NPDES GAR248716 · Clean Water Act
GEORGIA POWER CO ARKWRIGHT- NORTH MACON/SOUTH MACON (WCD-EPD), Macon, GA: NPDES GAR248716 discharge permit, effluent exceedances, inspections, penalties
GEORGIA POWER CO ARKWRIGHT- NORTH MACON/SOUTH MACON (WCD-EPD), Macon, Georgia: General permit coverage GAR248716, held by Georgia Power Company; Construction stormwater; Administratively continued; issued September 23, 2013, term to July 31, 2018.
Georgia holds 40,604 Construction stormwater coverages of this permit type in EPA’s file; 24 were issued before GAR248716. Georgia Power Company holds 2 permits in Georgia.
Other permits held by Georgia Power Company
- GRUMMAN ROAD LANDFILL CLOSURE (CHATHAM COUNTY), Savannah: GAR152883, issued 2013-09-23
Coverages issued nearest GAR248716
- 2013-09-23: CR42 - GOWDER ROAD: GAR248710, held by BANKS COUNTY BOARD OF COMMISSIONERS
- 2013-09-23: CR34 - JOHN MORRIS ROAD: GAR248711, held by BANKS COUNTY BOARD OF COMMISSIONERS
- 2013-09-23: BOWDON HP PRIM, Bowdon: GAR248713, held by Southern Company Gas
- 2013-09-23: RIDGEWOOD PARK WATER MAIN REPLACEMENT: GAR248714, held by Cobb County Water System
- 2013-09-23: POTTERS CORSSING 115/25 KV SUBSTATION: GAR248715, held by Georgia Transmission Corp.
- 2013-09-23: FORT GORDON OH/UG CONVERSION PHASE 6, Fort Gordon: GAR248717, held by Georgia Power Company (Burns Wetherington)
- 2013-09-23: FEMC FLINT ELECTRIC MEMBERSHIP CORPORATION PROJECT #177308 (CWP 210) (WCD-EPD): GAR248718, held by FLINT ELECTRIC MEMBERSHIP CORPORATION
- 2013-09-23: ATKINSON BRIDGE ROAD WATER: GAR248721, held by FRANKLIN COUNTY BOARD OF COMMISSIONERS
- 2013-09-23: SPRING STREET ENHANCEMENT PROJECT: GAR248723, held by City of Monroe
- 2013-09-23: DUKE ROAD CLEARING, GRADING, BASE & PAVING, Harlem: GAR248725, held by Columbia County Board of Commissioners
GEORGIA POWER CO ARKWRIGHT- NORTH MACON/SOUTH MACON (WCD-EPD) among its neighbors
45 discharge permits are in the Stone Creek-Ocmulgee River subwatershed (HUC 030701031605); GAR248716 is one.
Other permits in the Stone Creek-Ocmulgee River subwatershed (HUC 030701031605)
- 301 JOE TAMPLIN BOULEVARD CLEARING & GRASSING, Macon: GAR147088, minor, term to 2018-07-31
- ARDENT MILLS, LLC, Macon: GAIS02231, minor, term to 2017-05-31
- BROOKS COUNTY CDBG 2012, Unknown: GAR244947, minor, term to 2018-07-31
- BROOKS LANDING LOT 15, Unknown: GAR371763, minor, term to 2018-07-31
- CENTRAL CITY PARK FIELD #7 SOFTBALL FIELD RENO, 150 WILLIE SMOKIE GLOVER DR, Macon: GAR18BBE5, minor, term to 2028-07-31
- CK EM SOLUTION USA - MACON, Macon: GAIS14593, minor, term to 2027-05-31
- CREEKSIDE VILLAGE ? LOT 15, Unknown: GAR380913, minor, term to 2018-07-31
- D.T. WALTON MIXED USE DEVELOPMENT, Macon: GAR18B32B, minor, term to 2028-07-31
- DEMOLITION OF TINDALL HEIGHTS (PHASE 1A), Macon: GAR151215, minor, term to 2018-07-31
- DEMOLITION OF TINDALL HEIGHTS (PHASE 1B), Macon: GAR151216, minor, term to 2018-07-31
What stands out
- Its term runs 4 years and 311 days, September 23, 2013 to July 31, 2018; the term ended 2,968 days before EPA's file was loaded on September 15, 2026, and the file lists the permit as administratively continued.
- No dated event in the 365 days to September 15, 2026.
- It is one of 45,725 discharge permits on the register in Georgia; 40,604 of them (89%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility | GEORGIA POWER CO ARKWRIGHT- NORTH MACON/SOUTH MACON (WCD-EPD) |
|---|---|
| Permittee | Georgia Power Company |
| NPDES ID | GAR248716 |
| Status | Administratively continued |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Construction stormwater |
| Issued | September 23, 2013 |
| Expires | July 31, 2018 |
| Address | Macon, GA 11111 |
| Subwatershed | Stone Creek-Ocmulgee River (HUC 030701031605) |
NPDES GAR248716: effluent limits and exceedances
GEORGIA POWER CO ARKWRIGHT- NORTH MACON/SOUTH MACON (WCD-EPD) (NPDES GAR248716): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES GAR248716: no pollutant row on file.
NPDES GAR248716: inspections, violations and enforcement
NPDES GAR248716 (GEORGIA POWER CO ARKWRIGHT- NORTH MACON/SOUTH MACON (WCD-EPD)): no single-event violation, inspection, formal enforcement action and informal enforcement action on file.
Watch NPDES GAR248716
NPDES GAR248716: one email when its EPA record changes — $99/month.
Permits near NPDES GAR248716
NPDES GAR248716: 0 pollutant rows, 0 dated events; ICIS-NPDES download, loaded September 15, 2026.