Clean Water Act discharge permit · NPDES INRA14873

STONE MILL PHASE ONE, Lowell, IN: NPDES INRA14873 discharge permit, effluent exceedances, inspections, penalties

STONE MILL PHASE ONE, held by John Carroll, holds NPDES permit INRA14873. EPA’s file records it issued November 6, 2024 and expiring November 5, 2029. The status and dates are as EPA’s permit file stood when Velarion loaded it (September 15, 2026); EPA’s free Detailed Facility Report on ECHO carries the permit’s current standing.

What the register holds for STONE MILL PHASE ONE: its NPDES ID, its permit type and status, its dates, its address in Lowell, Indiana. EPA’s effluent violation file and its single-event violation file hold no violation for NPDES INRA14873.

What stands out

  • Its term runs 4 years and 364 days, November 6, 2024 to November 5, 2029.
  • No dated event in the 365 days to September 15, 2026.
  • It is one of 13,164 discharge permits on the register in Indiana; 9,355 of them (71%) are in its program, Construction stormwater, and it is a minor discharger.

Identity

Facility as filedSTONE MILL PHASE ONE
Permittee as filedJohn Carroll
NPDES IDINRA14873
Permit statusEffective
Permit typeCoverage under a general permit
Discharger classMinor discharger
Facility typeNot a publicly owned treatment works
ProgramConstruction stormwater
IssuedNovember 6, 2024
Expiration dateNovember 5, 2029
Issuing agencyState
AddressLowell, IN 46356
SubwatershedGreisel Ditch (HUC 071200011304)

Cited to the EPA ICIS-NPDES permit file (ECHO download).

Effluent limits and exceedances

EPA’s limits and effluent violation files hold no pollutant row for NPDES INRA14873.

Cited to the EPA ICIS-NPDES limits and effluent violations files (ECHO download); up to 60 rows shown, most exceedances first.

Inspections, violations and enforcement

EPA’s single-event violation file, as loaded, holds no violation for NPDES INRA14873.

Inspections

EPA’s inspection file holds no inspection for NPDES INRA14873.

Formal enforcement and penalties

0 formal actions, 0 of them with a penalty assessed. Federal and state penalties are separate figures from separate authorities and are shown as each was filed, never added together.

Informal enforcement

EPA’s informal enforcement file holds no action for NPDES INRA14873.

Cited to the EPA ICIS-NPDES violation, inspection and enforcement files (ECHO download); up to 50 rows of each shown, newest first.

Watch this permit

One permit holder, $99/month. Watch the register for one permit holder and the places and receiving waters tied to its permits. Choose “One permit holder” and enter this permit’s NPDES ID, INRA14873.

Start the watch

How often?
  • One permit holder — $99/month
  • One watershed — $2,990/year
  • One state — $4,990/year
  • The whole register — $18,000/year

How we handle your data → Privacy

EPA publishes a free Detailed Facility Report for every permit on ECHO: its compliance status quarter by quarter, its inspections, and its enforcement actions and penalties. EPA also sends free notices of new inspections and enforcement actions through ECHO Notify; enter NPDES ID INRA14873 there.

STONE MILL PHASE ONE, Lowell, Indiana: Coverage under a general permit INRA14873, held by John Carroll; Construction stormwater; Effective; issued November 6, 2024, term to November 5, 2029, by State.

Indiana holds 7,813 Construction stormwater coverages of this permit type in EPA’s file; 4,230 were issued before INRA14873. John Carroll holds 3 permits in Indiana.

Other permits held by John Carroll

Coverages issued nearest INRA14873

STONE MILL PHASE ONE among its neighbors

4 discharge permits are in the Greisel Ditch subwatershed (HUC 071200011304); INRA14873 is one.

Other permits in the Greisel Ditch subwatershed (HUC 071200011304)

Nearby on the register

Figures from EPA’s ICIS-NPDES download, loaded September 15, 2026.

What this page shows

STONE MILL PHASE ONE is among 37 storm water construction permits in Lowell, and 0.0% of that group has a violation on file. Counting this permit, 67.6% of the Lowell group was issued earlier. The Greisel Ditch subwatershed lists 4 NPDES permits, including this permit.