000402); AZC112040 is one.
Other permits in the Silver King Wash-Queen Creek subwatershed (HUC 150501000402)
- IMERYS PERLITE USA, Superior: AZI106994, minor, term to 2030-01-15
- IMERYS PERLITE USA, Superior: AZMS81413, minor, term to 2024-12-30
- IMERYS PERLITE USA INC, Superior: AZMS67807, minor, term to 2016-05-31
- OMYA, INC, Superior: AZI107055, minor, term to 2030-01-15
- OMYA, INC, Superior: AZI107056, minor, term to 2030-01-15
- OMYA, INC, Unknown: AZMS80390, minor, term to 2024-12-30
- RESOLUTION COPPER MINING - SUPERIOR OPERATIONS, Superior: AZI108986, minor, term to 2030-01-15
- RESOLUTION COPPER MINING - SUPERIOR OPERATIONS, Superior: AZMS81431, minor, term to 2024-12-30
- RESOLUTION COPPER MINING (EAST PLANT OP), Superior: AZI108987, minor, term to 2030-01-15
- RESOLUTION COPPER MINING (EAST PLANT OP), Superior: AZMS81433, minor, term to 2024-12-30
What stands out
- Its term runs 4 years and 364 days, August 29, 2025 to August 28, 2030.
- No dated event in the 365 days to October 14, 2026.
- 1 of its 2 pollutants on file has an effluent exceedance (50%); 2 are under a numeric limit; the largest exceedance is Copper, dissolved [as Cu] at 1,478,119% over its limit.
- It is one of 7,318 discharge permits on the register in Arizona; the file names no program for it, and it is a minor discharger.
Identity
| Facility | US 60 AT QUEEN CREEK BRIDGE REPLACEMENT |
|---|---|
| Permittee | Ames Construction, Inc. |
| NPDES ID | AZC112040 |
| Status | Effective |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Issued | August 29, 2025 |
| Expires | August 28, 2030 |
| Agency | ADEQ |
| Address | AZ 85307 |
| Receiving water | Queen Creek | Headwaters - SUPERIOR WWTP OUTFA |
| Receiving water impaired | 303(D) Listed |
| Subwatershed | Silver King Wash-Queen Creek (HUC 150501000402) |
NPDES AZC112040: effluent limits and exceedances
US 60 AT QUEEN CREEK BRIDGE REPLACEMENT (NPDES AZC112040): 2 pollutants on file, 2 limited; 2 with a violation of any kind, 1 with an exceedance.
| Pollutant | Limits | Violations | Exceedances | Latest | Largest, as filed |
|---|---|---|---|---|---|
| Copper, dissolved [as Cu] | 6 | 4 | 2 | May 31, 2026 | 1,478,119% over the limit |
| Lead, total [as Pb] | 8 | 4 | 0 |
NPDES AZC112040: inspections, violations and enforcement
NPDES AZC112040 (US 60 AT QUEEN CREEK BRIDGE REPLACEMENT): no single-event violation, inspection, formal enforcement action and informal enforcement action on file.
Watch NPDES AZC112040
NPDES AZC112040: one email when its EPA record changes — $99/month.
Permits near NPDES AZC112040
NPDES AZC112040: 2 pollutant rows, 0 dated events; ICIS-NPDES download, loaded October 14, 2026.