NPDES GAR18B584 · Clean Water Act
SPRING RIDGE LOT 3, Dallas, GA: NPDES GAR18B584 discharge permit, effluent exceedances, inspections, penalties
SPRING RIDGE LOT 3, Dallas, Georgia: General permit coverage GAR18B584, held by Jonathan Leggett; Construction stormwater; Effective; issued August 1, 2023, term to July 31, 2028.
Georgia holds 40,604 Construction stormwater coverages of this permit type in EPA’s file; 31,933 were issued before GAR18B584. Jonathan Leggett holds 3 permits in Georgia.
Other permits held by Jonathan Leggett
- SPRING RIDGE LOT 4, Dallas: GAR18C20E, issued 2023-08-01
- SPRING RIDGE LOT 5B, Dallas: GAR18C30E, issued 2023-08-01
Coverages issued nearest GAR18B584
- 2023-08-01: CHANDLER RIDGE (SCOTT PUCKETT), Buford: GAR18B57F, held by Scott Puckett
- 2023-08-01: THE GALLOWAY SCHOOL, Atlanta: GAR18B580, held by Kristin Wold
- 2023-08-01: COASTAL TERRACE SOLID WASTE HANDLING FACILITY, Waynesville: GAR18B581, held by John Kelly
- 2023-08-01: MARTIN ROAD UTILITY BARN, Dalton: GAR18B582, held by Curt Welch
- 2023-08-01: OMAHA DRIVE - LOT 32, Elberton: GAR18B583, held by Ethan Collins
- 2023-08-01: MARINE CORPS LOGISTICS BASE, Albany: GAR18B586, held by Bryan Henderson
- 2023-08-01: JUSTIN BAILEY POULTRY FARM, Cohutta: GAR18B587, held by Justin Bailey
- 2023-08-01: CIVIC CENTER R1 SENIOR, Atlanta: GAR18B588, held by The Michaels Organization
- 2023-08-01: GBA 198 WASHINGTON STATE PRISON, Davisboro: GAR18B589, held by Charles Parrish
- 2023-08-01: CITY OF CARTERSVILLE RECREATION CENTER, Cartersville: GAR18B58B, held by Cartersville
SPRING RIDGE LOT 3 among its neighbors
85 discharge permits are in the Lane Creek-Pumpkinvine Creek subwatershed (HUC 031501041102); GAR18B584 is one.
Other permits in the Lane Creek-Pumpkinvine Creek subwatershed (HUC 031501041102)
- 1090 W MEMORIAL DR, Dallas: GAR18B577, minor, term to 2028-07-31
- 600 FT. RUNWAY 31 SAFETY OVERRUN PROJECT, Dallas: GAR147617, minor, term to 2018-07-31
- 693 LONE BEAR PATH, Dallas: GAR18B96B, minor, term to 2028-07-31
- AIRPORT FIRE STATION, E911, & EOC FACILITY, Dallas: GAR147594, minor, term to 2018-07-31
- ARBORS AT SILVER TRAIL, Dallas: GAR3858DF, minor, term to 2018-07-31
- ARBORS AT SILVER TRAIL LOT 2, Dallas: GAR380466, minor, term to 2018-07-31
- ARBORS AT SILVER TRAIL LOT 96, Dallas: GAR381608, minor, term to 2018-07-31
- ARBORS AT SILVER TRAIL LOTS 101, 104, 377, & 376, Dallas: GAR381569, minor, term to 2018-07-31
- ARBORS AT SILVER TRAIL- LOTS 123, 124, 353, 358, Dallas: GAR3852AA, minor, term to 2018-07-31
- ARBORS AT SILVER TRAIL- 147, 364-366, Dallas: GAR384B3D, minor, term to 2018-07-31
What stands out
- Its term runs 4 years and 365 days, August 1, 2023 to July 31, 2028.
- No dated event in the 365 days to September 15, 2026.
- It is one of 45,725 discharge permits on the register in Georgia; 40,604 of them (89%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility | SPRING RIDGE LOT 3 |
|---|---|
| Permittee | Jonathan Leggett |
| NPDES ID | GAR18B584 |
| Status | Effective |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Construction stormwater |
| Issued | August 1, 2023 |
| Expires | July 31, 2028 |
| Address | Dallas, GA 30132 |
| Subwatershed | Lane Creek-Pumpkinvine Creek (HUC 031501041102) |
NPDES GAR18B584: effluent limits and exceedances
SPRING RIDGE LOT 3 (NPDES GAR18B584): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES GAR18B584: no pollutant row on file.
NPDES GAR18B584: inspections, violations and enforcement
NPDES GAR18B584 (SPRING RIDGE LOT 3): no single-event violation, inspection, formal enforcement action and informal enforcement action on file.
Watch NPDES GAR18B584
NPDES GAR18B584: one email when its EPA record changes — $99/month.
Permits near NPDES GAR18B584
NPDES GAR18B584: 0 pollutant rows, 0 dated events; ICIS-NPDES download, loaded September 15, 2026.