NPDES INRA14055 · Clean Water Act
HERITAGE FALLS SUBDIVISION PHASE 3, Lowell, IN: NPDES INRA14055 discharge permit, effluent exceedances, inspections, penalties
HERITAGE FALLS SUBDIVISION PHASE 3, Lowell, Indiana: General permit coverage INRA14055, held by Peter Manhard; Construction stormwater; Effective; issued June 12, 2024, term to June 11, 2029, by State.
Indiana holds 7,813 Construction stormwater coverages of this permit type in EPA’s file; 3,497 were issued before INRA14055.
Coverages issued nearest INRA14055
- 2024-06-11: THE APPROACH, Westfield: INRA14044, held by Rohin Singh
- 2024-06-11: MISSION FIRST, Elberfeld: INRA14048, held by Danny Barr
- 2024-06-12: BROWNSBURG HIGH SCHOOL ROARK STADIUM REDEVELOPMENT, Brownsburg: INRA14050, held by Shane Hacker
- 2024-06-12: POPEYES GOSHEN, Goshen: INRA14051, held by Aby Mohammed
- 2024-06-12: TPS HOTEL, Hammond: INRA14053, held by Nash Patel
- 2024-06-13: WHITELAND HIGH SCHOOL, Whiteland: INRA14056, held by Sam Arnes
- 2024-06-13: WEIHE CONSTRUCTION, Pendleton: INRA14057, held by Alan Small
- 2024-06-13: WILLIAMS - HOMESTEAD RD & US-24, Fort Wayne: INRA14059, held by Mike Williams
- 2024-06-14: ESTES EXPRESS LINES KOKOMO, Kokomo: INRA13951, held by Michael Gilbert
- 2024-06-14: FIREFLY RIDGE RE SD, Lafayette: INRA14027, held by Robert Smeltz
HERITAGE FALLS SUBDIVISION PHASE 3 among its neighbors
47 discharge permits are in the Cedar Creek subwatershed (HUC 071200011306); INRA14055 is one.
Other permits in the Cedar Creek subwatershed (HUC 071200011306)
- 141ST AVE PARTNERS STORAGE, Cedar Lake: INRA11798, minor, term to 2028-05-15
- AMG RESOURCES CORPORATION, Gary: INRM02974, minor, term to 2028-08-03
- BEACON POINTE UNIT 5, Cedar Lake: INRA06129, minor, term to 2025-09-08
- BOULDER RIDGE, Lowell: INRA17689, minor, term to 2031-03-03
- BUCKHILL ESTATES WWTP, Crown Point: IN0058548, minor, term to 2025-11-30
- CEDAR LAKE 2022 ROADWAY IMPROVEMENTS (PARRISH, VERMILLION/HILLTOP & HIGHLAND SUB, Cedar Lake: INRA09487, minor, term to 2027-04-10
- CEDAR LAKE PUBLIC SAFETY CENTER, Cedar Lake: INRA11781, minor, term to 2028-05-11
- CEDAR LAKE RESTORATION SEDIMENT DEWATERING FACILITY, Lowell: INRA09206, minor, term to 2027-02-27
- CEDAR LAKE STORAGE SITE, Cedar Lake: INRA08631, minor, term to 2026-10-28
- CENTENNIAL TOWNHOMES, Cedar Lake: INRA17490, minor, term to 2031-01-26
What stands out
- Its term runs 4 years and 364 days, June 12, 2024 to June 11, 2029.
- No dated event in the 365 days to September 15, 2026.
- It is one of 13,164 discharge permits on the register in Indiana; 9,355 of them (71%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility | HERITAGE FALLS SUBDIVISION PHASE 3 |
|---|---|
| Permittee | Peter Manhard |
| NPDES ID | INRA14055 |
| Status | Effective |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Construction stormwater |
| Issued | June 12, 2024 |
| Expires | June 11, 2029 |
| Agency | State |
| Address | Lowell, IN 46356 |
| Subwatershed | Cedar Creek (HUC 071200011306) |
NPDES INRA14055: effluent limits and exceedances
HERITAGE FALLS SUBDIVISION PHASE 3 (NPDES INRA14055): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES INRA14055: no pollutant row on file.
NPDES INRA14055: inspections, violations and enforcement
NPDES INRA14055 (HERITAGE FALLS SUBDIVISION PHASE 3): no single-event violation, inspection, formal enforcement action and informal enforcement action on file.
Watch NPDES INRA14055
NPDES INRA14055: one email when its EPA record changes — $99/month.
Permits near NPDES INRA14055
NPDES INRA14055: 0 pollutant rows, 0 dated events; ICIS-NPDES download, loaded September 15, 2026.