NPDES ILR10ZFLU · Clean Water Act
GRAND OAKS - PHASE 2, Morris, IL: NPDES ILR10ZFLU discharge permit, effluent exceedances, inspections, penalties
GRAND OAKS - PHASE 2, Morris, Illinois: General permit coverage ILR10ZFLU, held by Brandon Road Properties LLC; Construction stormwater; Effective; issued November 12, 2025, term to August 31, 2028, by IEPA.
Illinois holds 5,215 Construction stormwater coverages of this permit type in EPA’s file; 3,813 were issued before ILR10ZFLU.
Coverages issued nearest ILR10ZFLU
- 2025-11-09: MISSISSIPPI RIVER TO ROCK RIVER TRAIL - PHASE II, Moline: ILR10ZGAA, held by TBD
- 2025-11-09: LANDMARK RECREATION CENTER, Peoria: ILR10ZGAB, held by Landmark Recreation Center
- 2025-11-09: TWO BLUES SOLAR SITE COMMUNITY SOLAR, Pinckneyville: ILR10ZGAD, held by Knobelsdorff Energy, LLC
- 2025-11-09: SNAPDRAGON SOLAR, LLC, Swanwick: ILR10ZGAE, held by Knobelsdorff Energy, LLC
- 2025-11-10: DIAMOND STORAGE, Diamond: ILR10ZGB0, held by Airy's Inc.
- 2025-11-12: MARBLEHEAD N TRANSMISSION LINE REBUILD PROJECT, Quincy: ILR10ZGAG, held by TBD
- 2025-11-12: SOUTH QUINCY TRANSMISSION LINE REBUILD PROJECT, Quincy: ILR10ZGAH, held by TBD
- 2025-11-12: ST. ANTHONY TRANSMISSION LINE REBUILD PROJECT, Quincy: ILR10ZGAI, held by TBD
- 2025-11-12: SHELL STATION, Pontiac: ILR10ZGAJ, held by Heidner Properties
- 2025-11-12: TPE IL MH459, LLC, Woodstock: ILR10ZGAK, held by Knobelsdorff Energy, LLC
GRAND OAKS - PHASE 2 among its neighbors
3 discharge permits are in the Nettle Creek subwatershed (HUC 071200050602); ILR10ZFLU is one.
Other permits in the Nettle Creek subwatershed (HUC 071200050602)
- ILLINOIS AMERICAN WATER - NETTLE CREEK, Morris: ILG551082, minor, term to 2018-06-30
- NARVICK HARDWARE, Morris: ILR10ZEXJ, minor, term to 2028-08-31
What stands out
- Its term runs 2 years and 293 days, November 12, 2025 to August 31, 2028.
- No dated event in the 365 days to September 15, 2026.
- It is one of 10,926 discharge permits on the register in Illinois; 5,215 of them (48%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility | GRAND OAKS - PHASE 2 |
|---|---|
| Permittee | Brandon Road Properties LLC |
| NPDES ID | ILR10ZFLU |
| Status | Effective |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Construction stormwater |
| Issued | November 12, 2025 |
| Expires | August 31, 2028 |
| Agency | IEPA |
| Address | Morris, IL 60450 |
| Subwatershed | Nettle Creek (HUC 071200050602) |
NPDES ILR10ZFLU: effluent limits and exceedances
GRAND OAKS - PHASE 2 (NPDES ILR10ZFLU): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES ILR10ZFLU: no pollutant row on file.
NPDES ILR10ZFLU: inspections, violations and enforcement
NPDES ILR10ZFLU (GRAND OAKS - PHASE 2): no single-event violation, inspection, formal enforcement action and informal enforcement action on file.
Watch NPDES ILR10ZFLU
NPDES ILR10ZFLU: one email when its EPA record changes — $99/month.
Permits near NPDES ILR10ZFLU
NPDES ILR10ZFLU: 0 pollutant rows, 0 dated events; ICIS-NPDES download, loaded September 15, 2026.