NPDES FLR20HI40 · Clean Water Act
MULHOLLAND ROADWAY IMPROVEMENTS, Parrish, FL: NPDES FLR20HI40 discharge permit, effluent exceedances, inspections, penalties
MULHOLLAND ROADWAY IMPROVEMENTS, Parrish, Florida: General permit coverage FLR20HI40, held by E.T. MacKenzie of Florida, Inc.; Construction stormwater; Effective; issued June 23, 2024, term to June 22, 2029, by Florida Department of Environmental Protection.
- March 24, 2025: WW Storm Water Construction - Failure to Implement SWPPP/SWMP (ST6).
- March 24, 2025: WW Storm Water Construction - Failure to properly install/implement BMPs (ST6).
- March 24, 2025: WW Storm Water Construction - Failure to properly operate and maintain BMPs (ST6).
Florida holds 15,654 Construction stormwater coverages of this permit type in EPA’s file; 7,145 were issued before FLR20HI40. E.T. MacKenzie of Florida, Inc. holds 4 permits in Florida.
Other permits held by E.T. MacKenzie of Florida, Inc.
- SEAFLOWER CENTRAL AND EAST MITIGATION NODES, Bradenton: FLR20HV46, issued 2025-01-16
- ESPLANADE AT WELLEN PARK NEIGHBORHOOD 1 & 2, Englewood: FLR20IF71, issued 2025-05-12
- BOURNESIDE BLVD PH 3, Sarasota: FLR20JI90, issued 2026-06-19
Coverages issued nearest FLR20HI40
- 2024-06-23: MERIDIAN PARKS N-7, Orlando: FLR20HI34, held by Beachline South Residential LLC
- 2024-06-23: BENTLEY CROSSING, Fort Myers: FLR20HI35, held by DR Horton Inc
- 2024-06-23: WHISPERING LAKES II, Lehigh Acres: FLR20HI37, held by Pulte Home Company LLC
- 2024-06-23: SERENGETI, Yulee: FLR20HI38, held by Jb Coxwell Contracting, Inc.
- 2024-06-23: MANOR BISCAYNE 1650, Miami: FLR20HI39, held by Manor Biscayne 1650
- 2024-06-24: WFHC FP TEMP PARKING, Fort Pierce: FLR10WX54, held by Richard K Davis Construction Corp
- 2024-06-24: COWH LAKE CONINE NATURE PARK, Winter Haven: FLR10WX65
- 2024-06-24: TRAILMARK 10B, Saint Augustine: FLR10WX68, held by Richmond American Homes of Florida LP
- 2024-06-24: PROJECT SKYLINE, Miami: FLR10WX70, held by Turner Construction Company
- 2024-06-24: KEY LARGO III - ROADWAY AND DRAINAGE IMPROVEMENTS, Tavernier: FLR10WX73, held by H&R Paving, Inc.
MULHOLLAND ROADWAY IMPROVEMENTS among its neighbors
37 discharge permits are in the Lake Manatee subwatershed (HUC 031002020105); FLR20HI40 is one. Its county: 517, 12 major; FLR20HI40 is minor permit.
Other permits in the Lake Manatee subwatershed (HUC 031002020105)
- 44TH AVENUE EAST-PHASE VI EXTENSION, Lakewood Ranch: FLR20GJ05, minor, term to 2028-05-21
- AMBER CREEK TOWNHOMES, Bradenton: FLR10WS49, minor, term to 2029-04-05
- AVALON WOODS, Bradenton: FLR10VD08, minor, term to 2027-04-23
- AZARIO, Bradenton: FLR20DO52, minor, term to 2025-04-09
- BB LIVING LAKEWOOD RANCH, Bradenton: FLR20HU45, minor, term to 2029-12-21
- CHALETS AT LAKEWOOD RANCH, Lakewood Ranch: FLR20JD45, minor, term to 2031-04-04
- CODDINGTON SUBDIVISION, Bradenton: FLR10VB84, minor, term to 2027-04-06
- COYOTE SUBSTATION, Parrish: FLR10XQ14, minor, term to 2030-04-29
- CRESSWIND AT LAKEWOOD RANCH, Lakewood Ranch: FLR10WL85, minor, term to 2028-12-22
- DAVIS PARCEL J MULTI-FAMILY, Lakewood Ranch: FLR20IR67, minor, term to 2030-10-18
What stands out
- Its term runs 4 years and 364 days, June 23, 2024 to June 22, 2029.
- Its newest dated event on file is a single-event violation on March 24, 2025, 540 days before EPA's file was loaded.
- No dated event in the 365 days to September 15, 2026.
- EPA's file dates 3 events for it, all in 2025.
- It is one of 23,564 discharge permits on the register in Florida; 15,654 of them (66%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility | MULHOLLAND ROADWAY IMPROVEMENTS |
|---|---|
| Permittee | E.T. MacKenzie of Florida, Inc. |
| NPDES ID | FLR20HI40 |
| Status | Effective |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Construction stormwater |
| Issued | June 23, 2024 |
| Expires | June 22, 2029 |
| Agency | Florida Department of Environmental Protection |
| Address | Parrish, FL 34219 |
| Subwatershed | Lake Manatee (HUC 031002020105) |
NPDES FLR20HI40: effluent limits and exceedances
MULHOLLAND ROADWAY IMPROVEMENTS (NPDES FLR20HI40): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES FLR20HI40: no pollutant row on file.
NPDES FLR20HI40: inspections, violations and enforcement
NPDES FLR20HI40: 3 single-event violations
| Date | What EPA recorded | Agency |
|---|---|---|
| March 24, 2025 | WW Storm Water Construction - Failure to Implement SWPPP/SWMP | ST6 |
| March 24, 2025 | WW Storm Water Construction - Failure to properly install/implement BMPs | ST6 |
| March 24, 2025 | WW Storm Water Construction - Failure to properly operate and maintain BMPs | ST6 |
NPDES FLR20HI40 (MULHOLLAND ROADWAY IMPROVEMENTS): no inspection, formal enforcement action and informal enforcement action on file.
Watch NPDES FLR20HI40
NPDES FLR20HI40: one email when its EPA record changes — $99/month.
Permits near NPDES FLR20HI40
NPDES FLR20HI40: 0 pollutant rows, 3 dated events; ICIS-NPDES download, loaded September 15, 2026.