Velarion Records
Free: one email when NPDES FL0127434 changes. Unsubscribe any time.

NPDES FL0127434 · Clean Water Act

NEW PORT RICHEY CITY OF WWTF, New Port Richey, FL: NPDES FL0127434 discharge permit, effluent exceedances, inspections, penalties

NEW PORT RICHEY CITY OF WWTF, New Port Richey, Florida: Individual permit FL0127434, held by City of New Port Richey; Publicly owned treatment works; Administratively continued; issued November 7, 2017, term to November 6, 2022, by Florida Department of Environmental Protection; discharges to Gulf of Mexico Class III WBID 8044E.

15 of the 17 pollutants listed for NPDES FL0127434 have no violation or effluent exceedance.

  • IC25 Static Renewal 7 Day Chronic Ceriodaphnia dubia: 3 limits, 1 violation of any kind, 1 effluent exceedance, latest August 31, 2021, largest 30% over the limit.
  • IC25 Static Renewal 7 Day Chronic Chrpimephales: 3 limits, 1 violation of any kind, 1 effluent exceedance, latest August 31, 2021, largest 59% over the limit.
  • Solids, total suspended: 4 limits.
  • Flow, in conduit or thru treatment plant: 4 limits.
  • BOD, carbonaceous [5 day, 20 C]: 4 limits.
  • Nitrogen, ammonia total [as N]: 3 limits.
  • Coliform, fecal general: 3 limits.
  • pH: 2 limits.
  • Nitrogen, total [as N]: 2 limits.
  • Phosphorus, total [as P]: 2 limits.
  • Copper, total recoverable: 2 limits.
  • Enterococci: group D, MF trans, M-E, EIA: 2 limits.
  • Dichlorobromomethane: 2 limits.
  • Chlorodibromomethane: 2 limits.
  • Chlorine, total residual: 2 limits.
  • Plant capacity fact. percent of capacity: 1 limit.
  • Oxygen, dissolved [DO]: 1 limit.
  • June 4, 2026: WW SSO - Overflow to Dry Land or Building Backup (ST6).
  • September 29, 2025: WW SSO - Overflow to Dry Land or Building Backup (ST6).
  • September 26, 2025: WW SSO - Overflow to Dry Land or Building Backup (ST6).
  • September 25, 2025: WW SSO - Discharge to Waters (ST6).
  • July 22, 2025: WW SSO - Overflow to Dry Land or Building Backup (ST6).
  • July 21, 2025: WW SSO - Overflow to Dry Land or Building Backup (ST6).
  • July 18, 2025: WW SSO - Overflow to Dry Land or Building Backup (ST6).
  • July 9, 2025: WW SSO - Overflow to Dry Land or Building Backup (ST6).
  • July 1, 2025: WW SSO - Overflow to Dry Land or Building Backup (ST6).
  • June 26, 2025: WW SSO - Overflow to Dry Land or Building Backup (ST6).
  • May 29, 2025: WW SSO - Overflow to Dry Land or Building Backup (ST6).
  • May 16, 2025: WW SSO - Overflow to Dry Land or Building Backup (ST6).
  • March 27, 2025: WW SSO - Overflow to Dry Land or Building Backup (ST6).
  • February 21, 2025: WW SSO - Overflow to Dry Land or Building Backup (ST6).
  • January 1, 2025: WW SSO - Overflow to Dry Land or Building Backup (ST6).
  • October 22, 2024: WW SSO - Overflow to Dry Land or Building Backup (ST6).
  • October 11, 2024: WW SSO - Overflow to Dry Land or Building Backup (ST6).
  • August 29, 2024: WW SSO - Overflow to Dry Land or Building Backup (ST6).
  • August 19, 2024: WW SSO - Overflow to Dry Land or Building Backup (ST6).
  • August 5, 2024: WW SSO - Overflow to Dry Land or Building Backup (ST6).
  • May 29, 2024: WW SSO - Overflow to Dry Land or Building Backup (ST6).
  • March 25, 2024: WW SSO - Overflow to Dry Land or Building Backup (ST6).
  • February 27, 2024: WW SSO - Overflow to Dry Land or Building Backup (ST6).
  • October 30, 2023: WW SSO - Overflow to Dry Land or Building Backup (ST6).
  • September 23, 2023: WW SSO - Overflow to Dry Land or Building Backup (ST6).
  • September 17, 2023: WW SSO - Overflow to Dry Land or Building Backup (ST6).
  • August 6, 2023: WW SSO - Discharge to Waters (ST6).
  • July 27, 2023: WW SSO - Overflow to Dry Land or Building Backup (ST6).
  • June 20, 2023: WW SSO - Overflow to Dry Land or Building Backup (ST6).
  • May 10, 2023: WW SSO - Overflow to Dry Land or Building Backup (ST6).
  • March 19, 2023: WW SSO - Overflow to Dry Land or Building Backup (ST6).
  • December 19, 2022: WW SSO - Overflow to Dry Land or Building Backup (ST6).
  • December 7, 2022: WW SSO - Discharge to Waters (ST6).
  • December 6, 2022: WW SSO - Overflow to Dry Land or Building Backup (ST6).
  • November 16, 2022: WW SSO - Discharge to Waters (ST6).
  • October 12, 2022: WW SSO - Overflow to Dry Land or Building Backup (ST6).
  • October 11, 2022: WW SSO - Overflow to Dry Land or Building Backup (ST6).
  • October 2, 2022: WW SSO - Overflow to Dry Land or Building Backup (ST6).
  • October 1, 2022: WW SSO - Overflow to Dry Land or Building Backup (ST6).
  • September 11, 2022: WW SSO - Overflow to Dry Land or Building Backup (ST6).
  • September 9, 2022: WW SSO - Discharge to Waters (ST6).
  • September 9, 2022: WW SSO - Overflow to Dry Land or Building Backup (ST6).
  • August 9, 2022: WW SSO - Discharge to Waters (ST6).
  • August 3, 2022: WW SSO - Overflow to Dry Land or Building Backup (ST6).
  • November 11, 2021: WW SSO - Discharge to Waters (ST6).
  • August 27, 2021: WW SSO - Overflow to Dry Land or Building Backup (ST6).
  • August 14, 2021: WW SSO - Overflow to Dry Land or Building Backup (ST6).
  • August 5, 2021: WW SSO - Overflow to Dry Land or Building Backup (ST6).
  • August 4, 2021: WW SSO - Overflow to Dry Land or Building Backup (ST6).
  • July 15, 2021: WW SSO - Overflow to Dry Land or Building Backup (ST6).

Florida holds 151 Publicly owned treatment works coverages of this permit type in EPA’s file; 76 were issued before FL0127434.

Coverages issued nearest FL0127434

NEW PORT RICHEY CITY OF WWTF among its neighbors

81 discharge permits are in the Oyster Creek-Rocky CreekFrontal subwatershed (HUC 031002070502); FL0127434 is one. Its county: 700, 1 major; FL0127434 is minor permit.

Other permits in the Oyster Creek-Rocky CreekFrontal subwatershed (HUC 031002070502)

What stands out

  • Its term runs 4 years and 364 days, November 7, 2017 to November 6, 2022; the term ended 1,409 days before EPA's file was loaded on September 15, 2026, and the file lists the permit as administratively continued.
  • Its newest dated event on file is a single-event violation on June 4, 2026, 103 days before EPA's file was loaded.
  • In the 365 days to September 15, 2026, it was dated 4 single-event violations.
  • 2 of its 17 pollutants on file have an effluent exceedance (12%); 17 are under a numeric limit; the largest exceedance is IC25 Static Renewal 7 Day Chronic Chrpimephales at 59% over its limit.
  • It is one of 23,564 discharge permits on the register in Florida; 151 of them (0.6%) are in its program, Publicly owned treatment works, and it is a minor discharger.

Identity

FacilityNEW PORT RICHEY CITY OF WWTF
PermitteeCity of New Port Richey
NPDES IDFL0127434
StatusAdministratively continued
TypeIndividual permit
ClassMinor
Facility typePublicly owned treatment works
ProgramPublicly owned treatment works
IssuedNovember 7, 2017
ExpiresNovember 6, 2022
AgencyFlorida Department of Environmental Protection
AddressNew Port Richey, FL 34652
Receiving waterGulf of Mexico Class III WBID 8044E
SubwatershedOyster Creek-Rocky CreekFrontal (HUC 031002070502)
Other EPA IDs (FRS)RCRA handler FLR000132746

NPDES FL0127434: effluent limits and exceedances

NEW PORT RICHEY CITY OF WWTF (NPDES FL0127434): 17 pollutants on file, 17 limited; 2 with a violation of any kind, 2 with an exceedance.

How exceedances are counted.

PollutantLimitsViolationsExceedancesLatestLargest, as filed
IC25 Static Renewal 7 Day Chronic Ceriodaphnia dubia311August 31, 202130% over the limit
IC25 Static Renewal 7 Day Chronic Chrpimephales311August 31, 202159% over the limit
Solids, total suspended400
Flow, in conduit or thru treatment plant400
BOD, carbonaceous [5 day, 20 C]400
Nitrogen, ammonia total [as N]300
Coliform, fecal general300
pH200
Nitrogen, total [as N]200
Phosphorus, total [as P]200
Copper, total recoverable200
Enterococci: group D, MF trans, M-E, EIA200
Dichlorobromomethane200
Chlorodibromomethane200
Chlorine, total residual200
Plant capacity fact. percent of capacity100
Oxygen, dissolved [DO]100

NPDES FL0127434: inspections, violations and enforcement

NPDES FL0127434: 66 single-event violations

The newest 50 of 66.

DateWhat EPA recordedAgency
June 4, 2026WW SSO - Overflow to Dry Land or Building BackupST6
September 29, 2025WW SSO - Overflow to Dry Land or Building BackupST6
September 26, 2025WW SSO - Overflow to Dry Land or Building BackupST6
September 25, 2025WW SSO - Discharge to WatersST6
July 22, 2025WW SSO - Overflow to Dry Land or Building BackupST6
July 21, 2025WW SSO - Overflow to Dry Land or Building BackupST6
July 18, 2025WW SSO - Overflow to Dry Land or Building BackupST6
July 9, 2025WW SSO - Overflow to Dry Land or Building BackupST6
July 1, 2025WW SSO - Overflow to Dry Land or Building BackupST6
June 26, 2025WW SSO - Overflow to Dry Land or Building BackupST6
May 29, 2025WW SSO - Overflow to Dry Land or Building BackupST6
May 16, 2025WW SSO - Overflow to Dry Land or Building BackupST6
March 27, 2025WW SSO - Overflow to Dry Land or Building BackupST6
February 21, 2025WW SSO - Overflow to Dry Land or Building BackupST6
January 1, 2025WW SSO - Overflow to Dry Land or Building BackupST6
October 22, 2024WW SSO - Overflow to Dry Land or Building BackupST6
October 11, 2024WW SSO - Overflow to Dry Land or Building BackupST6
August 29, 2024WW SSO - Overflow to Dry Land or Building BackupST6
August 19, 2024WW SSO - Overflow to Dry Land or Building BackupST6
August 5, 2024WW SSO - Overflow to Dry Land or Building BackupST6
May 29, 2024WW SSO - Overflow to Dry Land or Building BackupST6
March 25, 2024WW SSO - Overflow to Dry Land or Building BackupST6
February 27, 2024WW SSO - Overflow to Dry Land or Building BackupST6
October 30, 2023WW SSO - Overflow to Dry Land or Building BackupST6
September 23, 2023WW SSO - Overflow to Dry Land or Building BackupST6
September 17, 2023WW SSO - Overflow to Dry Land or Building BackupST6
August 6, 2023WW SSO - Discharge to WatersST6
July 27, 2023WW SSO - Overflow to Dry Land or Building BackupST6
June 20, 2023WW SSO - Overflow to Dry Land or Building BackupST6
May 10, 2023WW SSO - Overflow to Dry Land or Building BackupST6
March 19, 2023WW SSO - Overflow to Dry Land or Building BackupST6
December 19, 2022WW SSO - Overflow to Dry Land or Building BackupST6
December 7, 2022WW SSO - Discharge to WatersST6
December 6, 2022WW SSO - Overflow to Dry Land or Building BackupST6
November 16, 2022WW SSO - Discharge to WatersST6
October 12, 2022WW SSO - Overflow to Dry Land or Building BackupST6
October 11, 2022WW SSO - Overflow to Dry Land or Building BackupST6
October 2, 2022WW SSO - Overflow to Dry Land or Building BackupST6
October 1, 2022WW SSO - Overflow to Dry Land or Building BackupST6
September 11, 2022WW SSO - Overflow to Dry Land or Building BackupST6
September 9, 2022WW SSO - Discharge to WatersST6
September 9, 2022WW SSO - Overflow to Dry Land or Building BackupST6
August 9, 2022WW SSO - Discharge to WatersST6
August 3, 2022WW SSO - Overflow to Dry Land or Building BackupST6
November 11, 2021WW SSO - Discharge to WatersST6
August 27, 2021WW SSO - Overflow to Dry Land or Building BackupST6
August 14, 2021WW SSO - Overflow to Dry Land or Building BackupST6
August 5, 2021WW SSO - Overflow to Dry Land or Building BackupST6
August 4, 2021WW SSO - Overflow to Dry Land or Building BackupST6
July 15, 2021WW SSO - Overflow to Dry Land or Building BackupST6

NPDES FL0127434 (NEW PORT RICHEY CITY OF WWTF): no inspection, formal enforcement action and informal enforcement action on file.

Watch NPDES FL0127434

NPDES FL0127434: one email when its EPA record changes — $99/month.

Billing

Privacy

Permits near NPDES FL0127434

NPDES FL0127434: 17 pollutant rows, 66 dated events; ICIS-NPDES download, loaded September 15, 2026.