NPDES FLR20JE82 · Clean Water Act
DUKE ENERGY DRIFTON - LLOYD TRANSMISSION LINE, Monticello, FL: NPDES FLR20JE82 discharge permit, effluent exceedances, inspections, penalties
DUKE ENERGY DRIFTON - LLOYD TRANSMISSION LINE, Monticello, Florida: General permit coverage FLR20JE82, held by Duke Energy Florida, LLC.; Construction stormwater; Effective; issued April 25, 2026, term to April 24, 2031, by Florida Department of Environmental Protection.
Florida holds 15,654 Construction stormwater coverages of this permit type in EPA’s file; 13,943 were issued before FLR20JE82.
Coverages issued nearest FLR20JE82
- 2026-04-25: 8500 BISCAYNE, Miami: FLR10YK42, held by Diversified Site General Contracting Inc
- 2026-04-25: BEHAVIORAL HEALTH TREATMENT CENTER PARKING ADDITION, New Port Richey: FLR10YK89, held by K and B Sitework LLC
- 2026-04-25: PINE TREE GOLF CLUB, Boynton Beach: FLR10YK94, held by Pine Tree Golf Club
- 2026-04-25: DAIRY QUEEN EUSTIS, Eustis: FLR10YK96, held by Yogiraj 22 LLC
- 2026-04-25: RIVER OAKS PRESERVE, Fort Lauderdale: FLR10YK99, held by Ric-Man Construction Florida
- 2026-04-25: SPIRIT LAKE RD INTERSECTION IMPROVEMENTS, Winter Haven: FLR20JE83, held by Kamminga Roodvoets, Inc.
- 2026-04-25: RACETRAC - WAUCHULA EDO, Wauchula: FLR20JE84, held by RaceTrac, Inc.
- 2026-04-25: ELLI-3525, Gulf Stream: FLR20JE85
- 2026-04-25: SORRENTO PINES PHASE 3B, Eustis: FLR20JE86, held by Hughes Brothers Construction, Inc.
- 2026-04-25: ABACUS STORAGE BIG BEND, Gibsonton: FLR20JE87, held by Abacus Storage Riverview, LLC
Other permits in Monticello
- (DB) MONTICELLO - BOSTON, Monticello: FLR20JE19, minor, term to 2031-04-15
- ASHVILLE HWY REPAVE, Monticello: FLR10XJ26, minor, term to 2030-01-17
- ASHVILLE HWY REPAVE, Monticello: FLR10XK93, minor, term to 2030-02-13
- BAILEY MILL RENEWABLE ENERGY CENTER, Monticello: FLR20IP56, minor, term to 2030-09-20
- BOSTON HWY PH I II - JEFFERSON CO, Monticello: FLR20JJ96, minor, term to 2031-07-01
- CITY OF MONTICELLO, Monticello: FLL027839, minor, term to 2025-12-31
- CR 259 OVE SCL RAILROAD BRIDGE, Monticello: FLR20FE77, minor, term to 2027-02-23
- JEFFERSON COUNTY REST AREA SPRAYFIELD, Monticello: FLR20GU69, minor, term to 2028-11-30
- JEFFERSON MOSQUITO CONTROL DISTRICT, Monticello: FLG510071, minor, term to 2022-02-08
- LAKE ROAD RESURFACING, Monticello: FLR20FS27, minor, term to 2027-09-16
What stands out
- Its term runs 4 years and 364 days, April 25, 2026 to April 24, 2031.
- No dated event in the 365 days to September 15, 2026.
- It is one of 23,564 discharge permits on the register in Florida; 15,654 of them (66%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility | DUKE ENERGY DRIFTON - LLOYD TRANSMISSION LINE |
|---|---|
| Permittee | Duke Energy Florida, LLC. |
| NPDES ID | FLR20JE82 |
| Status | Effective |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Construction stormwater |
| Issued | April 25, 2026 |
| Expires | April 24, 2031 |
| Agency | Florida Department of Environmental Protection |
| Address | Monticello, FL 32344 |
NPDES FLR20JE82: effluent limits and exceedances
DUKE ENERGY DRIFTON - LLOYD TRANSMISSION LINE (NPDES FLR20JE82): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES FLR20JE82: no pollutant row on file.
NPDES FLR20JE82: inspections, violations and enforcement
NPDES FLR20JE82 (DUKE ENERGY DRIFTON - LLOYD TRANSMISSION LINE): no single-event violation, inspection, formal enforcement action and informal enforcement action on file.
Watch NPDES FLR20JE82
NPDES FLR20JE82: one email when its EPA record changes — $99/month.
Permits near NPDES FLR20JE82
NPDES FLR20JE82: 0 pollutant rows, 0 dated events; ICIS-NPDES download, loaded September 15, 2026.