NPDES MI0001422 · Clean Water Act
CECO-J H CAMPBELL POWER PLT, West Olive, MI: NPDES MI0001422 discharge permit, effluent exceedances, inspections, penalties
CECO-J H CAMPBELL POWER PLT, West Olive, Michigan: Individual permit MI0001422, held by Consumers Energy Company; Effective; issued May 29, 2018, term to October 1, 2022, by State; discharges to Pigeon Lake; Fossil Fuel Electric Power Generation.
3 of the 14 pollutants listed for NPDES MI0001422 have no violation or effluent exceedance.
- Oxidants, total residual: 4 limits, 89 violations of any kind, 4 effluent exceedances, latest April 30, 2005, largest 297% over the limit.
- pH: 4 limits, 79 violations of any kind, 1 effluent exceedance, latest May 31, 2012.
- Flow, in conduit or thru treatment plant: 7 limits, 138 violations of any kind.
- Total residual ooxidant-discharge time: 1 limit, 70 violations of any kind.
- Solids, total suspended: 6 limits, 58 violations of any kind.
- Outfall observation,visual, y/n response: 2 limits, 37 violations of any kind.
- Temperature, water deg. fahrenheit: 4 limits, 27 violations of any kind.
- Copper, total [as Cu]: 4 limits, 27 violations of any kind.
- Iron, total [as Fe]: 4 limits, 27 violations of any kind.
- Oil & Grease: 5 limits, 10 violations of any kind.
- Selenium, total [as Se]: 4 limits, 4 violations of any kind.
- Phosphorus, total [as P]: 4 limits.
- Arsenic, total [as As]: 2 limits.
- Chlorination duration: 1 limit.
- September 4, 2019: Reporting Violations - Failure to Notify (ST6).
- April 26, 2019: Permit Violations - Discharge Without a Valid Permit (ST6).
Other permits held by Consumers Energy Company
- CECO-LUDINGTON PUMPED STORAGE, Ludington: MI0035912, issued 2013-12-20
- CONSUMERS ENERGY-NUISANCE PLANT, Jackson: MIG031078, issued 2018-09-19
- CECO-MUSK RIVER COMP STA, Marion: MIG250103, issued 2013-06-14
- CECO-HARDY DAM AND HYDRO PLANT, Newaygo: MIG250336, issued 2022-09-02
- CECO-ALCONA DAM AND HYDRO PLANT, Glennie: MIG250377, issued 2022-07-26
- CECO-MIO DAM AND HYDRO PLANT, Mio: MIG250381, issued 2019-10-14
- CECO-LOUD DAM AND HYDRO PLANT, Glennie: MIG250386, issued 2019-09-27
- CECO-FOOTE DAM AND HYDRO PLANT, Oscoda: MIG250389, issued 2022-07-11
- ZEELAND GENERATING STATION, Zeeland: MIS211074, issued 2018-06-15
CECO-J H CAMPBELL POWER PLT among its neighbors
2 discharge permits are in the Pigeon River subwatershed (HUC 040500020303); MI0001422 is one. Its county: 63, 7 major; MI0001422 is major permit.
Other permits in the Pigeon River subwatershed (HUC 040500020303)
- OTTAWA CDC MS4, West Olive: MI0059969, minor, term to 2023-10-01
What stands out
- Its term runs 4 years and 125 days, May 29, 2018 to October 1, 2022; the term ended 1,474 days before EPA's file was loaded on October 14, 2026, and the file lists the permit as effective.
- Its newest dated event on file is a single-event violation on September 4, 2019, 2,597 days before EPA's file was loaded.
- No dated event in the 365 days to October 14, 2026.
- EPA's file dates 2 events for it, all in 2019.
- 2 of its 14 pollutants on file have an effluent exceedance (14%); 14 are under a numeric limit; the largest exceedance is Oxidants, total residual at 297% over its limit.
- It is one of 3,396 discharge permits on the register in Michigan; the file names no program for it, and it is a major discharger.
Identity
| Facility | CECO-J H CAMPBELL POWER PLT |
|---|---|
| Permittee | Consumers Energy Company |
| NPDES ID | MI0001422 |
| Status | Effective |
| Type | Individual permit |
| Class | Major |
| Facility type | Non-POTW |
| Issued | May 29, 2018 |
| Expires | October 1, 2022 |
| Agency | State |
| Address | West Olive, MI 49460 |
| Receiving water | Pigeon Lake |
| Subwatershed | Pigeon River (HUC 040500020303) |
| NAICS | 221112 – Fossil Fuel Electric Power Generation |
| SIC | 4911 – Electric Services |
| Other EPA IDs (FRS) | RCRA handler MID041409954; ICIS-AIR source MI00000000000B2835 |
NPDES MI0001422: effluent limits and exceedances
CECO-J H CAMPBELL POWER PLT (NPDES MI0001422): 14 pollutants on file, 14 limited; 11 with a violation of any kind, 2 with an exceedance.
| Pollutant | Limits | Violations | Exceedances | Latest | Largest, as filed |
|---|---|---|---|---|---|
| Oxidants, total residual | 4 | 89 | 4 | April 30, 2005 | 297% over the limit |
| pH | 4 | 79 | 1 | May 31, 2012 | |
| Flow, in conduit or thru treatment plant | 7 | 138 | 0 | ||
| Total residual ooxidant-discharge time | 1 | 70 | 0 | ||
| Solids, total suspended | 6 | 58 | 0 | ||
| Outfall observation,visual, y/n response | 2 | 37 | 0 | ||
| Temperature, water deg. fahrenheit | 4 | 27 | 0 | ||
| Copper, total [as Cu] | 4 | 27 | 0 | ||
| Iron, total [as Fe] | 4 | 27 | 0 | ||
| Oil & Grease | 5 | 10 | 0 | ||
| Selenium, total [as Se] | 4 | 4 | 0 | ||
| Phosphorus, total [as P] | 4 | 0 | 0 | ||
| Arsenic, total [as As] | 2 | 0 | 0 | ||
| Chlorination duration | 1 | 0 | 0 |
NPDES MI0001422: inspections, violations and enforcement
NPDES MI0001422: 2 single-event violations
| Date | What EPA recorded | Agency |
|---|---|---|
| September 4, 2019 | Reporting Violations - Failure to Notify | ST6 |
| April 26, 2019 | Permit Violations - Discharge Without a Valid Permit | ST6 |
NPDES MI0001422 (CECO-J H CAMPBELL POWER PLT): no inspection, formal enforcement action and informal enforcement action on file.
Watch NPDES MI0001422
NPDES MI0001422: one email when its EPA record changes — $99/month.
Permits near NPDES MI0001422
NPDES MI0001422: 14 pollutant rows, 2 dated events; ICIS-NPDES download, loaded October 14, 2026.