SR 92 SOUTH WATER MAIN RELOCATION - GOTHARD'S CREEK TO NEBO ROAD, Hiram, Georgia: General permit coverage GAR2488FA, held by Paulding County Water System; Construction stormwater; Administratively continued; issued September 24, 2013, term to July 31, 2018; Highway, Street, and Bridge Construction.
Georgia holds 40,604 Construction stormwater coverages of this permit type in EPA’s file; 27,822 were issued before GAR2488FA. Paulding County Water System holds 5 permits in Georgia.
Other permits held by Paulding County Water System
- PAULDING COUNTY WATER SYSTEM (UPPER SWEETWATER WRF), Villa Rica: GA0038890, issued 2013-05-16
- MACLAND ROAD WATER TANKS PHASE II: GAR151110, issued 2013-09-23
- MACLAND ROAD TANK SIGHT: GAR247716, issued 2013-09-23
- PAULDING COUNTY SR 61 AT NEBO ROAD INTERSECTION WATER RELOCATION, Dallas: GAR247967, issued 2013-09-23
Coverages issued nearest GAR2488FA
- 2013-09-24: DOVE CREEK SCHOOL R/W IMPROVEMENTS, Statham: GAR2488E6, held by Oconee County Public Works Department
- 2013-09-24: BROOKWOOD ROAD, Cumming: GAR2488EB, held by Forsyth County
- 2013-09-24: GATE 8 EXPANSION (GARDEN CITY TERMINAL) (CHATHAM COUNTY), Garden City: GAR2488ED, held by Georgia Ports Authority
- 2013-09-24: COBB NORTH WATER MAIN REPLACEMENT, Marietta: GAR2488F4, held by Cobb County Water System
- 2013-09-24: NORTHWINDS SUBSTATION, Forest Park: GAR2488F8, held by Georgia Power Company
- 2013-09-24: HIGHWAY 54 FIBER PROJECT, Fayetteville: GAR2488FE, held by Georgia Transmission Corporation
- 2013-09-24: SPRINGFIELD SUBSTATION, N/A: GAR248902, held by Georgia Power Company
- 2013-09-24: SERENBE LAND APPLICATION SYSTEM, PHASE II (DRAIN FIELD), Palmetto: GAR24890B, held by Chattahoochee Hills Utilities, LLC
- 2013-09-24: NEW TRACK TO SERVE CHOICE TERMINAL INLAND PORT, Bainbridge: GAR248914, held by Decatur County Industrial Development Authority
- 2013-09-24: HIGHWAY 319 BUSINESS PARK ONE GEORGIA PROJECT, Fitzgerald: GAR248918, held by Fitzgerald/Ben Hill County Development Authority
SR 92 SOUTH WATER MAIN RELOCATION - GOTHARD'S CREEK TO NEBO ROAD among its neighbors
90 discharge permits are in the Middle Sweetwater Creek subwatershed (HUC 031300020203); GAR2488FA is one.
Other permits in the Middle Sweetwater Creek subwatershed (HUC 031300020203)
- , -PROVIDENCE WALK (FKA EVANS PARK) LOT 2-12,16-22,25-29,32-35,44-46,54A, 78-1, N/A: GAR366493, minor, term to 2018-07-31
- 458 MARY HILL LANE, Douglasville: GAR18B9D7, minor, term to 2028-07-31
- 4595 MARONEY MILL, Douglasville: GAR3970B4, minor, term to 2028-07-31
- 480 MARY HILL LANE, Douglasville: GAR18B9DA, minor, term to 2028-07-31
- ASHBROOKE HILLS LOT 15, Powder Springs: GAR379913, minor, term to 2018-07-31
- ASHBROOKE HILLS LOT 17, Powder Springs: GAR380035, minor, term to 2018-07-31
- ASHBROOKE HILLS LOT 27, Powder Springs: GAR380708, minor, term to 2018-07-31
- ASHBROOKE HILLS LOT 38, Powder Springs: GAR379909, minor, term to 2018-07-31
- ASHBROOKE HILLS LOT 51, Powder Springs: GAR381580, minor, term to 2018-07-31
- ASHBROOKE HILLS LOTS 10 & 18, Powder Springs: GAR379911, minor, term to 2018-07-31
What stands out
- Its term runs 4 years and 310 days, September 24, 2013 to July 31, 2018; the term ended 2,997 days before EPA's file was loaded on October 14, 2026, and the file lists the permit as administratively continued.
- No dated event in the 365 days to October 14, 2026.
- It is one of 45,725 discharge permits on the register in Georgia; 40,604 of them (89%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility | SR 92 SOUTH WATER MAIN RELOCATION - GOTHARD'S CREEK TO NEBO ROAD |
|---|---|
| Permittee | Paulding County Water System |
| NPDES ID | GAR2488FA |
| Status | Administratively continued |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Construction stormwater |
| Issued | September 24, 2013 |
| Expires | July 31, 2018 |
| Address | Hiram, GA 30141 |
| Subwatershed | Middle Sweetwater Creek (HUC 031300020203) |
| NAICS | 237310 – Highway, Street, and Bridge Construction |
| SIC | 1611 – Highway And Street Construction |
NPDES GAR2488FA: effluent limits and exceedances
SR 92 SOUTH WATER MAIN RELOCATION - GOTHARD'S CREEK TO NEBO ROAD (NPDES GAR2488FA): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES GAR2488FA: no pollutant row on file.
NPDES GAR2488FA: inspections, violations and enforcement
NPDES GAR2488FA (SR 92 SOUTH WATER MAIN RELOCATION - GOTHARD'S CREEK TO NEBO ROAD): no single-event violation, inspection, formal enforcement action and informal enforcement action on file.
Watch NPDES GAR2488FA
NPDES GAR2488FA: one email when its EPA record changes — $99/month.
Permits near NPDES GAR2488FA
NPDES GAR2488FA: 0 pollutant rows, 0 dated events; ICIS-NPDES download, loaded October 14, 2026.