NPDES ILR10ZEVO · Clean Water Act
KEOKUK TRANSMISSION LINE RELIABILITY PROJECT, Hamilton, IL: NPDES ILR10ZEVO discharge permit, effluent exceedances, inspections, penalties
KEOKUK TRANSMISSION LINE RELIABILITY PROJECT, Hamilton, Illinois: General permit coverage ILR10ZEVO, held by TBD; Construction stormwater; Effective; issued November 27, 2024, term to August 31, 2028, by IEPA.
Illinois holds 5,215 Construction stormwater coverages of this permit type in EPA’s file; 2,332 were issued before ILR10ZEVO. TBD holds 547 permits in Illinois.
Other permits held by TBD
- W.O. 192939 AND W.O. 192924 COAL CITY RD. AND NOVY RD., Uninc. Braidwood: ILR10BG14, issued 2024-03-19
- SITE IMPROVEMENTS FOR DUCKEE'S TRAVEL CENTER, Hodgkins: ILR10BN41, issued 2024-01-04
- POPEYES LOUISIANA KITCHEN ZION, IL, Zion: ILR10ZAE9, issued 2024-02-26
- WORKFORCE SUSTAINABILITY CENTER ICC, East Peoria: ILR10ZALO, issued 2023-11-01
- THORNTONS ST. CHARLES, St. Charles: ILR10ZB54, issued 2024-02-26
- WHEATON RETAIL, Wheaton: ILR10ZB82, issued 2023-09-28
- LASALLE, IL SOUTHERN TIRE MART AT PILOT FLYING J, Lasalle: ILR10ZBDK, issued 2023-08-30
- TRUCK REPAIR FACILITY, Crestwood: ILR10ZBH3, issued 2023-10-02
- WEST APRON EXPANSION, Peoria: ILR10ZBJP, issued 2023-08-09
- CIRCLE K - OAK BROOK, Oak Brook: ILR10ZBJQ, issued 2024-02-26
Coverages issued nearest ILR10ZEVO
- 2024-11-26: DECATUR WEST CAMPUS: STORMWATER DETENTION POND VOLUME AND PH ADJUSTMENT, Decatur: ILR10ZEUK, held by TBD
- 2024-11-26: KEWANEE GROW FACILITY, Kewanee: ILR10ZEUR, held by To Be Determined
- 2024-11-26: PROPOSED KIDDIE ACADEMY DEVELOPMENT, Vernon Hills: ILR10ZEWL, held by TBD
- 2024-11-26: PITTSFIELD SAWMILL DEVELOPMENT, Pittsfield: ILR10ZEWT, held by Legends Holdings, LLC
- 2024-11-26: NVA TRUCKING FACILITY EXPANSION, Crystal Lake: ILR10ZEX4, held by NVA Properties of IL LLC
- 2024-11-27: 4743: ELGIN O'HARE WESTERN ACCESS FROM I-294 TO FRANKLIN AVENUE, Franklin Avenue: ILR10ZEVP, held by Plote Construction Inc.
- 2024-11-27: AAA RENTS MILAN STORAGE, Milan: ILR10ZEVW, held by AAA Rents
- 2024-11-27: THE WILDFLOWER FARM, Monee: ILR10ZEX6, held by Toepper Enterprises, LLC
- 2024-11-27: ESTATES AT ARCADIA, Palatine: ILR10ZEXG, held by GWR Enterprises, Inc
- 2024-11-28: LODA FERTILIZER BUILDING, Loda: ILR10ZEVR, held by Stueve Construction
KEOKUK TRANSMISSION LINE RELIABILITY PROJECT among its neighbors
6 discharge permits are in the Cedar Glen Creek-Mississippi River subwatershed (HUC 070801041806); ILR10ZEVO is one.
Other permits in the Cedar Glen Creek-Mississippi River subwatershed (HUC 070801041806)
- CITY OF KEOKUK, Keokuk: IAL042609, minor, term to 2025-12-31
- KEOKUK CITY OF STP, Keokuk: IA0042609, major, term to 2023-08-31
- KEOKUK ENERGY CENTER, Keokuk: IA0033600, minor, term to 2021-06-30
- ROQUETTE AMERICA, INC., Keokuk: IA0000256, major, term to 2023-06-30
- TP1587 LINE REBUILD - NORTH SECTION, Hamilton: ILR10ZFAP, minor, term to 2028-08-31
What stands out
- Its term runs 3 years and 278 days, November 27, 2024 to August 31, 2028.
- No dated event in the 365 days to September 15, 2026.
- It is one of 10,926 discharge permits on the register in Illinois; 5,215 of them (48%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility | KEOKUK TRANSMISSION LINE RELIABILITY PROJECT |
|---|---|
| Permittee | TBD |
| NPDES ID | ILR10ZEVO |
| Status | Effective |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Construction stormwater |
| Issued | November 27, 2024 |
| Expires | August 31, 2028 |
| Agency | IEPA |
| Address | Hamilton, IL 62341 |
| Subwatershed | Cedar Glen Creek-Mississippi River (HUC 070801041806) |
NPDES ILR10ZEVO: effluent limits and exceedances
KEOKUK TRANSMISSION LINE RELIABILITY PROJECT (NPDES ILR10ZEVO): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES ILR10ZEVO: no pollutant row on file.
NPDES ILR10ZEVO: inspections, violations and enforcement
NPDES ILR10ZEVO (KEOKUK TRANSMISSION LINE RELIABILITY PROJECT): no single-event violation, inspection, formal enforcement action and informal enforcement action on file.
Watch NPDES ILR10ZEVO