NPDES LA0127226 · Clean Water Act
NORMC PARKING GARAGE & THERMAL FACILITY - CHILLER PLANT, New Orleans, LA: NPDES LA0127226 discharge permit, effluent exceedances, inspections, penalties
NORMC PARKING GARAGE & THERMAL FACILITY - CHILLER PLANT, New Orleans, Louisiana: Individual permit LA0127226, held by Centrio Energy South, LLC; Administratively continued; issued April 4, 2017, term to April 3, 2022.
- Chlorine, total residual: 1 limit, 23 violations of any kind, 20 effluent exceedances, latest April 30, 2026, largest 1,000% over the limit.
- Oxygen demand, chem. [high level] [COD]: 1 limit, 17 violations of any kind, 14 effluent exceedances, latest August 31, 2024, largest 93% over the limit.
- pH: 4 limits, 16 violations of any kind, 5 effluent exceedances, latest December 31, 2025.
- Solids, total suspended: 1 limit, 5 violations of any kind, 2 effluent exceedances, latest February 28, 2023, largest 444% over the limit.
- Carbon, tot organic [TOC]: 1 limit, 4 violations of any kind, 2 effluent exceedances, latest September 30, 2024, largest 13% over the limit.
- Flow, in conduit or thru treatment plant: 4 limits, 18 violations of any kind.
- Oil & Grease: 2 limits, 4 violations of any kind.
NORMC PARKING GARAGE & THERMAL FACILITY - CHILLER PLANT among its neighbors
35 discharge permits are in the Metairie Canal-Canal No 2 subwatershed (HUC 080902030103); LA0127226 is one. Its county: 106, 6 major; LA0127226 is minor permit.
Other permits in the Metairie Canal-Canal No 2 subwatershed (HUC 080902030103)
- BAYOU BEND OFFSHORE, LTD, New Orleans: GMG290342, minor, term to 2012-09-30
- BEVERLY CONSTRUCTION CO., LLC - RR201 TAFT PLACE, New Orleans: LAR10N469, minor, term to 2019-09-30
- BLOCK BUILDERS LLC - SACRED HEART @ ST. BERNARD, New Orleans: LAR10M060, minor, term to 2018-02-12
- BOH BROS. CONSTRUCTION CO. LLC, New Orleans: LAR10K586, minor, term to 2017-12-29
- BROADMOOR LLC- TULANE, New Orleans: LAR10L760, minor, term to 2017-08-25
- CENTURY EXPLOR NEW ORLEANS INC, Metairie: GMG290077, minor, term to 2012-09-30
- COLDREN OIL & GAS COMPANY LP, New Orleans: GMG290318, minor, term to 2012-09-30
- COMMAND CONSTRUCTION INDUSTRIES LLC, New Orleans: LAR10M118, minor, term to 2018-03-13
- COMMAND CONSTRUCTION INDUSTRIES LLC, New Orleans: LAR10N114, minor, term to 2020-03-28
- CORE CONSTRUCTION SVCS LLC - BOOKER T. WASHINGTON SCHOOL, Metairie: LAR10L849, minor, term to 2018-10-19
What stands out
- Its term runs 4 years and 364 days, April 4, 2017 to April 3, 2022; the term ended 1,655 days before EPA's file was loaded on October 14, 2026, and the file lists the permit as administratively continued.
- No dated event in the 365 days to October 14, 2026.
- 5 of its 7 pollutants on file have an effluent exceedance (71%); 7 are under a numeric limit; the largest exceedance is Chlorine, total residual at 1,000% over its limit.
- It is one of 4,455 discharge permits on the register in Louisiana; the file names no program for it, and it is a minor discharger.
Identity
| Facility | NORMC PARKING GARAGE & THERMAL FACILITY - CHILLER PLANT |
|---|---|
| Permittee | Centrio Energy South, LLC |
| NPDES ID | LA0127226 |
| Status | Administratively continued |
| Type | Individual permit |
| Class | Minor |
| Facility type | Non-POTW |
| Issued | April 4, 2017 |
| Expires | April 3, 2022 |
| Address | New Orleans, LA 70112 |
| Receiving water impaired | 303(D) Listed |
| Subwatershed | Metairie Canal-Canal No 2 (HUC 080902030103) |
| SIC | 4961 – Steam And Air-Conditioning Supply |
NPDES LA0127226: effluent limits and exceedances
NORMC PARKING GARAGE & THERMAL FACILITY - CHILLER PLANT (NPDES LA0127226): 7 pollutants on file, 7 limited; 7 with a violation of any kind, 5 with an exceedance.
| Pollutant | Limits | Violations | Exceedances | Latest | Largest, as filed |
|---|---|---|---|---|---|
| Chlorine, total residual | 1 | 23 | 20 | April 30, 2026 | 1,000% over the limit |
| Oxygen demand, chem. [high level] [COD] | 1 | 17 | 14 | August 31, 2024 | 93% over the limit |
| pH | 4 | 16 | 5 | December 31, 2025 | |
| Solids, total suspended | 1 | 5 | 2 | February 28, 2023 | 444% over the limit |
| Carbon, tot organic [TOC] | 1 | 4 | 2 | September 30, 2024 | 13% over the limit |
| Flow, in conduit or thru treatment plant | 4 | 18 | 0 | ||
| Oil & Grease | 2 | 4 | 0 |
NPDES LA0127226: inspections, violations and enforcement
NPDES LA0127226 (NORMC PARKING GARAGE & THERMAL FACILITY - CHILLER PLANT): no single-event violation, inspection, formal enforcement action and informal enforcement action on file.
Watch NPDES LA0127226
NPDES LA0127226: one email when its EPA record changes — $99/month.
Permits near NPDES LA0127226
NPDES LA0127226: 7 pollutant rows, 0 dated events; ICIS-NPDES download, loaded October 14, 2026.