NPDES MORA19934 · Clean Water Act
STONE CROSSING PH 5 AND 6, Troy, MO: NPDES MORA19934 discharge permit, effluent exceedances, inspections, penalties
STONE CROSSING PH 5 AND 6, Troy, Missouri: General permit coverage MORA19934, held by Cannon Builders, Inc.; Construction stormwater; Effective; issued February 11, 2022, term to February 7, 2027.
- September 2, 2022: WW Storm Water Construction - Failure to develop any or adequate SWPPP/SWMP (ST6).
Missouri holds 5,942 Construction stormwater coverages of this permit type in EPA’s file; 125 were issued before MORA19934. Cannon Builders, Inc. holds 3 permits in Missouri.
Other permits held by Cannon Builders, Inc.
- GETTYSBURG COMMONS PH 6, 7 AND 8, Wright City: MORA19960, issued 2022-02-14
- TBD - OFF WESTHAMPTON DRIVE, Troy: MORA26167, issued 2024-03-15
Coverages issued nearest MORA19934
- 2022-02-11: NEW MELLE FIRE HOUSE #1, New Melle: MORA19916, held by New Melle Fire Protection District
- 2022-02-11: CALEDONIA PLACE LLC, Linn Creek: MORA19918, held by Kenny Carroll Excavating
- 2022-02-11: HWY EE BORROW AREA PEMISCOT COUNTY, Gideon: MORA19919, held by Robertson Contractors, Inc. - Poplar Blu
- 2022-02-11: STONEBRIDGE III AND VILLAS, Troy: MORA19923, held by Stonebridge III and Villas
- 2022-02-11: HWY FF CONSTRUCTION YARD, Eureka: MORA19924, held by Precision Infrastructure, LLC
- 2022-02-11: TIFFANY HIGHLANDS, Nixa: MORA19935, held by Tiffany Highlands LLC
- 2022-02-11: ASBURY POWER PLANT POND CLOSURE, Asbury: MORA19936, held by The Empire District Electric Company
- 2022-02-11: FIENUP FARMS, Chesterfield: MORA19939, held by McBride Fienup Farms, LLC
- 2022-02-11: JB CAPITAL LOT 18, Washington: MORA19940, held by JB Capital Investments LLC
- 2022-02-11: RUSKIN HIGH SCHOOL, Kansas City: MORA19941, held by Hickman Mills C-1 School District
STONE CROSSING PH 5 AND 6 among its neighbors
35 discharge permits are in the Crooked Creek subwatershed (HUC 071100080402); MORA19934 is one. Its county: 226, 2 major; MORA19934 is minor permit.
Other permits in the Crooked Creek subwatershed (HUC 071100080402)
- 484 LINNS MILL ROAD, Troy: MORA24332, minor, term to 2027-02-07
- AUTO PARTS COMPANY OF ST. LOUIS, Moscow Mills: MOR60A031, minor, term to 2023-12-11
- BILL SULLIVAN EXCAVATION, INC., Silex: MORA23157, minor, term to 2027-02-07
- CELTIC CROSSINGS, Troy: MORA24923, minor, term to 2027-02-07
- CHAPELWOOD PLACE, Moscow Mills: MORA21645, minor, term to 2027-02-07
- CHESTNUT RIDGE, Moscow Mills: MORA26005, minor, term to 2027-02-07
- CROOKED CREEK MILLPOINT COURT 4 LOT, Troy: MORA22683, minor, term to 2027-02-07
- CROSSROADS CENTER, Moscow Mills: MORA28606, minor, term to 2027-02-07
- DOLLAR GENERAL #24039 TROY MO, Troy: MORA20110, minor, term to 2027-02-07
- EMC PLANT 83 MOSCOW MILLS, Moscow Mills: MOG491585, minor, term to 2027-04-30
What stands out
- Its term runs 4 years and 361 days, February 11, 2022 to February 7, 2027.
- Its newest dated event on file is a single-event violation on September 2, 2022, 1,474 days before EPA's file was loaded.
- No dated event in the 365 days to September 15, 2026.
- EPA's file dates 1 event for it, all in 2022.
- It is one of 13,736 discharge permits on the register in Missouri; 5,942 of them (43%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility | STONE CROSSING PH 5 AND 6 |
|---|---|
| Permittee | Cannon Builders, Inc. |
| NPDES ID | MORA19934 |
| Status | Effective |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Construction stormwater |
| Issued | February 11, 2022 |
| Expires | February 7, 2027 |
| Address | Troy, MO 63379 |
| Subwatershed | Crooked Creek (HUC 071100080402) |
NPDES MORA19934: effluent limits and exceedances
STONE CROSSING PH 5 AND 6 (NPDES MORA19934): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES MORA19934: no pollutant row on file.
NPDES MORA19934: inspections, violations and enforcement
NPDES MORA19934: 1 single-event violation
| Date | What EPA recorded | Agency |
|---|---|---|
| September 2, 2022 | WW Storm Water Construction - Failure to develop any or adequate SWPPP/SWMP | ST6 |
NPDES MORA19934 (STONE CROSSING PH 5 AND 6): no inspection, formal enforcement action and informal enforcement action on file.
Watch NPDES MORA19934
NPDES MORA19934: one email when its EPA record changes — $99/month.
Permits near NPDES MORA19934
NPDES MORA19934: 0 pollutant rows, 1 dated events; ICIS-NPDES download, loaded September 15, 2026.