MAGNOLIA POINT SUBDIVISION EXPANSION, Richmond, Kentucky: General permit coverage KYR10T595, held by Magnolia Point Subdivision Expansion; Construction stormwater; Effective; issued June 27, 2025, term to December 31, 2029, by KY DEP; discharges to Otter Creek.
- June 29, 2026: Failure to properly install, initiate, or fully implement construction stormwater controls (ST6).
- June 29, 2026: Failure to develop, maintain, or get approval of an adequate SWPPP (construction stormwater) (ST6).
- June 29, 2026: Evaluation (S).
Kentucky holds 1,852 Construction stormwater coverages of this permit type in EPA’s file; 553 were issued before KYR10T595.
Coverages issued nearest KYR10T595
- 2025-06-25: MAD EQUIPMENT - STORAGE AREA, Bardstown: KYR10T609, held by MAD Equipment - Storage Area
- 2025-06-26: REPLACE DETERIORATED UNDERGROUND UTILITIES, Lexington: KYR10T605, held by Replace Deteriorated Underground Utilities
- 2025-06-26: BARNES MILL VILLAS, Richmond: KYR10T614
- 2025-06-26: DUKE ENERGY – CIRCUIT 2166 - BRENT SPENCE BRIDGE RELOCATIONS, Erlanger: KYR10T615, held by Duke Energy – Circuit 2166 - Brent Spence Bridge Relocations
- 2025-06-27: FRANKLIN SIMPSON BASEBALL AND SOFTBALL FIELD IMPROVEMENTS, Franklin: KYR10T594, held by Franklin Simpson Baseball and Softball Field Improvements
- 2025-06-27: KYTC PROJECT: ITEM 02-229.00, Utica: KYR10T596, held by KYTC Project: Item 02-229.00
- 2025-06-27: REPAVE/REPAIR ASPHALT ROAD AT GATE 7, Fort Campbell: KYR10T598, held by Repave/repair Asphalt Road at Gate 7
- 2025-06-27: BJ'S WHOLESALE CLUB - FRANKFORT, Frankfort: KYR10T599, held by BJ's Wholesale Club - Frankfort
- 2025-06-27: CAMP LANDING LIFT STATION REPLACEMENT, Ashland: KYR10T601, held by Camp Landing Lift Station Replacement
- 2025-06-27: COMMERCE PARK WAREHOUSE, Bowling Green: KYR10T612, held by Commerce Park Warehouse
MAGNOLIA POINT SUBDIVISION EXPANSION among its neighbors
17 discharge permits are in the Upper Otter Creek subwatershed (HUC 051002050105); KYR10T595 is one. Its county: 126, 4 major; KYR10T595 is minor permit.
Other permits in the Upper Otter Creek subwatershed (HUC 051002050105)
- BOB RILEY DISTRIBUTORS INC, Richmond: KY0109908, minor, term to 2023-07-31
- BOURBON BARREL BEEF - RICHMOND, KY, Richmond: KYR10U141, minor, term to 2029-12-31
- CARRIAGE PLACE (LOTS 1-108), Richmond: KYR10U417, minor, term to 2029-12-31
- DOLLAR GENERAL, Richmond: KYR10U078, minor, term to 2029-12-31
- EASTERN KENTUCKY UNIVERSITY, Richmond: KYG200053, minor, term to 2015-03-31
- ENERSYS INC, Richmond: KY0097381, minor, term to 2023-08-31
- GATES FORD NEW TRUCK SERVICE SHOP, Richmond: KYR10U435, minor, term to 2029-12-31
- GREENS CROSSING COLLECTION SYSTEM, Richmond: KYP000071, minor, term to 2014-04-30
- JACOBS MINI STORAGE UNITS, Richmond: KYR10T964, minor, term to 2029-12-31
- LIFE CHURCH, CHURCH OF GOD, INC, Richmond: KYR10U824, minor, term to 2029-12-31
What stands out
- Its term runs 4 years and 187 days, June 27, 2025 to December 31, 2029.
- Its newest dated event on file is single-event violation and inspection on June 29, 2026, 107 days before EPA's file was loaded.
- In the 365 days to October 14, 2026, it was dated 2 single-event violations, 1 inspection.
- EPA's file dates 3 events for it, all in 2026.
- It is one of 5,741 discharge permits on the register in Kentucky; 1,852 of them (32%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility | MAGNOLIA POINT SUBDIVISION EXPANSION |
|---|---|
| Permittee | Magnolia Point Subdivision Expansion |
| NPDES ID | KYR10T595 |
| Status | Effective |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Construction stormwater |
| Issued | June 27, 2025 |
| Expires | December 31, 2029 |
| Agency | KY DEP |
| Address | Richmond, KY 40475 |
| Receiving water | Otter Creek |
| Subwatershed | Upper Otter Creek (HUC 051002050105) |
| SIC | 1611 – Highway And Street Construction |
NPDES KYR10T595: effluent limits and exceedances
MAGNOLIA POINT SUBDIVISION EXPANSION (NPDES KYR10T595): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES KYR10T595: no pollutant row on file.
NPDES KYR10T595: inspections, violations and enforcement
NPDES KYR10T595: 2 single-event violations
| Date | What EPA recorded | Agency |
|---|---|---|
| June 29, 2026 | Failure to properly install, initiate, or fully implement construction stormwater controls | ST6 |
| June 29, 2026 | Failure to develop, maintain, or get approval of an adequate SWPPP (construction stormwater) | ST6 |
NPDES KYR10T595: 1 inspection
| Date | What EPA recorded | Agency |
|---|---|---|
| June 29, 2026 | Evaluation | S |
NPDES KYR10T595 (MAGNOLIA POINT SUBDIVISION EXPANSION): no formal enforcement action and informal enforcement action on file.
Watch NPDES KYR10T595
NPDES KYR10T595: one email when its EPA record changes — $99/month.
Permits near NPDES KYR10T595
NPDES KYR10T595: 0 pollutant rows, 3 dated events; ICIS-NPDES download, loaded October 14, 2026.