IPL - M.L. KAPP GENERATING STATION, Clinton, IA: NPDES IA0001759 discharge permit, effluent exceedances, inspections, penalties

IPL - M.L. KAPP GENERATING STATION, Clinton, Iowa: Individual permit IA0001759, held by INTERSTATE POWER & LIGHT COMPANY; Effective; issued April 1, 2013, term to March 31, 2018, by STA.

  • Flow, in conduit or thru treatment plant: 1 limit, 126 violations of any kind, 117 effluent exceedances, latest January 31, 2013, largest 15% over the limit.
  • Temperature, water deg. fahrenheit: 24 limits, 36 violations of any kind, 31 effluent exceedances, latest July 31, 2012, largest 15% over the limit.
  • Solids, total suspended: 12 limits, 72 violations of any kind, 25 effluent exceedances, latest June 30, 2013, largest 730% over the limit.
  • pH: 6 limits, 30 violations of any kind, 6 effluent exceedances, latest November 30, 2006.
  • Chlorine, total residual: 1 limit, 12 violations of any kind, 3 effluent exceedances, latest April 30, 2017, largest 43% over the limit.
  • Iron, total [as Fe]: 0 limits, 26 violations of any kind, 2 effluent exceedances, latest March 31, 2004, largest 374% over the limit.
  • Oil & Grease: 12 limits, 29 violations of any kind, 1 effluent exceedance, latest November 30, 2000, largest 10% over the limit.
  • Copper, total [as Cu]: 0 limits, 26 violations of any kind.
  • Temperature, length of excursion: 1 limit, 19 violations of any kind.
  • Chlorination duration: 1 limit, 1 violation of any kind.

Other permits held by INTERSTATE POWER & LIGHT COMPANY

IPL - M.L. KAPP GENERATING STATION among its neighbors

2 discharge permits are in the Mill Creek subwatershed (HUC 070801010202); IA0001759 is one. Its county: 28, 4 major; IA0001759 is minor permit.

Other permits in the Mill Creek subwatershed (HUC 070801010202)

What stands out

  • Its term runs 4 years and 364 days, April 1, 2013 to March 31, 2018; the term ended 3,090 days before EPA's file was loaded on September 15, 2026, and the file lists the permit as effective.
  • No dated event in the 365 days to September 15, 2026.
  • 7 of its 10 pollutants on file have an effluent exceedance (70%); 8 are under a numeric limit; the largest exceedance is Solids, total suspended at 730% over its limit.
  • It is one of 1,610 discharge permits on the register in Iowa; the file names no program for it, and it is a minor discharger.

Identity

FacilityIPL - M.L. KAPP GENERATING STATION
PermitteeINTERSTATE POWER & LIGHT COMPANY
NPDES IDIA0001759
StatusEffective
TypeIndividual permit
ClassMinor
Facility typeNon-POTW
IssuedApril 1, 2013
ExpiresMarch 31, 2018
AgencySTA
AddressClinton, IA 52732
SubwatershedMill Creek (HUC 070801010202)
Other EPA IDs (FRS)RCRA handler IAD000766246

NPDES IA0001759: effluent limits and exceedances

IPL - M.L. KAPP GENERATING STATION (NPDES IA0001759): 10 pollutants on file, 8 limited; 10 with a violation of any kind, 7 with an exceedance.

How exceedances are counted.

PollutantLimitsViolationsExceedancesLatestLargest, as filed
Flow, in conduit or thru treatment plant1126117January 31, 201315% over the limit
Temperature, water deg. fahrenheit243631July 31, 201215% over the limit
Solids, total suspended127225June 30, 2013730% over the limit
pH6306November 30, 2006
Chlorine, total residual1123April 30, 201743% over the limit
Iron, total [as Fe]0262March 31, 2004374% over the limit
Oil & Grease12291November 30, 200010% over the limit
Copper, total [as Cu]0260
Temperature, length of excursion1190
Chlorination duration110

NPDES IA0001759: inspections, violations and enforcement

NPDES IA0001759 (IPL - M.L. KAPP GENERATING STATION): no single-event violation, inspection, formal enforcement action and informal enforcement action on file.

Watch NPDES IA0001759

NPDES IA0001759: one email when its EPA record changes — $99/month.

Billing

Privacy

Permits near NPDES IA0001759

NPDES IA0001759: 10 pollutant rows, 0 dated events; ICIS-NPDES download, loaded September 15, 2026.