PERENNIAL WALK AT LAKE MONROE, PHASE 2 LOT 43-48, Georgia: General permit coverage GAR370098, held by Matthew Cout; Construction stormwater; Effective; issued September 23, 2013, term to July 31, 2018.
Georgia holds 40,604 Construction stormwater coverages of this permit type in EPA’s file; 24 were issued before GAR370098.
Coverages issued nearest GAR370098
- 2013-09-23: CARTER GROVE PLANTATION PHASE 1 SECTION A LOT 1164, Cartersville: GAR370093, held by Meritage Homes of Georgia
- 2013-09-23: VINEYARD PLACE EAST LOT 28, Powder Springs: GAR370094, held by Meritage Homes of GA
- 2013-09-23: PERNNIAL WALK AT LAKE MONROE, PHASE 2, LOTS 39-42, 49-57: GAR370095, held by Matthew Coutu
- 2013-09-23: SEVEN HILLS UNIT N LOT 98, Dallas: GAR370096, held by Rivermont Homes, LLC
- 2013-09-23: SEVEN HILLS UNIT N LOT 97, Dallas: GAR370097, held by Rivermont Homes, LLC
- 2013-09-23: DODSON WOODS COMMUNITY LOT- 186, Union City: GAR370101, held by Century Communities, LLC
- 2013-09-23: TRADITIONS MODEL HOME - TRD035: GAR370105, held by Carey Station Community, LLC
- 2013-09-23: ELLERSLIE PLACE SECTION 5, LOT 521, Ellerslie: GAR370109, held by Ellerslie Development, LLC
- 2013-09-23: STANE BROOK - LOT 83, 84, 80, 81, 82, Jackson: GAR370115, held by Eric Ordorica
- 2013-09-23: GRAYSTONE - LOT 27, Appling: GAR370120, held by IDK Homes
What stands out
- Its term runs 4 years and 311 days, September 23, 2013 to July 31, 2018; the term ended 2,968 days before EPA's file was loaded on September 15, 2026, and the file lists the permit as effective.
- No dated event in the 365 days to September 15, 2026.
- It is one of 45,725 discharge permits on the register in Georgia; 40,604 of them (89%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility | PERENNIAL WALK AT LAKE MONROE, PHASE 2 LOT 43-48 |
|---|---|
| Permittee | Matthew Cout |
| NPDES ID | GAR370098 |
| Status | Effective |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Construction stormwater |
| Issued | September 23, 2013 |
| Expires | July 31, 2018 |
| Address | GA |
NPDES GAR370098: effluent limits and exceedances
PERENNIAL WALK AT LAKE MONROE, PHASE 2 LOT 43-48 (NPDES GAR370098): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES GAR370098: no pollutant row on file.
NPDES GAR370098: inspections, violations and enforcement
NPDES GAR370098 (PERENNIAL WALK AT LAKE MONROE, PHASE 2 LOT 43-48): no single-event violation, inspection, formal enforcement action and informal enforcement action on file.
Watch NPDES GAR370098
NPDES GAR370098: one email when its EPA record changes — $99/month.
Permits near NPDES GAR370098
NPDES GAR370098: 0 pollutant rows, 0 dated events; ICIS-NPDES download, loaded September 15, 2026.