NPDES GAR248933 · Clean Water Act
CARGILL SANITARY SEWER IMPROVEMENTS - PHASE 3, Gainesville, GA: NPDES GAR248933 discharge permit, effluent exceedances, inspections, penalties
CARGILL SANITARY SEWER IMPROVEMENTS - PHASE 3, Gainesville, Georgia: General permit coverage GAR248933, held by City of Gainesville; Construction stormwater; Administratively continued; issued September 24, 2013, term to July 31, 2018; Water and Sewer Line and Related Structures Construction.
Georgia holds 40,604 Construction stormwater coverages of this permit type in EPA’s file; 27,822 were issued before GAR248933. City of Gainesville holds 6 permits in Georgia.
Other permits held by City of Gainesville
- CITY OF GAINESVILLE MS4, Gainesville: GAG610042, issued 2017-12-06
- CITY OF GAINESVILLE, Gainesville: GAL020168, issued 2021-01-01
- CITY OF GAINESVILLE - PUBLIC SAFETY COMPLEX, Gainesville: GAR18B5D2, issued 2023-08-01
- FY17 WATER MAIN EXTENSIONS AND IMPROVEMENTS: GAR248772, issued 2013-09-23
- ATHENS STREET CORRIDOR PEDESTRIANS IMPROVEMENT, Gainesville: GAR25444C, issued 2023-08-01
Coverages issued nearest GAR248933
- 2013-09-24: WOLF CREEK 230/25 KV SUBSTATION, Atlanta: GAR248922, held by Georgia Transmission Corp
- 2013-09-24: PLAINVIEW ROAD, Commerce: GAR248923, held by Georgia DOT
- 2013-09-24: PARALLEL TAXIWAY PHASE I & IIA, Jesup: GAR248924, held by Wayne County Board of Commissioners
- 2013-09-24: PATAULA CREEK 115/12 KV SUBSTATION, Morris: GAR248926, held by Georgia Transmission Corp.
- 2013-09-24: FRANKLIN-HART COUNTY AIRPORT- PARALLEL TAXIWAY PHASE 1, Canon: GAR248928, held by Harris Little
- 2013-09-24: ALCOVY RIVER PUMP STATION AND FORCE MAIN, Monroe: GAR248936, held by City of Monroe
- 2013-09-24: CAIRO-GRADY COUNTY AIRPORT, Cairo: GAR248939, held by City of Cairao
- 2013-09-24: CHATEAU ELAN - LEGENDS SANITARY SEWER, Braselton: GAR24893D, held by Fountainhead Residential Development, LLC
- 2013-09-24: BELLS FERRY ROAD AT RIDGE ROAD INTERSECTION, Canton: GAR24893E, held by Cherokee County Board of Commissioners
- 2013-09-24: ALSTON 46/25 KV SUBSTATION, Mount Vernon: GAR248941, held by Georgia Transmission Corp.
CARGILL SANITARY SEWER IMPROVEMENTS - PHASE 3 among its neighbors
64 discharge permits are in the Upper Lake Sidney Lanier subwatershed (HUC 031300010801); GAR248933 is one.
Other permits in the Upper Lake Sidney Lanier subwatershed (HUC 031300010801)
- 2484 S. SMITH ROAD, Gainesville: GAR18AAA4, minor, term to 2028-07-31
- BEECHWOOD BORROW PIT, Unknown: GAR147089, minor, term to 2018-07-31
- BEND BIOSCIENCE (FORMERLY RECRO), Gainesville: GAR18BEEC, minor, term to 2028-07-31
- BRF00-0012-01 (080), PI# 122012, Gainesville: GAR248841, minor, term to 2023-07-31
- CARRIAGE NISSAN (CAR LOT ADDITIONS), Gainesville: GAR149419, minor, term to 2018-07-31
- CHATTAHOOCHEE GOLF CLUB, Gainesville: GAR18C03B, minor, term to 2028-07-31
- CRESSWIND AT LAKE LANIER - PHASE IIB FKA OK LAKE LANIER LLLP, Gainesville: GAR338701, minor, term to 2018-07-31
- DAVIS ROAD SELF STORAGE, Stockbridge: GAR18B387, minor, term to 2028-07-31
- FIFTH THIRD BANK THOMPSON BRIDGE, Gainesville: GAR18BA90, minor, term to 2028-07-31
- GAINESVILLE MAINTENANCE SHOP, Gainesville: GAIS10592, minor, term to 2017-05-31
What stands out
- Its term runs 4 years and 310 days, September 24, 2013 to July 31, 2018; the term ended 2,997 days before EPA's file was loaded on October 14, 2026, and the file lists the permit as administratively continued.
- No dated event in the 365 days to October 14, 2026.
- It is one of 45,725 discharge permits on the register in Georgia; 40,604 of them (89%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility | CARGILL SANITARY SEWER IMPROVEMENTS - PHASE 3 |
|---|---|
| Permittee | City of Gainesville |
| NPDES ID | GAR248933 |
| Status | Administratively continued |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Construction stormwater |
| Issued | September 24, 2013 |
| Expires | July 31, 2018 |
| Address | Gainesville, GA 30501 |
| Receiving water impaired | 303(D) Listed |
| Subwatershed | Upper Lake Sidney Lanier (HUC 031300010801) |
| NAICS | 237110 – Water and Sewer Line and Related Structures Construction |
| SIC | 1623 – Water, Sewer, And Utility Lines |
NPDES GAR248933: effluent limits and exceedances
CARGILL SANITARY SEWER IMPROVEMENTS - PHASE 3 (NPDES GAR248933): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES GAR248933: no pollutant row on file.
NPDES GAR248933: inspections, violations and enforcement
NPDES GAR248933 (CARGILL SANITARY SEWER IMPROVEMENTS - PHASE 3): no single-event violation, inspection, formal enforcement action and informal enforcement action on file.
Watch NPDES GAR248933
NPDES GAR248933: one email when its EPA record changes — $99/month.
Permits near NPDES GAR248933
NPDES GAR248933: 0 pollutant rows, 0 dated events; ICIS-NPDES download, loaded October 14, 2026.