BIGELOW ROAD AND MEMORIAL BEACH PFAS WATER TREATMENT PLANTS, Webster, MA: NPDES MAR1005BL discharge permit, effluent exceedances, inspections, penalties
BIGELOW ROAD AND MEMORIAL BEACH PFAS WATER TREATMENT PLANTS, Webster, Massachusetts: General permit coverage MAR1005BL, held by Methuen Construction, Inc.; Construction stormwater; Effective; issued July 31, 2024, term to February 16, 2027, by U.S. EPA.
Massachusetts holds 3,320 Construction stormwater coverages of this permit type in EPA’s file; 1,934 were issued before MAR1005BL. Methuen Construction, Inc. holds 3 permits in Massachusetts.
Other permits held by Methuen Construction, Inc.
- LITTLETON WATER RESOURCE RECOVERY FACILITY, Littleton: MAR1004SZ, issued 2023-09-11
- FAIRHAVEN WATER POLLUTION CONTROL FACILITY UPGRADES, Fairhaven: MAR1004ZT, issued 2024-01-22
Coverages issued nearest MAR1005BL
- 2024-07-29: VILLAGE OF WESTERLY CONDOMINIUMS, Ashland: MAR1005BD, held by Brigs, LLC
- 2024-07-29: HANSON STREET RECONSTRUCTION, Lynn: MAR1005BE, held by Tasco Construction, Inc.
- 2024-07-29: V5/U6 AND S8 115KV TRANSMISSION LINES ASSET CONDITION REFURBISHMENT PROJECT, Dighton: MAR1005BF, held by Massachusetts Electric Company and New England Power Company dba National Grid
- 2024-07-30: 23 CAPE ROAD, Mendon: MAR1005BG, held by ARCO Design/Build
- 2024-07-30: SHOPS AT BILLERICA OUTPARCEL, Billerica: MAR1005BI, held by Inter-City Construction
- 2024-08-01: RANDOLPH ROAD LOT 2, Randolph: MAR1005BM, held by ARCO Design/Build
- 2024-08-01: 50 WESTFORD RD, TYNGSBOROUGH, MA, Tyngsborough: MAR1005BN, held by Moises Dias, Petroleum Engineering, Inc.
- 2024-08-02: GENERAL KNOX ROAD REALIGNMENT, Russell: MAR1005BP, held by Rifenburg Contracting Corp.
- 2024-08-05: NANTASKET AVENUE SEAWALL PROJECT, Hull: MAR1005BS, held by Manafort Transit
- 2024-08-05: MILLIKEN TENNIS COURT RENOVATIONS, Cohasset: MAR1005BT, held by RAD Sports
BIGELOW ROAD AND MEMORIAL BEACH PFAS WATER TREATMENT PLANTS among its neighbors
24 discharge permits are in the Middle French River subwatershed (HUC 011000010203); MAR1005BL is one.
Other permits in the Middle French River subwatershed (HUC 011000010203)
- #608433, WEBSTER, INTERSECTION IMPROVEMENTS AT I-395 RAMPS AT RT 16 & SUTTON RD, Webster: MAR1005NO, minor, term to 2027-02-16
- 8 TOWN FOREST ROAD - OXFORD, MA, Oxford: MAR100408, minor, term to 2027-02-16
- CHASE CORPORATION, Oxford: MANOE3848, minor, term to 2021-03-18
- CONSOLIDATED FABRICATORS, Oxford: MANOE3501, minor, term to 2020-09-08
- DUDLEY SEWER COLLECTION SYSTEM, Dudley: MAC010439, minor, term to 2026-11-30
- DUDLEY TOWN OF, Dudley: MAR041108
- GENTEX OPTICS INC, Dudley: MANOE2011, minor, term to 2022-07-17
- INTERSECTION IMPROVEMENTS AT I-395 RAMPS (EXIT 3) AT RT 16 & SUTTON RD, Webster: MAR1005FJ, minor, term to 2027-02-16
- IPG PHOTONICS, Oxford: MANOE3047, minor, term to 2020-08-13
- LAKEVIEW MARINE, INC, Webster: MANOEJ0CT, minor, term to 2029-03-29
What stands out
- Its term runs 2 years and 200 days, July 31, 2024 to February 16, 2027.
- No dated event in the 365 days to September 15, 2026.
- It is one of 6,154 discharge permits on the register in Massachusetts; 3,324 of them (54%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility | BIGELOW ROAD AND MEMORIAL BEACH PFAS WATER TREATMENT PLANTS |
|---|---|
| Permittee | Methuen Construction, Inc. |
| NPDES ID | MAR1005BL |
| Status | Effective |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Construction stormwater |
| Issued | July 31, 2024 |
| Expires | February 16, 2027 |
| Agency | U.S. EPA |
| Address | Webster, MA 01570 |
| Receiving water impaired | 303(D) Listed |
| Subwatershed | Middle French River (HUC 011000010203) |
NPDES MAR1005BL: effluent limits and exceedances
BIGELOW ROAD AND MEMORIAL BEACH PFAS WATER TREATMENT PLANTS (NPDES MAR1005BL): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES MAR1005BL: no pollutant row on file.
NPDES MAR1005BL: inspections, violations and enforcement
NPDES MAR1005BL (BIGELOW ROAD AND MEMORIAL BEACH PFAS WATER TREATMENT PLANTS): no single-event violation, inspection, formal enforcement action and informal enforcement action on file.
Watch NPDES MAR1005BL
NPDES MAR1005BL: one email when its EPA record changes — $99/month.
Permits near NPDES MAR1005BL
NPDES MAR1005BL: 0 pollutant rows, 0 dated events; ICIS-NPDES download, loaded September 15, 2026.