NPDES MAR1003Q2 · Clean Water Act
FISH ROAD RECLAMATION PROJECT, Dudley, MA: NPDES MAR1003Q2 discharge permit, effluent exceedances, inspections, penalties
FISH ROAD RECLAMATION PROJECT, Dudley, Massachusetts: General permit coverage MAR1003Q2, held by Rampco Construction Co. Inc.; Construction stormwater; Administratively continued; issued February 9, 2022, term to February 15, 2022, by U.S. EPA.
Massachusetts holds 3,320 Construction stormwater coverages of this permit type in EPA’s file; 527 were issued before MAR1003Q2.
Coverages issued nearest MAR1003Q2
- 2022-02-03: C116287 BALTAZAR: HADLEY, MA - RUSSELL ST (ROUTE 9), Hadley: MAR1003PS, held by Baltazar Contractors, Inc.
- 2022-02-04: PROPOSED HOSPITAL DRIVE SUBDIVISION - PHASE 2, Worcester: MAR1003PU, held by JH Lynch & Sons, Inc.
- 2022-02-07: GODDARD SCHOOL - 193 CENTRAL AVENUE, Milton: MAR1003PY, held by Acella Construction
- 2022-02-08: LEASE PARCEL A-BARNES REGIONAL AIRPORT-AIRPORT ROAD, Westfield: MAR1003PZ, held by J.L. Raymaakers & Sons, Inc.
- 2022-02-08: BRIDGE REPLACEMENT BR. NO. R-04-004 ON REED STREET - REHOBOTH, MA, Rehoboth: MAR1003Q1, held by Tully Construction Corp.
- 2022-02-10: DYER STREET, Rockland: MAR1003Q4, held by Gaspar Investment, Inc.
- 2022-02-14: INTERSECTION RECONSTRUCTION ON ROUTE 108 AT ROUTE 110 (KENOZA AVE), Haverhil: MAR1003O3, held by Newport Construction Corporation
- 2022-02-14: CAPE COD LUMBER EXPANSION, Abington: MAR1003Q6, held by Industrial Building Group, LLC.
- 2022-02-14: LOVELL ACADEMY, Rockland: MAR1003Q8, held by Integrated Builders, Inc.
- 2022-02-14: SWANSEA MALL REDEVELOPMENT PROJECT - PHASE 2, Swansea: MAR1003QF, held by Brady Sullivan Properties, LLC
FISH ROAD RECLAMATION PROJECT among its neighbors
4 discharge permits are in the Shunway Brook-Quinebaug River subwatershed (HUC 011000010105); MAR1003Q2 is one.
Other permits in the Shunway Brook-Quinebaug River subwatershed (HUC 011000010105)
- QUINEBAUG VALLEY RAIL TRAIL, Southbridge: MAR1005F4, minor, term to 2027-02-16
- WALNUT LANE FARM RECLAMATION PROJECT, Dudley: MAR1006B0, minor, term to 2027-02-16
- WALNUT LANE FARM RECLAMATION PROJECT, Dudley: MAR1006B8, minor, term to 2027-02-16
What stands out
- Its term runs 6 days, February 9, 2022 to February 15, 2022; the term ended 1,702 days before EPA's file was loaded on October 14, 2026, and the file lists the permit as administratively continued.
- No dated event in the 365 days to October 14, 2026.
- It is one of 6,154 discharge permits on the register in Massachusetts; 3,324 of them (54%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility | FISH ROAD RECLAMATION PROJECT |
|---|---|
| Permittee | Rampco Construction Co. Inc. |
| NPDES ID | MAR1003Q2 |
| Status | Administratively continued |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Construction stormwater |
| Issued | February 9, 2022 |
| Expires | February 15, 2022 |
| Agency | U.S. EPA |
| Address | Dudley, MA 01571 |
| Receiving water impaired | 303(D) Listed |
| Subwatershed | Shunway Brook-Quinebaug River (HUC 011000010105) |
NPDES MAR1003Q2: effluent limits and exceedances
FISH ROAD RECLAMATION PROJECT (NPDES MAR1003Q2): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES MAR1003Q2: no pollutant row on file.
NPDES MAR1003Q2: inspections, violations and enforcement
NPDES MAR1003Q2 (FISH ROAD RECLAMATION PROJECT): no single-event violation, inspection, formal enforcement action and informal enforcement action on file.
Watch NPDES MAR1003Q2
NPDES MAR1003Q2: one email when its EPA record changes — $99/month.
Permits near NPDES MAR1003Q2
NPDES MAR1003Q2: 0 pollutant rows, 0 dated events; ICIS-NPDES download, loaded October 14, 2026.