NPDES KYR10T205 · Clean Water Act
LN 100-3 MAKE PIGGABLE PROJECT – BARREN RIVER HDD WITH HYDROSTATIC TESTING, Glasgow, KY: NPDES KYR10T205 discharge permit, effluent exceedances, inspections, penalties
LN 100-3 MAKE PIGGABLE PROJECT – BARREN RIVER HDD WITH HYDROSTATIC TESTING, Glasgow, Kentucky: General permit coverage KYR10T205, held by LN 100-3 Make Piggable Project – Barren River HDD with Hydrostatic Testing; Construction stormwater; Effective; issued March 4, 2025, term to December 31, 2029, by KY DEP; discharges to Barren River.
Kentucky holds 1,852 Construction stormwater coverages of this permit type in EPA’s file; 208 were issued before KYR10T205.
Coverages issued nearest KYR10T205
- 2025-03-03: GRAYSON COUNTY TECHNOLOGY CENTER ADDITION/RENOVATION, Leitchfield: KYR10T202, held by Grayson County Technology Center Addition/Renovation
- 2025-03-03: TK STONE MIDDLE SCHOOL RENOVATION, Elizabethtown: KYR10T203, held by TK Stone Middle School Renovation
- 2025-03-03: CAROL DRIVE STORMWATER IMPROVEMENTS, Fort Wright: KYR10T206
- 2025-03-03: HYDROSTATIC DISCHARGE - BEP 60 VALVE REPLACEMENT, Louisville: KYR10T210, held by Hydrostatic Discharge - BEP 60 Valve Replacement
- 2025-03-04: MAYFIELD CITY HALL AND POLICE STATION DEVELOPMENT, Mayfield: KYR10T194, held by Mayfield City Hall and Police Station Development
- 2025-03-04: MENELAUS RD SUBDIVISION DEVELOPMENT, Berea: KYR10T207, held by Menelaus Rd Subdivision Development
- 2025-03-04: BEULAH CROSSING, Louisville: KYR10T208, held by Beulah Crossing
- 2025-03-04: VINEYARD ESTATES SUBDIVISION, Burlington: KYR10T209, held by Vineyard Estates Subdivision
- 2025-03-04: AIRPARK LOGISTICS 237 - EAST PHASE CLEARING, Hebron: KYR10T211, held by Airpark Logistics 237 - East Phase Clearing
- 2025-03-04: GYM INVESTMENT - LOT 4, Bowling Green: KYR10T212, held by Gym Investment - Lot 4
LN 100-3 MAKE PIGGABLE PROJECT – BARREN RIVER HDD WITH HYDROSTATIC TESTING among its neighbors
1 discharge permits are in the Little Difficult Creek-Barren River subwatershed (HUC 051100020405); KYR10T205 is one. Its county: 39, 1 major; KYR10T205 is minor permit.
What stands out
- Its term runs 4 years and 302 days, March 4, 2025 to December 31, 2029.
- No dated event in the 365 days to September 15, 2026.
- It is one of 5,741 discharge permits on the register in Kentucky; 1,852 of them (32%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility | LN 100-3 MAKE PIGGABLE PROJECT – BARREN RIVER HDD WITH HYDROSTATIC TESTING |
|---|---|
| Permittee | LN 100-3 Make Piggable Project – Barren River HDD with Hydrostatic Testing |
| NPDES ID | KYR10T205 |
| Status | Effective |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Construction stormwater |
| Issued | March 4, 2025 |
| Expires | December 31, 2029 |
| Agency | KY DEP |
| Address | Glasgow, KY 42141 |
| Receiving water | Barren River |
| Subwatershed | Little Difficult Creek-Barren River (HUC 051100020405) |
NPDES KYR10T205: effluent limits and exceedances
LN 100-3 MAKE PIGGABLE PROJECT – BARREN RIVER HDD WITH HYDROSTATIC TESTING (NPDES KYR10T205): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES KYR10T205: no pollutant row on file.
NPDES KYR10T205: inspections, violations and enforcement
NPDES KYR10T205 (LN 100-3 MAKE PIGGABLE PROJECT – BARREN RIVER HDD WITH HYDROSTATIC TESTING): no single-event violation, inspection, formal enforcement action and informal enforcement action on file.
Watch NPDES KYR10T205
NPDES KYR10T205: one email when its EPA record changes — $99/month.
Permits near NPDES KYR10T205
NPDES KYR10T205: 0 pollutant rows, 0 dated events; ICIS-NPDES download, loaded September 15, 2026.