Clean Water Act discharge permit · NPDES GAR3967AB
PLANTERS RIDGE SECTION 3 PHASE 1, 2, AND 3, Perry, GA: NPDES GAR3967AB discharge permit, effluent exceedances, inspections, penalties
- EffectivePermit status
- MinorDischarger class
- 0Pollutants under a numeric limit
- 0Pollutants with an effluent exceedance
- 0Inspections on file
- 0Formal enforcement actions
PLANTERS RIDGE SECTION 3 PHASE 1, 2, AND 3, held by Lennar, holds NPDES permit GAR3967AB. EPA’s file records it issued August 1, 2023 and expiring July 31, 2028. The status and dates are as EPA’s permit file stood when Velarion loaded it (September 15, 2026); EPA’s free Detailed Facility Report on ECHO carries the permit’s current standing.
What the register holds for PLANTERS RIDGE SECTION 3 PHASE 1, 2, AND 3: its NPDES ID, its permit type and status, its dates, its address in Perry, Georgia. EPA’s effluent violation file and its single-event violation file hold no violation for NPDES GAR3967AB.
What stands out
- Its term runs 4 years and 365 days, August 1, 2023 to July 31, 2028.
- No dated event in the 365 days to September 15, 2026.
- It is one of 45,725 discharge permits on the register in Georgia; 40,604 of them (89%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility as filed | PLANTERS RIDGE SECTION 3 PHASE 1, 2, AND 3 |
|---|---|
| Permittee as filed | Lennar |
| NPDES ID | GAR3967AB |
| Permit status | Effective |
| Permit type | Coverage under a general permit |
| Discharger class | Minor discharger |
| Facility type | Not a publicly owned treatment works |
| Program | Construction stormwater |
| Issued | August 1, 2023 |
| Expiration date | July 31, 2028 |
| Address | Perry, GA 31069 |
| Subwatershed | Lower Mossy Creek (HUC 030701040206) |
Cited to the EPA ICIS-NPDES permit file (ECHO download).
Effluent limits and exceedances
- 0Pollutants on file
- 0Under a numeric limit
- 0With a violation of any kind
- 0With an effluent exceedance
EPA’s limits and effluent violation files hold no pollutant row for NPDES GAR3967AB.
Cited to the EPA ICIS-NPDES limits and effluent violations files (ECHO download); up to 60 rows shown, most exceedances first.
Inspections, violations and enforcement
- 0Single-event violations
EPA’s single-event violation file, as loaded, holds no violation for NPDES GAR3967AB.
Inspections
EPA’s inspection file holds no inspection for NPDES GAR3967AB.
Formal enforcement and penalties
0 formal actions, 0 of them with a penalty assessed. Federal and state penalties are separate figures from separate authorities and are shown as each was filed, never added together.
Informal enforcement
EPA’s informal enforcement file holds no action for NPDES GAR3967AB.
Cited to the EPA ICIS-NPDES violation, inspection and enforcement files (ECHO download); up to 50 rows of each shown, newest first.
Watch this permit
One permit holder, $99/month. Watch the register for one permit holder and the places and receiving waters tied to its permits. Choose “One permit holder” and enter this permit’s NPDES ID, GAR3967AB.
Start the watch
- One permit holder — $99/month
- One watershed — $2,990/year
- One state — $4,990/year
- The whole register — $18,000/year
How we handle your data → Privacy
EPA publishes a free Detailed Facility Report for every permit on ECHO: its compliance status quarter by quarter, its inspections, and its enforcement actions and penalties. EPA also sends free notices of new inspections and enforcement actions through ECHO Notify; enter NPDES ID GAR3967AB there.
PLANTERS RIDGE SECTION 3 PHASE 1, 2, AND 3, Perry, Georgia: Coverage under a general permit GAR3967AB, held by Lennar; Construction stormwater; Effective; issued August 1, 2023, term to July 31, 2028.
Georgia holds 40,604 Construction stormwater coverages of this permit type in EPA’s file; 31,933 were issued before GAR3967AB. Lennar holds 9 permits in Georgia.
Other permits held by Lennar
- BAYARD (F.K.A. ARDEN)(F.K.A. DEAN GARDENS), Johns Creek: GAR354264, issued 2013-09-23
- CHARLESTON'S WALK LOT 65, Mcdonough: GAR377273, issued 2013-09-23
- CHARLETSON'S WALK LOT -78, Mcdonough: GAR379341, issued 2013-09-23
- CHARLESTON'S WALK LOT - 71, Mcdonough: GAR380087, issued 2013-09-23
- CHARLESTON'S WALK LOT- 85, Mcdonough: GAR381321, issued 2013-09-23
- CHARLETSON'S WALK LOT- 84, Mcdonough: GAR382063, issued 2013-09-23
- PLANTERS RIDGE SECTION 2 PHASE 1, 2, AND 3, Perry: GAR3967AA, issued 2023-08-01
- PLANTERS RIDGE SECTION 4 PHASE 5 & 6, Kathleen: GAR397428, issued 2023-08-01
Coverages issued nearest GAR3967AB
- 2023-08-01: BARRINGTON PLACE LOT 43, Macon: GAR3967A2, held by Adams Homes
- 2023-08-01: THE RESERVE AT PROVIDENCE, Milton: GAR3967A6, held by Gogolin Industries, LLC
- 2023-08-01: EDGEWATER AT NEW HAMPSTEAD - PHASE 2, Bloomingdale: GAR3967A8, held by Lennar Georgia, LLC
- 2023-08-01: WEATHERFIELD, Flowery Branch: GAR3967A9, held by Taylor Morrison of Georgia, LLC
- 2023-08-01: PLANTERS RIDGE SECTION 2 PHASE 1, 2, AND 3, Perry: GAR3967AA, held by Lennar
- 2023-08-01: NOTTINGHAM EAST, Marietta: GAR3967AC, held by McKinley Construction
- 2023-08-01: NOTTINGHAM WEST, Marietta: GAR3967AD, held by McKinley Construction
- 2023-08-01: CANTON ON MAYFIELD, Alpharetta: GAR3967AE, held by Mayfield Canton Development
- 2023-08-01: HAWKS RIDGE, Cleveland: GAR3967AF, held by Fowler Construction
- 2023-08-01: 326 CAIN CREEK OVERLOOK, Ball Ground: GAR3967B1, held by PAUL NOBLE
PLANTERS RIDGE SECTION 3 PHASE 1, 2, AND 3 among its neighbors
95 discharge permits are in the Lower Mossy Creek subwatershed (HUC 030701040206); GAR3967AB is one.
Other permits in the Lower Mossy Creek subwatershed (HUC 030701040206)
- A NEW SHOPPING CENTER - HWY 247 CONN @ WALKER RD, Byron: GAR18C019, minor, term to 2028-07-31
- ABIGAIL'S LANDING AT THE TIFFANY SECTION 1, Warner Robins: GAR352402, minor, term to 2018-07-31
- ANTHONY URBAN, Fort Valley: GAR18A8C7, minor, term to 2028-07-31
- APEX OF PERRY, Perry: GAR18B424, minor, term to 2028-07-31
- AUTUMN COVE, ROWLAND CIRCLE, BYRON, S/D DEVELOPMENT, Byron: GAR18B9DC, minor, term to 2028-07-31
- BEAR BRANCH PUMP STATION UPGRADES PHASE 1 - FORCE MAIN, Perry: GAR254392, minor, term to 2028-07-31
- BLACKHAWK SUBDIVISION - PHASE 2, Perry: GAR349451, minor, term to 2018-07-31
- BUZZELL PLUMBING, HEATING & AIR INC., Warner Robins: GAR147882, minor, term to 2018-07-31
- CALIBER COLLISION, Warner Robins: GAR18AB01, minor, term to 2025-01-31
- CAR WASH, Warner Robbins: GAR18BB20, minor, term to 2028-07-31
Nearby on the register
- Discharge permits in Perry
- Every permit record in Perry, A to Z
- Discharge permits in Georgia
- Every permit record in Georgia, A to Z
Figures from EPA’s ICIS-NPDES download, loaded September 15, 2026.
What this page shows
Across the 87 storm water construction permits in Perry, 0.0% have a violation recorded against them. PLANTERS RIDGE SECTION 3 PHASE 1, 2, AND 3 is among those, while 49.4% of Perry's permits were issued before it and 95 NPDES permits sit in the Lower Mossy Creek subwatershed.