NPDES MIS111771 · Clean Water Act
MKR FABRICATORS-TOWERLINE, Saginaw, MI: NPDES MIS111771 discharge permit, effluent exceedances, inspections, penalties
MKR FABRICATORS-TOWERLINE, Saginaw, Michigan: General permit coverage MIS111771, held by MKR Fabricating; Administratively continued; issued June 2, 2016, term to April 1, 2021, by State; discharges to Bolton Drain.
- August 16, 2022: Management Practice Violations - Failure to Maintain Records (ST6).
- August 16, 2022: WW Storm Water Non-Construction - Failure to develop any or adequate SWPPP/SWMP (ST6).
MKR FABRICATORS-TOWERLINE among its neighbors
4 discharge permits are in the Trombley Drain-Cheboyganing Creek subwatershed (HUC 040802060103); MIS111771 is one.
Other permits in the Trombley Drain-Cheboyganing Creek subwatershed (HUC 040802060103)
- FRANKENMUTH WELD & FABRICATING, Saginaw: MIS110030, minor, term to 2026-04-01
- GENERAL MACHINE SERV-SAGINAW, Saginaw: MIS210978, minor, term to 2022-04-01
- GEORGETOWN-FLINT RECYCLING, Saginaw: MIS120633, minor, term to 2021-04-01
What stands out
- Its term runs 4 years and 303 days, June 2, 2016 to April 1, 2021; the term ended 2,022 days before EPA's file was loaded on October 14, 2026, and the file lists the permit as administratively continued.
- Its newest dated event on file is a single-event violation on August 16, 2022, 1,520 days before EPA's file was loaded.
- No dated event in the 365 days to October 14, 2026.
- EPA's file dates 2 events for it, all in 2022.
- It is one of 3,396 discharge permits on the register in Michigan; the file names no program for it, and it is a minor discharger.
Identity
| Facility | MKR FABRICATORS-TOWERLINE |
|---|---|
| Permittee | MKR Fabricating |
| NPDES ID | MIS111771 |
| Status | Administratively continued |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Issued | June 2, 2016 |
| Expires | April 1, 2021 |
| Agency | State |
| Address | Saginaw, MI 48601 |
| Receiving water | Bolton Drain |
| Subwatershed | Trombley Drain-Cheboyganing Creek (HUC 040802060103) |
| SIC | 3441 – Fabricated Structural Metal |
NPDES MIS111771: effluent limits and exceedances
MKR FABRICATORS-TOWERLINE (NPDES MIS111771): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES MIS111771: no pollutant row on file.
NPDES MIS111771: inspections, violations and enforcement
NPDES MIS111771: 2 single-event violations
| Date | What EPA recorded | Agency |
|---|---|---|
| August 16, 2022 | Management Practice Violations - Failure to Maintain Records | ST6 |
| August 16, 2022 | WW Storm Water Non-Construction - Failure to develop any or adequate SWPPP/SWMP | ST6 |
NPDES MIS111771 (MKR FABRICATORS-TOWERLINE): no inspection, formal enforcement action and informal enforcement action on file.
Watch NPDES MIS111771
NPDES MIS111771: one email when its EPA record changes — $99/month.
Permits near NPDES MIS111771
NPDES MIS111771: 0 pollutant rows, 2 dated events; ICIS-NPDES download, loaded October 14, 2026.