NPDES MORA26081 · Clean Water Act
PARK N GO PHASE 2, Kansas City, MO: NPDES MORA26081 discharge permit, effluent exceedances, inspections, penalties
PARK N GO PHASE 2, Kansas City, Missouri: General permit coverage MORA26081, held by Pnglu Cfc Kansas City LLC; Construction stormwater; Effective; issued March 4, 2024, term to February 7, 2027; discharges to Tributary to Wildcat Branch.
Missouri holds 5,942 Construction stormwater coverages of this permit type in EPA’s file; 3,035 were issued before MORA26081.
Coverages issued nearest MORA26081
- 2024-03-04: NEMO SUBSTATION AND INTERCONNECT, Hurdland: MORA26073, held by Northeast Missouri Wind, LLC
- 2024-03-04: 452 BORROW SITE, Trenton: MORA26076, held by 462 Borrow Area
- 2024-03-04: ACE HARDWARE, Perryville: MORA26077, held by KEMO Investments, LLC
- 2024-03-04: THOMPSON BORROW, West Plains: MORA26079, held by Ronald Thompson Borrow
- 2024-03-04: LOT 1 CAPE LACROIX FARMS, Cape Girardeau: MORA26080, held by ZAC JAMI HUDSON
- 2024-03-04: CRANE RESIDENCE, Columbia: MORA26083, held by HSM, LLC
- 2024-03-04: ST. ROBERT CAR WASH, St. Robert: MORA26084, held by farris brothers investments co
- 2024-03-04: THREE RIVERS COMMUNITY COLLEGE, Poplar Bluff: MORA26085, held by Three Rivers Community College
- 2024-03-05: O'REILLY AUTO PARTS ASHLAND MO, Ashland: MORA26088, held by O'Reilly Automotive Stores, Inc
- 2024-03-05: OPPIDAN DATA CENTER, Berkeley: MORA26091, held by Oppidan Investment Company
PARK N GO PHASE 2 among its neighbors
31 discharge permits are in the Todd Creek subwatershed (HUC 102400120710); MORA26081 is one. Its county: 214, 5 major; MORA26081 is minor permit.
Other permits in the Todd Creek subwatershed (HUC 102400120710)
- AMAZON.COM SERVICES LLC MCI4, Kansas City: MOR80C724, minor, term to 2027-11-30
- CHAVES DEVELOPMENT, Kansas City: MORA24243, minor, term to 2027-02-07
- CONGRESS CORPORATE CENTER, Kansas City: MORA20641, minor, term to 2027-02-07
- DELAVAL INC, Kansas City: MONX00808, minor, term to 2026-05-12
- ENVISION, Kansas City: MORA28246, minor, term to 2027-02-07
- GEIGER READY MIX COMPANY KCI SITE, Kansas City: MOG491625, minor, term to 2027-04-30
- HARLEY-DAVIDSON VEHICLE AND POWERTRAIN O, Kansas City: MOR203198, minor, term to 2019-08-31
- I-29 AND COOKINGHAM DRIVE ROUNDABOUTS, Kansas City: MORA28511, minor, term to 2027-02-07
- I-29 AND MEXICO CITY AVE INTERCHANGE, Kansas City: MORA24664, minor, term to 2027-02-07
- KANSAS CITY INTERNATIONAL AIRPORT, Kansas City: MO0114812, major, term to 2022-04-30
What stands out
- Its term runs 2 years and 340 days, March 4, 2024 to February 7, 2027.
- No dated event in the 365 days to September 15, 2026.
- It is one of 13,736 discharge permits on the register in Missouri; 5,942 of them (43%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility | PARK N GO PHASE 2 |
|---|---|
| Permittee | Pnglu Cfc Kansas City LLC |
| NPDES ID | MORA26081 |
| Status | Effective |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Construction stormwater |
| Issued | March 4, 2024 |
| Expires | February 7, 2027 |
| Address | Kansas City, MO 64163 |
| Receiving water | Tributary to Wildcat Branch |
| Subwatershed | Todd Creek (HUC 102400120710) |
NPDES MORA26081: effluent limits and exceedances
PARK N GO PHASE 2 (NPDES MORA26081): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES MORA26081: no pollutant row on file.
NPDES MORA26081: inspections, violations and enforcement
NPDES MORA26081 (PARK N GO PHASE 2): no single-event violation, inspection, formal enforcement action and informal enforcement action on file.
Watch NPDES MORA26081
NPDES MORA26081: one email when its EPA record changes — $99/month.
Permits near NPDES MORA26081
NPDES MORA26081: 0 pollutant rows, 0 dated events; ICIS-NPDES download, loaded September 15, 2026.