SOUTHPORT - HIGHPOINT 115 KV TRANSMISSION LINE, Panama City, FL: NPDES FLR20IU72 discharge permit, effluent exceedances, inspections, penalties
SOUTHPORT - HIGHPOINT 115 KV TRANSMISSION LINE, Panama City, Florida: General permit coverage FLR20IU72, held by PowerSouth Energy Cooperative; Construction stormwater; Effective; issued December 8, 2025, term to December 7, 2030, by Florida Department of Environmental Protection.
Florida holds 15,654 Construction stormwater coverages of this permit type in EPA’s file; 12,224 were issued before FLR20IU72. PowerSouth Energy Cooperative holds 5 permits in Florida.
Other permits held by PowerSouth Energy Cooperative
- AUBURN 115 KV SUBSTATION, Crestview: FLR10YD00, issued 2025-12-15
- FREEPORT DISTRIBUTION SUBSTATION, Freeport: FLR10YF06, issued 2026-01-24
- HIGHPOINT SUBSTATION, Panama City: FLR20JA29, issued 2026-02-26
- FREEPORT SW - FREEPORT 115KV TRANSMISSION LINE, Freeport: FLR20JL76, issued 2026-07-27
Coverages issued nearest FLR20IU72
- 2025-12-08: HORIZON WEST - SITE, Winter Garden: FLR10YC64, held by Keator Construction LLC
- 2025-12-08: DAIRY QUEEN LONGWOOD, Longwood: FLR10YC67, held by Yogiraj 21 LLC
- 2025-12-08: WILDLIGHT - TOWNHOMES AT WESTERLY PARK, Yulee: FLR10YC68, held by David Weekley Homes, LLC
- 2025-12-08: WILDERNESS TRAIL, Port Saint Lucie: FLR20IU69, held by Wilderness Trail
- 2025-12-08: GULFPORT 58TH STREET S ROADWAY IMPROVEMENTS, Saint Petersburg: FLR20IU70, held by Keystone Excavators Inc
- 2025-12-08: PINE FOREST DROP STRUCTURE REPAIRS, Cantonment: FLR20IU75, held by Blue Terra LLC
- 2025-12-08: RIVER LANDING NW TOWNHOMES, Zephyrhills: FLR20IU76, held by CF GTIS III River Landing, LLC
- 2025-12-08: DEVINE FARMS BRIDGE, Cantonment: FLR20IU77, held by Chavers Construction Inc.
- 2025-12-08: SUNTRAX, Auburndale: FLR20IU78, held by Tucker Paving Inc.
- 2025-12-10: SILVER LAKE ESTATES PHASE 2, Leesburg: FLR20IU79, held by City Homes Leesburg LLC
SOUTHPORT - HIGHPOINT 115 KV TRANSMISSION LINE among its neighbors
9 discharge permits are in the Deer Point Lake subwatershed (HUC 031401010505); FLR20IU72 is one.
Other permits in the Deer Point Lake subwatershed (HUC 031401010505)
- CRS SOUTHPORT, Southport: FLR10WC69, minor, term to 2028-07-16
- DOLLAR GENERAL, Panama City: FLG073951, minor, term to 2029-02-25
- HIGHPOINT SUBSTATION, Panama City: FLR20JA29, minor, term to 2031-02-25
- HODGES BAYOU PLANTATION PHASE 3, Panama City: FLR20FG40, minor, term to 2027-03-16
- HODGES BAYOU PLANTATION PHASE II, Panama City: FLR10VE33, minor, term to 2027-05-08
- MILLER MARINE YACHT SERVICE INC, Southport: FLR05F485, minor, term to 2012-08-11
- TITUS AND 2321 ROUNDABOUT, Panama City: FLR20IR30, minor, term to 2030-10-15
- TITUS PARK PHASE 4, Panama City: FLR20IZ75, minor, term to 2031-02-19
What stands out
- Its term runs 4 years and 364 days, December 8, 2025 to December 7, 2030.
- No dated event in the 365 days to September 15, 2026.
- It is one of 23,564 discharge permits on the register in Florida; 15,654 of them (66%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility | SOUTHPORT - HIGHPOINT 115 KV TRANSMISSION LINE |
|---|---|
| Permittee | PowerSouth Energy Cooperative |
| NPDES ID | FLR20IU72 |
| Status | Effective |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Construction stormwater |
| Issued | December 8, 2025 |
| Expires | December 7, 2030 |
| Agency | Florida Department of Environmental Protection |
| Address | Panama City, FL 32409 |
| Subwatershed | Deer Point Lake (HUC 031401010505) |
NPDES FLR20IU72: effluent limits and exceedances
SOUTHPORT - HIGHPOINT 115 KV TRANSMISSION LINE (NPDES FLR20IU72): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES FLR20IU72: no pollutant row on file.
NPDES FLR20IU72: inspections, violations and enforcement
NPDES FLR20IU72 (SOUTHPORT - HIGHPOINT 115 KV TRANSMISSION LINE): no single-event violation, inspection, formal enforcement action and informal enforcement action on file.
Watch NPDES FLR20IU72