NPDES GAR352949 · Clean Water Act
LAKE VISTA ESTATES - LOT 41, GA: NPDES GAR352949 discharge permit, effluent exceedances, inspections, penalties
LAKE VISTA ESTATES - LOT 41, Georgia: General permit coverage GAR352949, held by Rackley Construction; Construction stormwater; Effective; issued September 23, 2013, term to July 31, 2018.
Georgia holds 40,604 Construction stormwater coverages of this permit type in EPA’s file; 24 were issued before GAR352949. Rackley Construction holds 10 permits in Georgia.
Other permits held by Rackley Construction
- MCCAIN FARMS - LOT 3: GAR349819, issued 2013-09-23
- MCCAIN FARMS - LOT 5: GAR349824, issued 2013-09-23
- MCCAIN FARMS - LOT 10: GAR349826, issued 2013-09-23
- MCCAIN FARMS - LOT 13: GAR349827, issued 2013-09-23
- MCCAIN FARMS - LOT 16: GAR349828, issued 2013-09-23
- MCCAIN FARMS - LOT 34: GAR349829, issued 2013-09-23
- MCCAIN FARMS_LOT 32: GAR350195, issued 2013-09-23
- LAKE VISTA ESTATES - LOT 42: GAR354627, issued 2013-09-23
- LAKE VISTA ESTATES - LOT 43: GAR354628, issued 2013-09-23
Coverages issued nearest GAR352949
- 2013-09-23: ADDITION TO LEXINGTON HILLS, LOT 1J, Columbus: GAR352921, held by Grayhawk Homes Inc.
- 2013-09-23: CANTERBURY FARMS PHASE XII-WILLIFORD RUN SECTION II, Grovetown: GAR352924, held by Euchee Forest, LLC
- 2013-09-23: MADISON RESERVE SUBDIVISION, Alpharetta: GAR352925, held by Talmar Construction LLC
- 2013-09-23: WALKER HILL PHASE 2 - LOT 92, Hephzibah: GAR352934, held by Carbon Construction
- 2013-09-23: WALKER HILL PHASE 2 - LOT 97, Hephzibah: GAR352935, held by Carbon Construction
- 2013-09-23: MAGNOLIA VALLEY - LOT 7E, Evans: GAR352958, held by Faircloth Homes, Inc.
- 2013-09-23: GROVE POINTE SUBDIVISION PHASE 1 LOT # 36, Hahira: GAR352963, held by THAD MITCHELL
- 2013-09-23: MCCOY'S CREEK SECTION 2 - LOT 8D: GAR352974, held by Winchester Homes of GA
- 2013-09-23: MCCOY'S CREEK SECTION 2 - LOT 9D: GAR352975, held by Winchester Homes of GA
- 2013-09-23: CASTLEBERRY HILLS-UNIT 3: GAR352976, held by Southside Land Ventures, LLC
What stands out
- Its term runs 4 years and 311 days, September 23, 2013 to July 31, 2018; the term ended 2,997 days before EPA's file was loaded on October 14, 2026, and the file lists the permit as effective.
- No dated event in the 365 days to October 14, 2026.
- It is one of 45,725 discharge permits on the register in Georgia; 40,604 of them (89%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility | LAKE VISTA ESTATES - LOT 41 |
|---|---|
| Permittee | Rackley Construction |
| NPDES ID | GAR352949 |
| Status | Effective |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Construction stormwater |
| Issued | September 23, 2013 |
| Expires | July 31, 2018 |
| Address | GA |
NPDES GAR352949: effluent limits and exceedances
LAKE VISTA ESTATES - LOT 41 (NPDES GAR352949): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES GAR352949: no pollutant row on file.
NPDES GAR352949: inspections, violations and enforcement
NPDES GAR352949 (LAKE VISTA ESTATES - LOT 41): no single-event violation, inspection, formal enforcement action and informal enforcement action on file.
Watch NPDES GAR352949
NPDES GAR352949: one email when its EPA record changes — $99/month.
Permits near NPDES GAR352949
NPDES GAR352949: 0 pollutant rows, 0 dated events; ICIS-NPDES download, loaded October 14, 2026.