NPDES ILR10ZG9R · Clean Water Act
NEW PARKING LOT, Quincy, IL: NPDES ILR10ZG9R discharge permit, effluent exceedances, inspections, penalties
NEW PARKING LOT, Quincy, Illinois: General permit coverage ILR10ZG9R, held by Eric Green Construction; Construction stormwater; Effective; issued November 6, 2025, term to August 31, 2028, by IEPA.
Illinois holds 5,215 Construction stormwater coverages of this permit type in EPA’s file; 3,794 were issued before ILR10ZG9R.
Coverages issued nearest ILR10ZG9R
- 2025-11-05: IL SOLAR THOROMAN PROJECT1, Clayton: ILR10ZG9J, held by Knobelsdorff Energy, LLC
- 2025-11-05: TPE IL KA335, LLC, Grant Park: ILR10ZG9M, held by Knobelsdorff Energy, LLC
- 2025-11-05: CITY OF OAKLAND LAGOON IMPROVEMENTS, Oakland: ILR10ZG9N, held by B&T Drainage, Inc.
- 2025-11-05: IPAVA TRANSMISSION LINE REBUILD PROJECT, Ipava: ILR10ZG9O, held by TBD
- 2025-11-05: LOCKPORT GAS STATION, Lockport: ILR10ZG9P, held by DW Bruinius Construction, LLC.
- 2025-11-06: MOORE CEMETERY ROAD BRIDGE REPLACEMENT, Carlinville: ILR10ZG9S, held by C-Hill Civil Contractors
- 2025-11-06: BROADWAY RECONSTRUCTION PROJECT, Harvey: ILR10ZG9U, held by City of Harvey
- 2025-11-06: CONTRACT 93828 HAGAMAN BRIDGE REPLACEMENT, Hagaman: ILR10ZG9V, held by C-Hill Civil Contractors
- 2025-11-06: CINCINNATI CSG 2 LLC, Pekin: ILR10ZG9W, held by Faith Technologies, Inc
- 2025-11-07: VENICE HOME REVITALIZATION, Venice: ILR10ZFUI, held by Impact Strategies
NEW PARKING LOT among its neighbors
30 discharge permits are in the Curtis Creek-Mississippi River subwatershed (HUC 071100011006); ILR10ZG9R is one.
Other permits in the Curtis Creek-Mississippi River subwatershed (HUC 071100011006)
- ADAMS 1A SOLAR, Quincy: ILR10ZDRO, minor, term to 2028-08-31
- ADAMS 1B SOLAR, Quincy: ILR10ZDRN, minor, term to 2028-08-31
- ADM ALLIANCE NUTRITION, Quincy: ILR005515, minor, term to 2008-06-01
- ALEXANDRIA HEIGHTS SUBDIVISION, Quincy: ILR10ZCS2, minor, term to 2028-08-31
- ARCHER DANIELS MIDLAND, Quincy: IL0003590, minor, term to 2019-02-28
- ARCHER DANIELS MIDLAND, Quincy: IL0078255, minor, term to 2022-07-31
- AYERCO #25, Taylor: MOG940247, minor, term to 2027-08-31
- BNSF - WEST QUINCY YARD, West Quincy: MOR80C622, minor, term to 2022-11-30
- CODES TAYLOR, Taylor: MORA27610, minor, term to 2027-02-07
- COLTEC IND. QUINCY COMP. DIV., Quincy: ILR000259, minor, term to 2008-06-01
What stands out
- Its term runs 2 years and 299 days, November 6, 2025 to August 31, 2028.
- No dated event in the 365 days to September 15, 2026.
- It is one of 10,926 discharge permits on the register in Illinois; 5,215 of them (48%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility | NEW PARKING LOT |
|---|---|
| Permittee | Eric Green Construction |
| NPDES ID | ILR10ZG9R |
| Status | Effective |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Construction stormwater |
| Issued | November 6, 2025 |
| Expires | August 31, 2028 |
| Agency | IEPA |
| Address | Quincy, IL 62305 |
| Subwatershed | Curtis Creek-Mississippi River (HUC 071100011006) |
NPDES ILR10ZG9R: effluent limits and exceedances
NEW PARKING LOT (NPDES ILR10ZG9R): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES ILR10ZG9R: no pollutant row on file.
NPDES ILR10ZG9R: inspections, violations and enforcement
NPDES ILR10ZG9R (NEW PARKING LOT): no single-event violation, inspection, formal enforcement action and informal enforcement action on file.
Watch NPDES ILR10ZG9R
NPDES ILR10ZG9R: one email when its EPA record changes — $99/month.
Permits near NPDES ILR10ZG9R
NPDES ILR10ZG9R: 0 pollutant rows, 0 dated events; ICIS-NPDES download, loaded September 15, 2026.