Velarion Records
Free: one email when NPDES GA0037206 changes. Unsubscribe any time.

NPDES GA0037206 · Clean Water Act

PATTERSON, CITY OF (PATTERSON WPCP), Patterson, GA: NPDES GA0037206 discharge permit, effluent exceedances, inspections, penalties

PATTERSON, CITY OF (PATTERSON WPCP), Patterson, Georgia: Individual permit GA0037206, held by Patterson, City of; Publicly owned treatment works; Effective; issued June 26, 2017, term to June 30, 2022; Sewage Treatment Facilities.

  • Solids, suspended percent removal: 1 limit, 118 violations of any kind, 6 effluent exceedances, latest June 30, 2026, largest 447% over the limit.
  • Solids, total suspended: 8 limits, 886 violations of any kind, 4 effluent exceedances, latest March 31, 2003, largest 827% over the limit.
  • BOD, 5-day, 20 deg. C: 12 limits, 884 violations of any kind, 4 effluent exceedances, latest August 31, 2023, largest 480% over the limit.
  • Flow, in conduit or thru treatment plant: 2 limits, 224 violations of any kind, 4 effluent exceedances, latest September 30, 2017, largest 192% over the limit.
  • BOD, 5-day, percent removal: 1 limit, 114 violations of any kind, 2 effluent exceedances, latest August 31, 2023, largest 101% over the limit.
  • pH: 2 limits, 221 violations of any kind, 1 effluent exceedance, latest April 30, 2009.
  • Coliform, fecal general: 2 limits, 135 violations of any kind, 1 effluent exceedance, latest August 31, 2021, largest 57% over the limit.
  • Nitrogen, ammonia total [as N]: 8 limits, 440 violations of any kind.
  • Solids, sludge, total, dry weight: 1 limit, 71 violations of any kind.
  • Oxygen, dissolved [DO]: 1 limit, 1 violation of any kind.
  • August 13, 2026: Notice of Noncompliance Issued (State).
  • July 17, 2026: Management Practice Violations - Improper Operation and Maintenance (ST6).
  • July 17, 2026: Notice of Noncompliance Issued (State).
  • June 24, 2026: Evaluation (S).

Georgia holds 458 Publicly owned treatment works coverages of this permit type in EPA’s file; 303 were issued before GA0037206.

Coverages issued nearest GA0037206

PATTERSON, CITY OF (PATTERSON WPCP) among its neighbors

73 discharge permits are in the Lower Buffalo Creek subwatershed (HUC 030702011104); GA0037206 is one.

Other permits in the Lower Buffalo Creek subwatershed (HUC 030702011104)

What stands out

  • Its term runs 5 years and 4 days, June 26, 2017 to June 30, 2022; the term ended 1,567 days before EPA's file was loaded on October 14, 2026, and the file lists the permit as effective.
  • Its newest dated event on file is an informal enforcement action on August 13, 2026, 62 days before EPA's file was loaded.
  • In the 365 days to October 14, 2026, it was dated 1 single-event violation, 1 inspection, 2 informal enforcement actions.
  • EPA's file dates 4 events for it, all in 2026.
  • 7 of its 10 pollutants on file have an effluent exceedance (70%); 10 are under a numeric limit; the largest exceedance is Solids, total suspended at 827% over its limit.
  • It is one of 45,725 discharge permits on the register in Georgia; 521 of them (1.1%) are in its program, Publicly owned treatment works, and it is a minor discharger.

Identity

FacilityPATTERSON, CITY OF (PATTERSON WPCP)
PermitteePatterson, City of
NPDES IDGA0037206
StatusEffective
TypeIndividual permit
ClassMinor
Facility typePublicly owned treatment works
ProgramPublicly owned treatment works
IssuedJune 26, 2017
ExpiresJune 30, 2022
AddressPatterson, GA 31557
SubwatershedLower Buffalo Creek (HUC 030702011104)
NAICS221320 – Sewage Treatment Facilities
SIC4952 – Sewerage Systems

NPDES GA0037206: effluent limits and exceedances

PATTERSON, CITY OF (PATTERSON WPCP) (NPDES GA0037206): 10 pollutants on file, 10 limited; 10 with a violation of any kind, 7 with an exceedance.

How exceedances are counted.

PollutantLimitsViolationsExceedancesLatestLargest, as filed
Solids, suspended percent removal11186June 30, 2026447% over the limit
Solids, total suspended88864March 31, 2003827% over the limit
BOD, 5-day, 20 deg. C128844August 31, 2023480% over the limit
Flow, in conduit or thru treatment plant22244September 30, 2017192% over the limit
BOD, 5-day, percent removal11142August 31, 2023101% over the limit
pH22211April 30, 2009
Coliform, fecal general21351August 31, 202157% over the limit
Nitrogen, ammonia total [as N]84400
Solids, sludge, total, dry weight1710
Oxygen, dissolved [DO]110

NPDES GA0037206: inspections, violations and enforcement

NPDES GA0037206: 1 single-event violation

DateWhat EPA recordedAgency
July 17, 2026Management Practice Violations - Improper Operation and MaintenanceST6

NPDES GA0037206: 1 inspection

DateWhat EPA recordedAgency
June 24, 2026EvaluationS

NPDES GA0037206: 2 informal enforcement actions

DateWhat EPA recordedAgency
August 13, 2026Notice of Noncompliance IssuedState
July 17, 2026Notice of Noncompliance IssuedState

NPDES GA0037206 (PATTERSON, CITY OF (PATTERSON WPCP)): no formal enforcement action on file.

Watch NPDES GA0037206

NPDES GA0037206: one email when its EPA record changes — $99/month.

Billing

Privacy

Permits near NPDES GA0037206

NPDES GA0037206: 10 pollutant rows, 4 dated events; ICIS-NPDES download, loaded October 14, 2026.