NPDES CTSIU0119 · Clean Water Act
MERIMERE WATER TREATMENT FACILITY, Meriden, CT: NPDES CTSIU0119 discharge permit, effluent exceedances, inspections, penalties
MERIMERE WATER TREATMENT FACILITY, Meriden, Connecticut: General permit coverage CTSIU0119, held by City of Meriden; Administratively continued; issued December 7, 2023, term to October 30, 2025, by CT DEEP; discharges to Meriden WPCF.
- Flow, maximum during 24 hr period: 1 limit, 30 violations of any kind, 14 effluent exceedances, latest July 31, 2026, largest 83% over the limit.
- Flow: 1 limit, 23 violations of any kind, 7 effluent exceedances, latest July 31, 2026, largest 30% over the limit.
- pH: 2 limits, 32 violations of any kind.
- Flow rate: 1 limit, 16 violations of any kind.
- Solids, total suspended: 1 limit, 16 violations of any kind.
- Phosphorus, total [as P]: 1 limit, 16 violations of any kind.
- Arsenic, total [as As]: 1 limit, 16 violations of any kind.
- Copper, total [as Cu]: 1 limit, 16 violations of any kind.
- Lead, total [as Pb]: 1 limit, 16 violations of any kind.
- Zinc, total [as Zn]: 1 limit, 16 violations of any kind.
- Aluminum, total [as Al]: 1 limit, 16 violations of any kind.
- June 30, 2026: Notice of Violation (State).
- June 24, 2026: Permit Violations - Failure to Submit Timely Permit Renewal Application (ST6).
- May 22, 2026: Permit Violations - Failure to Submit Timely Permit Renewal Application (ST6).
- May 22, 2026: Notice of Noncompliance Issued (State).
- April 14, 2026: Permit Violations - Discharge Without a Valid Permit (ST6).
- April 14, 2026: Reporting Violations - Late Submittal of DMRs (ST6).
- April 14, 2026: Sampling (IU) (S).
- October 25, 2024: Permit Violations - Violation Specified in Comment (ST6).
- October 25, 2024: Management Practice Violations - Failure to Maintain Records (ST6).
- October 25, 2024: Monitoring Violations - Invalid/Unrepresentative Sample (ST6).
- October 25, 2024: Reporting Violations - Improper/ Incorrect Reporting (ST6).
- October 25, 2024: Reporting Violations - Failure to Notify (ST6).
- October 25, 2024: Reporting Violations - Failure to Submit DMRs (ST6).
MERIMERE WATER TREATMENT FACILITY among its neighbors
22 discharge permits are in the Headwaters Quinnipiac River subwatershed (HUC 011000040103); CTSIU0119 is one.
Other permits in the Headwaters Quinnipiac River subwatershed (HUC 011000040103)
- 3M PURIFICATION INC, Meriden: CTR050020, minor, term to 2030-09-30
- A. DUIE PYLE COMPANIES, Southington: CTR050076, minor, term to 2030-09-30
- ACCEL INTERNATIONAL HOLDINGS, LLC, Meriden: CTR050290, minor, term to 2030-09-30
- AMAZON.COM.DEDC.LLC BDL5, Wallingford: CTR050251, minor, term to 2030-09-30
- CANBERRA INDUSTRIES, INC., Meriden: CTR050190, minor, term to 2030-09-30
- CHESHIRE WPCF, Cheshire: CT0100081, major, term to 2017-09-30
- CHESHIRE WPCF, Cheshire: CTL100081, minor, term to 2025-12-31
- CHESIRE,WATER POLLUTION CONTROL FACILITY, Cheshire: CTR050244, minor, term to 2030-09-30
- CHUCK & EDDIE'S USED AUTO PARTS, Southington: CTR050381, minor, term to 2030-09-30
- GENERAL ELECTRIC COMPANY NORTH PLANT, Plainville: CTRSS0066, minor, term to 2026-03-01
What stands out
- Its term runs 1 year and 327 days, December 7, 2023 to October 30, 2025; the term ended 349 days before EPA's file was loaded on October 14, 2026, and the file lists the permit as administratively continued.
- Its newest dated event on file is an informal enforcement action on June 30, 2026, 106 days before EPA's file was loaded.
- In the 365 days to October 14, 2026, it was dated 4 single-event violations, 1 inspection, 2 informal enforcement actions.
- EPA's file dates 13 events for it, from 2024 to 2026; the busiest year is 2026 with 7.
- 2 of its 11 pollutants on file have an effluent exceedance (18%); 11 are under a numeric limit; the largest exceedance is Flow, maximum during 24 hr period at 83% over its limit.
- It is one of 1,045 discharge permits on the register in Connecticut; the file names no program for it, and it is a minor discharger.
Identity
| Facility | MERIMERE WATER TREATMENT FACILITY |
|---|---|
| Permittee | City of Meriden |
| NPDES ID | CTSIU0119 |
| Status | Administratively continued |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Issued | December 7, 2023 |
| Expires | October 30, 2025 |
| Agency | CT DEEP |
| Address | Meriden, CT 06451 |
| Receiving water | Meriden WPCF |
| Subwatershed | Headwaters Quinnipiac River (HUC 011000040103) |
NPDES CTSIU0119: effluent limits and exceedances
MERIMERE WATER TREATMENT FACILITY (NPDES CTSIU0119): 11 pollutants on file, 11 limited; 11 with a violation of any kind, 2 with an exceedance.
| Pollutant | Limits | Violations | Exceedances | Latest | Largest, as filed |
|---|---|---|---|---|---|
| Flow, maximum during 24 hr period | 1 | 30 | 14 | July 31, 2026 | 83% over the limit |
| Flow | 1 | 23 | 7 | July 31, 2026 | 30% over the limit |
| pH | 2 | 32 | 0 | ||
| Flow rate | 1 | 16 | 0 | ||
| Solids, total suspended | 1 | 16 | 0 | ||
| Phosphorus, total [as P] | 1 | 16 | 0 | ||
| Arsenic, total [as As] | 1 | 16 | 0 | ||
| Copper, total [as Cu] | 1 | 16 | 0 | ||
| Lead, total [as Pb] | 1 | 16 | 0 | ||
| Zinc, total [as Zn] | 1 | 16 | 0 | ||
| Aluminum, total [as Al] | 1 | 16 | 0 |
NPDES CTSIU0119: inspections, violations and enforcement
NPDES CTSIU0119: 10 single-event violations
| Date | What EPA recorded | Agency |
|---|---|---|
| June 24, 2026 | Permit Violations - Failure to Submit Timely Permit Renewal Application | ST6 |
| May 22, 2026 | Permit Violations - Failure to Submit Timely Permit Renewal Application | ST6 |
| April 14, 2026 | Permit Violations - Discharge Without a Valid Permit | ST6 |
| April 14, 2026 | Reporting Violations - Late Submittal of DMRs | ST6 |
| October 25, 2024 | Permit Violations - Violation Specified in Comment | ST6 |
| October 25, 2024 | Management Practice Violations - Failure to Maintain Records | ST6 |
| October 25, 2024 | Monitoring Violations - Invalid/Unrepresentative Sample | ST6 |
| October 25, 2024 | Reporting Violations - Improper/ Incorrect Reporting | ST6 |
| October 25, 2024 | Reporting Violations - Failure to Notify | ST6 |
| October 25, 2024 | Reporting Violations - Failure to Submit DMRs | ST6 |
NPDES CTSIU0119: 1 inspection
| Date | What EPA recorded | Agency |
|---|---|---|
| April 14, 2026 | Sampling (IU) | S |
NPDES CTSIU0119: 2 informal enforcement actions
| Date | What EPA recorded | Agency |
|---|---|---|
| June 30, 2026 | Notice of Violation | State |
| May 22, 2026 | Notice of Noncompliance Issued | State |
NPDES CTSIU0119 (MERIMERE WATER TREATMENT FACILITY): no formal enforcement action on file.
Watch NPDES CTSIU0119
NPDES CTSIU0119: one email when its EPA record changes — $99/month.
Permits near NPDES CTSIU0119
NPDES CTSIU0119: 11 pollutant rows, 13 dated events; ICIS-NPDES download, loaded October 14, 2026.