NPDES COR10F09N · Clean Water Act
REHABILITATE PARK HEADQUARTERS EAST WATER SYSTEM AND MORAINE PARK CAMPGROUND, Estes Park, CO: NPDES COR10F09N discharge permit, effluent exceedances, inspections, penalties
REHABILITATE PARK HEADQUARTERS EAST WATER SYSTEM AND MORAINE PARK CAMPGROUND, Estes Park, Colorado: General permit coverage COR10F09N, held by Dawson B&H Company; Construction stormwater; Effective; issued May 24, 2023, term to February 16, 2027, by U.S. EPA.
Colorado holds 252 Construction stormwater coverages of this permit type in EPA’s file; 63 were issued before COR10F09N.
Coverages issued nearest COR10F09N
- 2022-11-13: BUCKLEY SFB PHASE 2, Buckley Sfb: COR10F093, held by QP Services, LLC
- 2022-11-15: FORT CARSON TA 30, Fort Carson: COR10F094, held by Alaniz Associates
- 2022-11-19: BLACK SQUIRREL CREEK CHANNEL AND HABITAT RESTORATION PHASE 1, Colorado Springs: COR10F095, held by 53 Corporation, LLC
- 2023-03-10: REPAIR AIRFIELD LIGHTING - BSFB, Buckley Sfb: COR10F09F, held by JBI Construction
- 2023-04-12: REPAIR AIRFIELD LIGHTING - CO-PERMIT WITH COR10F09F, Buckley Space Force Base: COR10F09I, held by 140 CES
- 2023-08-11: ADAL FITNESS CENTER, Schriever Afb: COR10F09T, held by HHI CORPORATION
- 2023-08-14: ENERGY & MINERALS RESEARCH FACILITY, Golden: COR10F09U, held by Robert Lee
- 2023-08-14: NLR FLATIRONS CAMPUS CONTROL CENTER FACILITY, Arvada: COR10F09V, held by U.S. Department of Energy
- 2023-08-18: ENERGY & MINERALS RESEARCH FACILITY, Golden: COR10F09Y, held by AP Mountain States, LLC
- 2023-08-21: NREL FLATIRONS CAMPUS CONTROL CENTER FACILITY, Arvada: COR10F09Z, held by Alliance for Energy Innovation LLC
REHABILITATE PARK HEADQUARTERS EAST WATER SYSTEM AND MORAINE PARK CAMPGROUND among its neighbors
1 discharge permits are in the Headwaters Big Thompson River subwatershed (HUC 101900060202); COR10F09N is one.
What stands out
- Its term runs 3 years and 268 days, May 24, 2023 to February 16, 2027.
- No dated event in the 365 days to September 15, 2026.
- It is one of 8,712 discharge permits on the register in Colorado; 299 of them (3.4%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility | REHABILITATE PARK HEADQUARTERS EAST WATER SYSTEM AND MORAINE PARK CAMPGROUND |
|---|---|
| Permittee | Dawson B&H Company |
| NPDES ID | COR10F09N |
| Status | Effective |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Construction stormwater |
| Issued | May 24, 2023 |
| Expires | February 16, 2027 |
| Agency | U.S. EPA |
| Address | Estes Park, CO 80517 |
| Subwatershed | Headwaters Big Thompson River (HUC 101900060202) |
NPDES COR10F09N: effluent limits and exceedances
REHABILITATE PARK HEADQUARTERS EAST WATER SYSTEM AND MORAINE PARK CAMPGROUND (NPDES COR10F09N): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES COR10F09N: no pollutant row on file.
NPDES COR10F09N: inspections, violations and enforcement
NPDES COR10F09N (REHABILITATE PARK HEADQUARTERS EAST WATER SYSTEM AND MORAINE PARK CAMPGROUND): no single-event violation, inspection, formal enforcement action and informal enforcement action on file.
Watch NPDES COR10F09N
NPDES COR10F09N: one email when its EPA record changes — $99/month.
Permits near NPDES COR10F09N
NPDES COR10F09N: 0 pollutant rows, 0 dated events; ICIS-NPDES download, loaded September 15, 2026.