ROSEBUD POWER PLANT, Colstrip, MT: NPDES MTR000058 discharge permit, effluent exceedances, inspections, penalties

ROSEBUD POWER PLANT, Colstrip, Montana: General permit coverage MTR000058, held by COLSTRIP ENERGY LIMITED PARTNERSHIP; Industrial stormwater; Administratively continued; issued June 1, 2018, term to January 31, 2023; discharges to EAST FORK ARMELLS CREEK.

No violation or effluent exceedance is on file for any of the 1 pollutants listed for NPDES MTR000058.

  • Iron, total [as Fe]: 3 limits.
  • January 11, 2023: WW Storm Water Non-Construction - Failure to properly install/implement BMPs (ST6).
  • January 11, 2023: WW Storm Water Non-Construction - Failure to submit required report (non-DMR) (ST6).
  • January 11, 2023: WW Storm Water Non-Construction - Failure to properly operate and maintain BMPs (ST6).

Montana holds 465 Industrial stormwater coverages of this permit type in EPA’s file; 188 were issued before MTR000058. COLSTRIP ENERGY LIMITED PARTNERSHIP holds 3 permits in Montana.

Other permits held by COLSTRIP ENERGY LIMITED PARTNERSHIP

Coverages issued nearest MTR000058

ROSEBUD POWER PLANT among its neighbors

3 discharge permits are in the East Fork Armells Creek-Sevenmile Creek subwatershed (HUC 101000011004); MTR000058 is one. Its county: 64, 1 major; MTR000058 is minor permit.

Other permits in the East Fork Armells Creek-Sevenmile Creek subwatershed (HUC 101000011004)

What stands out

  • Its term runs 4 years and 244 days, June 1, 2018 to January 31, 2023; the term ended 1,323 days before EPA's file was loaded on September 15, 2026, and the file lists the permit as administratively continued.
  • Its newest dated event on file is a single-event violation on January 11, 2023, 1,343 days before EPA's file was loaded.
  • No dated event in the 365 days to September 15, 2026.
  • EPA's file dates 3 events for it, all in 2023.
  • It is one of 4,574 discharge permits on the register in Montana; 470 of them (10%) are in its program, Industrial stormwater, and it is a minor discharger.

Identity

FacilityROSEBUD POWER PLANT
PermitteeCOLSTRIP ENERGY LIMITED PARTNERSHIP
NPDES IDMTR000058
StatusAdministratively continued
TypeGeneral permit coverage
ClassMinor
Facility typeNon-POTW
ProgramIndustrial stormwater
IssuedJune 1, 2018
ExpiresJanuary 31, 2023
AddressColstrip, MT 59323
Receiving waterEAST FORK ARMELLS CREEK
Receiving water impaired303(D) Listed
SubwatershedEast Fork Armells Creek-Sevenmile Creek (HUC 101000011004)
Other EPA IDs (FRS)RCRA handler MTR000004879; ICIS-AIR source MT0000003008700007

NPDES MTR000058: effluent limits and exceedances

ROSEBUD POWER PLANT (NPDES MTR000058): 1 pollutants on file, 1 limited; 0 with a violation of any kind, 0 with an exceedance.

How exceedances are counted.

PollutantLimitsViolationsExceedancesLatestLargest, as filed
Iron, total [as Fe]300

NPDES MTR000058: inspections, violations and enforcement

NPDES MTR000058: 3 single-event violations

DateWhat EPA recordedAgency
January 11, 2023WW Storm Water Non-Construction - Failure to properly install/implement BMPsST6
January 11, 2023WW Storm Water Non-Construction - Failure to submit required report (non-DMR)ST6
January 11, 2023WW Storm Water Non-Construction - Failure to properly operate and maintain BMPsST6

NPDES MTR000058 (ROSEBUD POWER PLANT): no inspection, formal enforcement action and informal enforcement action on file.

Watch NPDES MTR000058

NPDES MTR000058: one email when its EPA record changes — $99/month.

Billing

Privacy

Permits near NPDES MTR000058

NPDES MTR000058: 1 pollutant rows, 3 dated events; ICIS-NPDES download, loaded September 15, 2026.