- June 16, 2023: WW Storm Water Non-Construction - Failure to Monitor (ST6).
- June 16, 2023: WW Storm Water Non-Construction - Failure to properly operate and maintain BMPs (ST6).
- June 16, 2023: WW Storm Water Non-Construction - Failure to develop any or adequate SWPPP/SWMP (ST6).
- June 16, 2023: WW Storm Water Non-Construction - Failure to properly install/implement BMPs (ST6).
- June 16, 2023: WW Storm Water Non-Construction - Failure to Maintain Records (ST6).
- June 16, 2023: WW Storm Water Non-Construction - Failure to Conduct Inspections (ST6).
- June 30, 2020: WW Storm Water Non-Construction - Failure to Implement SWPPP/SWMP (ST6).
- June 30, 2020: WW Storm Water Non-Construction - Failure to Maintain Records (ST6).
- June 30, 2020: WW Storm Water Non-Construction - Failure to properly install/implement BMPs (ST6).
- June 30, 2020: WW Storm Water Non-Construction - Failure to properly operate and maintain BMPs (ST6).
- June 30, 2020: WW Storm Water Non-Construction - Failure to develop any or adequate SWPPP/SWMP (ST6).
Florida holds 3,868 Industrial stormwater coverages of this permit type in EPA’s file; 2,323 were issued before FLR05H675.
Coverages issued nearest FLR05H675
- 2020-01-18: HERITAGE-CRYSTAL CLEAN, LLC, Plant City: FLR05H782, held by Heritage - Crystal Clean LLC
- 2020-01-20: PREFERRED MATERIALS, INC - GAINESVILLE ASPHALT PLANT, Gainesville: FLR05F949, held by Preferred Materials Inc
- 2020-01-20: POWER SYSTEMS MFG LLC, Jupiter: FLR05H779, held by Power Systems Mfg LLC
- 2020-01-24: TURTLE COVE MARINA, Tarpon Springs: FLR05F820, held by Turtle Cove Group LLC
- 2020-01-24: SAIA MOTOR FREIGHT LINE JAX, Jacksonville: FLR05G951, held by SAIA Motor Freight Line LLC
- 2020-01-24: CVS VERO FL DISTRIBUTION LLC, Vero Beach: FLRNEF278, held by CVS Vero FL Distribution LLC
- 2020-01-25: BEYEL BROTHERS INC - MERRIT ISLAND, Merritt Island: FLR05G858, held by Beyel Brothers Inc
- 2020-01-26: IGT GLOBAL SOLUTIONS CORPORATION, Lakeland: FLRNEE839, held by IGT Global Solutions Corp
- 2020-01-30: JCI JONES CHEMICALS INC, Jacksonville: FLR05G095, held by JCI Jones Chemicals Inc
- 2020-01-31: JELD-WEN, Venice: FLR05G012, held by Jeld-Wen Inc
RECYCLED PLASTIC FACTORY LLC among its neighbors
11 discharge permits are in the Rock Creek-Oyster Creek Frontal subwatershed (HUC 031002010302); FLR05H675 is one. Its county: 538, 9 major; FLR05H675 is minor permit.
Other permits in the Rock Creek-Oyster Creek Frontal subwatershed (HUC 031002010302)
- COCO BAY (FKA ISLAND ESTATES), Grove City: FLR20FK63, minor, term to 2027-05-08
- MERCHANTS CROSSING SHOPPING CENTER, Englewood: FLR10XY74, minor, term to 2030-09-17
- MURPHY USA NO. 7704 (FORMER 5797), Englewood: FLG072130, minor, term to 2023-05-15
- MURPHY USA NO. 7704 (FORMER 5797), Englewood: FLG914789, minor, term to 2023-05-15
- PARTRIDGE SUBSTATION, Englewood: FLR20IX39, minor, term to 2031-01-17
- PARTSBOX INC-ENGLEWOOD, Englewood: FLR05J302, minor, term to 2030-01-26
- SHORES AT STILLWATER, Englewood: FLR20HL56, minor, term to 2029-08-10
- SUN STATE AWNINGS INC, Englewood: FLRNEE248, minor, term to 2013-08-19
- SUNCOAST HUMANE SOCIETY, Englewood: FLR10WC31, minor, term to 2028-07-14
- WINDWARD STUMP PASS OWNER, LLC., Englewood: FLR05J099, minor, term to 2028-10-11
What stands out
- Its term runs 4 years and 365 days, January 24, 2020 to January 23, 2025; the term ended 629 days before EPA's file was loaded on October 14, 2026, and the file lists the permit as effective.
- Its newest dated event on file is a single-event violation on June 16, 2023, 1,216 days before EPA's file was loaded.
- No dated event in the 365 days to October 14, 2026.
- EPA's file dates 11 events for it, from 2020 to 2023; the busiest year is 2023 with 6.
- It is one of 23,564 discharge permits on the register in Florida; 3,868 of them (16%) are in its program, Industrial stormwater, and it is a minor discharger.
Identity
| Facility | RECYCLED PLASTIC FACTORY LLC |
|---|---|
| Permittee | Recycled Plastic Factory LLC |
| NPDES ID | FLR05H675 |
| Status | Effective |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Industrial stormwater |
| Issued | January 24, 2020 |
| Expires | January 23, 2025 |
| Agency | Florida Department of Environmental Protection |
| Address | Englewood, FL 34223 |
| Receiving water impaired | 303(D) Listed |
| Subwatershed | Rock Creek-Oyster Creek Frontal (HUC 031002010302) |
| NAICS | 326199 – All Other Plastics Product Manufacturing |
| SIC | 3089 – Plastics Products |
NPDES FLR05H675: effluent limits and exceedances
RECYCLED PLASTIC FACTORY LLC (NPDES FLR05H675): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES FLR05H675: no pollutant row on file.
NPDES FLR05H675: inspections, violations and enforcement
NPDES FLR05H675: 11 single-event violations
| Date | What EPA recorded | Agency |
|---|---|---|
| June 16, 2023 | WW Storm Water Non-Construction - Failure to Monitor | ST6 |
| June 16, 2023 | WW Storm Water Non-Construction - Failure to properly operate and maintain BMPs | ST6 |
| June 16, 2023 | WW Storm Water Non-Construction - Failure to develop any or adequate SWPPP/SWMP | ST6 |
| June 16, 2023 | WW Storm Water Non-Construction - Failure to properly install/implement BMPs | ST6 |
| June 16, 2023 | WW Storm Water Non-Construction - Failure to Maintain Records | ST6 |
| June 16, 2023 | WW Storm Water Non-Construction - Failure to Conduct Inspections | ST6 |
| June 30, 2020 | WW Storm Water Non-Construction - Failure to Implement SWPPP/SWMP | ST6 |
| June 30, 2020 | WW Storm Water Non-Construction - Failure to Maintain Records | ST6 |
| June 30, 2020 | WW Storm Water Non-Construction - Failure to properly install/implement BMPs | ST6 |
| June 30, 2020 | WW Storm Water Non-Construction - Failure to properly operate and maintain BMPs | ST6 |
| June 30, 2020 | WW Storm Water Non-Construction - Failure to develop any or adequate SWPPP/SWMP | ST6 |
NPDES FLR05H675 (RECYCLED PLASTIC FACTORY LLC): no inspection, formal enforcement action and informal enforcement action on file.
Watch NPDES FLR05H675
NPDES FLR05H675: one email when its EPA record changes — $99/month.
Permits near NPDES FLR05H675
NPDES FLR05H675: 0 pollutant rows, 11 dated events; ICIS-NPDES download, loaded October 14, 2026.