MAIN LINE STATION REST AREA (I-57) STP, Buckley, IL: NPDES ILG551072 discharge permit, effluent exceedances, inspections, penalties

MAIN LINE STATION REST AREA (I-57) STP, Buckley, Illinois: General permit coverage ILG551072, held by ILLINOIS DEPT OF TRANSPORTATION; Administratively continued; issued April 28, 2014, term to June 30, 2018; discharges to SPRING CREEK.

  • Solids, total suspended: 5 limits, 81 violations of any kind, 41 effluent exceedances, latest March 31, 2023, largest 197% over the limit.
  • BOD, carbonaceous [5 day, 20 C]: 4 limits, 54 violations of any kind, 16 effluent exceedances, latest September 30, 2021, largest 340% over the limit.
  • Oxygen, dissolved [DO]: 1 limit, 12 violations of any kind, 11 effluent exceedances, latest August 31, 2023, largest 95% over the limit.
  • pH: 2 limits, 21 violations of any kind, 3 effluent exceedances, latest May 31, 2022.
  • Flow, in conduit or thru treatment plant: 4 limits, 34 violations of any kind.
  • Chlorine, total residual: 1 limit, 10 violations of any kind.
  • BOD, 5-day, 20 deg. C: 1 limit, 8 violations of any kind.
  • Nitrogen, ammonia total [as N]: 1 limit, 1 violation of any kind.
  • Coliform, fecal general: 1 limit, 1 violation of any kind.

Other permits held by ILLINOIS DEPT OF TRANSPORTATION

MAIN LINE STATION REST AREA (I-57) STP among its neighbors

13 discharge permits are in the Headwaters Spring Creek subwatershed (HUC 071200020805); ILG551072 is one. Its county: 36, 1 major; ILG551072 is minor permit.

Other permits in the Headwaters Spring Creek subwatershed (HUC 071200020805)

What stands out

  • Its term runs 4 years and 63 days, April 28, 2014 to June 30, 2018; the term ended 3,028 days before EPA's file was loaded on October 14, 2026, and the file lists the permit as administratively continued.
  • No dated event in the 365 days to October 14, 2026.
  • 4 of its 9 pollutants on file have an effluent exceedance (44%); 9 are under a numeric limit; the largest exceedance is BOD, carbonaceous [5 day, 20 C] at 340% over its limit.
  • It is one of 10,926 discharge permits on the register in Illinois; the file names no program for it, and it is a minor discharger.

Identity

FacilityMAIN LINE STATION REST AREA (I-57) STP
PermitteeILLINOIS DEPT OF TRANSPORTATION
NPDES IDILG551072
StatusAdministratively continued
TypeGeneral permit coverage
ClassMinor
Facility typeNon-POTW
IssuedApril 28, 2014
ExpiresJune 30, 2018
AddressBuckley, IL 60918
Receiving waterSPRING CREEK
SubwatershedHeadwaters Spring Creek (HUC 071200020805)
SIC9621 – Regulation, Administration Of Transportation

NPDES ILG551072: effluent limits and exceedances

MAIN LINE STATION REST AREA (I-57) STP (NPDES ILG551072): 9 pollutants on file, 9 limited; 9 with a violation of any kind, 4 with an exceedance.

How exceedances are counted.

PollutantLimitsViolationsExceedancesLatestLargest, as filed
Solids, total suspended58141March 31, 2023197% over the limit
BOD, carbonaceous [5 day, 20 C]45416September 30, 2021340% over the limit
Oxygen, dissolved [DO]11211August 31, 202395% over the limit
pH2213May 31, 2022
Flow, in conduit or thru treatment plant4340
Chlorine, total residual1100
BOD, 5-day, 20 deg. C180
Nitrogen, ammonia total [as N]110
Coliform, fecal general110

NPDES ILG551072: inspections, violations and enforcement

NPDES ILG551072 (MAIN LINE STATION REST AREA (I-57) STP): no single-event violation, inspection, formal enforcement action and informal enforcement action on file.

Watch NPDES ILG551072

NPDES ILG551072: one email when its EPA record changes — $99/month.

Billing

Privacy

Permits near NPDES ILG551072

NPDES ILG551072: 9 pollutant rows, 0 dated events; ICIS-NPDES download, loaded October 14, 2026.