CHICKEN OF THE SEA INTERNATIONAL (TUNA CANNING PLANT), Lyons, GA: NPDES GAP050315 discharge permit, effluent exceedances, inspections, penalties

CHICKEN OF THE SEA INTERNATIONAL (TUNA CANNING PLANT), Lyons, Georgia: Individual industrial user permit GAP050315, held by Chicken of the Sea International; Administratively continued; issued August 3, 2017, term to August 31, 2022.

  • Oil & Grease: 2 limits, 8 violations of any kind, 4 effluent exceedances, latest February 28, 2026, largest 48% over the limit.
  • BOD, 5-day, 20 deg. C: 2 limits, 6 violations of any kind, 2 effluent exceedances, latest October 31, 2021, largest 53% over the limit.
  • pH: 2 limits, 5 violations of any kind, 1 effluent exceedance, latest May 31, 2018.
  • Solids, total suspended: 2 limits, 6 violations of any kind.
  • Flow, in conduit or thru treatment plant: 2 limits, 4 violations of any kind.
  • Solids, sludge, total, dry weight: 1 limit, 2 violations of any kind.
  • July 27, 2026: Notice of Noncompliance Issued (State).
  • February 24, 2026: Sampling (IU) (S).
  • February 24, 2026: Evaluation (IU) (S).

Other permits held by Chicken of the Sea International

Other permits in Lyons

What stands out

  • Its term runs 5 years and 28 days, August 3, 2017 to August 31, 2022; the term ended 1,476 days before EPA's file was loaded on September 15, 2026, and the file lists the permit as administratively continued.
  • Its newest dated event on file is an informal enforcement action on July 27, 2026, 50 days before EPA's file was loaded.
  • In the 365 days to September 15, 2026, it was dated 2 inspections, 1 informal enforcement action.
  • EPA's file dates 3 events for it, all in 2026.
  • 3 of its 6 pollutants on file have an effluent exceedance (50%); 6 are under a numeric limit; the largest exceedance is BOD, 5-day, 20 deg. C at 53% over its limit.
  • It is one of 45,725 discharge permits on the register in Georgia; the file names no program for it, and it is a minor discharger.

Identity

FacilityCHICKEN OF THE SEA INTERNATIONAL (TUNA CANNING PLANT)
PermitteeChicken of the Sea International
NPDES IDGAP050315
StatusAdministratively continued
TypeIndividual industrial user permit
ClassMinor
Facility typeNon-POTW
IssuedAugust 3, 2017
ExpiresAugust 31, 2022
AddressLyons, GA 30436

NPDES GAP050315: effluent limits and exceedances

CHICKEN OF THE SEA INTERNATIONAL (TUNA CANNING PLANT) (NPDES GAP050315): 6 pollutants on file, 6 limited; 6 with a violation of any kind, 3 with an exceedance.

How exceedances are counted.

PollutantLimitsViolationsExceedancesLatestLargest, as filed
Oil & Grease284February 28, 202648% over the limit
BOD, 5-day, 20 deg. C262October 31, 202153% over the limit
pH251May 31, 2018
Solids, total suspended260
Flow, in conduit or thru treatment plant240
Solids, sludge, total, dry weight120

NPDES GAP050315: inspections, violations and enforcement

NPDES GAP050315: 2 inspections

DateWhat EPA recordedAgency
February 24, 2026Sampling (IU)S
February 24, 2026Evaluation (IU)S

NPDES GAP050315: 1 informal enforcement action

DateWhat EPA recordedAgency
July 27, 2026Notice of Noncompliance IssuedState

NPDES GAP050315 (CHICKEN OF THE SEA INTERNATIONAL (TUNA CANNING PLANT)): no single-event violation and formal enforcement action on file.

Watch NPDES GAP050315

NPDES GAP050315: one email when its EPA record changes — $99/month.

Billing

Privacy

Permits near NPDES GAP050315

NPDES GAP050315: 6 pollutant rows, 3 dated events; ICIS-NPDES download, loaded September 15, 2026.