NPDES IDR05J119 · Clean Water Act
RUSSEL ROCK PIT, White Bird, ID: NPDES IDR05J119 discharge permit, effluent exceedances, inspections, penalties
RUSSEL ROCK PIT, White Bird, Idaho: General permit coverage IDR05J119, held by Atlas Sand and Rock, Inc.; Industrial stormwater; Administratively continued; issued January 15, 2021, term to February 28, 2026; discharges to Salmon River.
3 of the 5 pollutants listed for NPDES IDR05J119 have no violation or effluent exceedance.
- Solids, total suspended: 1 limit, 1 violation of any kind.
- Nitrite Plus Nitrate Total: 1 limit, 1 violation of any kind.
- pH: 2 limits.
- Temperature, water deg. centigrade: 1 limit.
- Mercury, total recoverable: 1 limit.
- March 2, 2026: Notice of Noncompliance Issued (State).
- March 2, 2026: No Further Action (State).
- February 11, 2026: Notice of Noncompliance Issued (State).
- February 7, 2026: Monitoring Violations - Invalid/Unrepresentative Sample (ST6).
- February 7, 2026: WW Storm Water Non-Construction - Failure to Conduct Inspections (ST6).
- December 10, 2025: WW Storm Water Non-Construction - Noncompliance with section 308 Information Request (ST6).
- November 7, 2025: WW Storm Water Non-Construction - Noncompliance with section 308 Information Request (ST6).
- August 26, 2025: WW Storm Water Non-Construction - Failure to develop any or adequate SWPPP/SWMP (ST6).
- August 26, 2025: WW Storm Water Non-Construction - Failure to properly operate and maintain BMPs (ST6).
Idaho holds 245 Industrial stormwater coverages of this permit type in EPA’s file; 32 were issued before IDR05J119.
Coverages issued nearest IDR05J119
- 2018-03-03: RASMUSSEN VALLEY, Soda Springs: IDR053257, held by Itafos Conda LLC
- 2018-10-19: PEAK SAND AND GRAVEL - FIGHTING CREEK QUARRY, Coeur D'Alene: IDR05IA00, held by Peak Sand and Gravel, Inc.
- 2021-01-15: MCKINLEY MINE, INC, Lucile: IDR05J10Z, held by Eric Klepfer
- 2021-01-15: MONDELEZ GLOBAL LLC, Kimberly: IDR05J115, held by Mondelez Global LLC
- 2021-01-15: CHOBANI, LLC., Twin Falls: IDR05J116, held by Chobani, LLC.
- 2021-01-15: BELLEVUE SOURCE, Bellevue: IDR05J11C, held by Premier Aggregates, LLC
- 2021-01-15: IMC PAYNE PIT, Middleton: IDR05J11J, held by Staker Parson Companies
- 2021-01-15: GLC ROSE PIT, Blackfoot: IDR05J11M, held by Gale Lim Construction LLC
- 2021-01-15: BUNKER HILL MINE, Kellogg: IDR05J11N, held by Silver Valley Metals Corp.
- 2021-01-15: NORTHWEST BUILDING SYSTEMS, Boise: IDR05J11W, held by Northwest Building Systems
RUSSEL ROCK PIT among its neighbors
2 discharge permits are in the McKinzie Creek-Salmon River subwatershed (HUC 170602090501); IDR05J119 is one.
Other permits in the McKinzie Creek-Salmon River subwatershed (HUC 170602090501)
- 20570, US-95, 210 SLIDE TO WHITEBIRD BR, White Bird: IDR10L0G3
What stands out
- Its term runs 5 years and 44 days, January 15, 2021 to February 28, 2026; the term ended 199 days before EPA's file was loaded on September 15, 2026, and the file lists the permit as administratively continued.
- Its newest dated event on file is an informal enforcement action on March 2, 2026, 197 days before EPA's file was loaded.
- In the 365 days to September 15, 2026, it was dated 4 single-event violations, 3 informal enforcement actions.
- EPA's file dates 9 events for it, from 2025 to 2026; the busiest year is 2026 with 5.
- It is one of 4,607 discharge permits on the register in Idaho; 245 of them (5.3%) are in its program, Industrial stormwater, and it is a minor discharger.
Identity
| Facility | RUSSEL ROCK PIT |
|---|---|
| Permittee | Atlas Sand and Rock, Inc. |
| NPDES ID | IDR05J119 |
| Status | Administratively continued |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Industrial stormwater |
| Issued | January 15, 2021 |
| Expires | February 28, 2026 |
| Address | White Bird, ID 83554 |
| Receiving water | Salmon River |
| Receiving water impaired | 303(D) Listed |
| Subwatershed | McKinzie Creek-Salmon River (HUC 170602090501) |
NPDES IDR05J119: effluent limits and exceedances
RUSSEL ROCK PIT (NPDES IDR05J119): 5 pollutants on file, 5 limited; 2 with a violation of any kind, 0 with an exceedance.
| Pollutant | Limits | Violations | Exceedances | Latest | Largest, as filed |
|---|---|---|---|---|---|
| Solids, total suspended | 1 | 1 | 0 | ||
| Nitrite Plus Nitrate Total | 1 | 1 | 0 | ||
| pH | 2 | 0 | 0 | ||
| Temperature, water deg. centigrade | 1 | 0 | 0 | ||
| Mercury, total recoverable | 1 | 0 | 0 |
NPDES IDR05J119: inspections, violations and enforcement
NPDES IDR05J119: 6 single-event violations
| Date | What EPA recorded | Agency |
|---|---|---|
| February 7, 2026 | Monitoring Violations - Invalid/Unrepresentative Sample | ST6 |
| February 7, 2026 | WW Storm Water Non-Construction - Failure to Conduct Inspections | ST6 |
| December 10, 2025 | WW Storm Water Non-Construction - Noncompliance with section 308 Information Request | ST6 |
| November 7, 2025 | WW Storm Water Non-Construction - Noncompliance with section 308 Information Request | ST6 |
| August 26, 2025 | WW Storm Water Non-Construction - Failure to develop any or adequate SWPPP/SWMP | ST6 |
| August 26, 2025 | WW Storm Water Non-Construction - Failure to properly operate and maintain BMPs | ST6 |
NPDES IDR05J119: 3 informal enforcement actions
| Date | What EPA recorded | Agency |
|---|---|---|
| March 2, 2026 | Notice of Noncompliance Issued | State |
| March 2, 2026 | No Further Action | State |
| February 11, 2026 | Notice of Noncompliance Issued | State |
NPDES IDR05J119 (RUSSEL ROCK PIT): no inspection and formal enforcement action on file.
Watch NPDES IDR05J119
NPDES IDR05J119: one email when its EPA record changes — $99/month.
Permits near NPDES IDR05J119
NPDES IDR05J119: 5 pollutant rows, 9 dated events; ICIS-NPDES download, loaded September 15, 2026.