NPDES IDR10C21W · Clean Water Act
CLEAR CREEK SUBSTATION, Cascade, ID: NPDES IDR10C21W discharge permit, effluent exceedances, inspections, penalties
CLEAR CREEK SUBSTATION, Cascade, Idaho: General permit coverage IDR10C21W, held by Idaho Power Company; Construction stormwater; Effective; issued January 10, 2022, term to February 9, 2027; discharges to Clear Creek.
Idaho holds 3,630 Construction stormwater coverages of this permit type in EPA’s file; 576 were issued before IDR10C21W. Idaho Power Company holds 48 permits in Idaho.
Other permits held by Idaho Power Company
- LANSING SUBSTATION, Middleton: IDR1000L4
- FILER SUBSTATION, Filer: IDR1001QK
- LINE 440 REBUILD, Picabo: IDR10020Y
- UPPER MALAD UNDERGROUND POWERLINE, Hagerman: IDR10027Z
- BEACON LIGHT SUBSTATION, Eagle: IDR100280
- WARM LAKE UNDERGROUND, Yellow Pine: IDR1002I4
- MIDPOINT STAGING YARD, Jerome: IDR1002KF
- EMMETT YARD DRAINAGE IMPROVEMENTS, Emmett: IDR1002UP
- LINE 172 REBUILD, Jerome: IDR1002WJ, issued 2021-01-26
- CALDWELL ROADS, Caldwell: IDR10033N, issued 2021-04-26
Coverages issued nearest IDR10C21W
- 2022-01-10: FOUNTAIN PARK SUBDIVISION NO 1 (CHALLENGER), Eagle: IDR10C21Q, held by Challenger Development, Inc.
- 2022-01-10: THUNDERBOLT LANDING SUBDIVISION NO 3 (CHALLENGER), Mountain Home: IDR10C21R, held by Challenger Development, Inc.
- 2022-01-10: MCDERMOTT TRUNK SEWER PACKAGE A, Meridian: IDR10C21S, held by Granite Excavation
- 2022-01-10: LONGBOW SUBDIVISION, Star: IDR10C21T, held by Longbow Estates, LLC
- 2022-01-10: QUARRY EAST PHASE 1 AND MASS GRADING (M3), Caldwell: IDR10C21V, held by M3 Companies, LLC
- 2022-01-10: HIGHLINE INDUSTRIAL PARK SUBDIVISION (CHALLENGER), Caldwell: IDR10C21X, held by Challenger Development, Inc.
- 2022-01-10: CANVASBACK SUBDIVISION NO 2 (CHALLENGER), Star: IDR10C21Y, held by Challenger Development, Inc.
- 2022-01-10: BLUE YONDER SUBDIVISION NO 2 (CHALLENGER), Mountain Home: IDR10C21Z, held by Challenger Development, Inc.
- 2022-01-10: PEREGRINE ESTATES SUBDIVISION NO. 7 (CHALLENGER), Nampa: IDR10C220, held by Challenger Development, Inc.
- 2022-01-10: VALENCIA VILLAGE SUBDIVISION NO 1 (CHALLENGER), Caldwell: IDR10C221, held by Challenger Development, Inc.
CLEAR CREEK SUBSTATION among its neighbors
1 discharge permits are in the Lower Clear Creek subwatershed (HUC 170501230506); IDR10C21W is one. Its county: 78, 0 major; IDR10C21W is minor permit.
What stands out
- Its term runs 5 years and 30 days, January 10, 2022 to February 9, 2027.
- No dated event in the 365 days to September 15, 2026.
- It is one of 4,607 discharge permits on the register in Idaho; 3,631 of them (79%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility | CLEAR CREEK SUBSTATION |
|---|---|
| Permittee | Idaho Power Company |
| NPDES ID | IDR10C21W |
| Status | Effective |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Construction stormwater |
| Issued | January 10, 2022 |
| Expires | February 9, 2027 |
| Address | Cascade, ID 83611 |
| Receiving water | Clear Creek |
| Subwatershed | Lower Clear Creek (HUC 170501230506) |
NPDES IDR10C21W: effluent limits and exceedances
CLEAR CREEK SUBSTATION (NPDES IDR10C21W): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES IDR10C21W: no pollutant row on file.
NPDES IDR10C21W: inspections, violations and enforcement
NPDES IDR10C21W (CLEAR CREEK SUBSTATION): no single-event violation, inspection, formal enforcement action and informal enforcement action on file.
Watch NPDES IDR10C21W
NPDES IDR10C21W: one email when its EPA record changes — $99/month.
Permits near NPDES IDR10C21W
NPDES IDR10C21W: 0 pollutant rows, 0 dated events; ICIS-NPDES download, loaded September 15, 2026.