NPDES MTR000058 · Clean Water Act
ROSEBUD POWER PLANT, Colstrip, MT: NPDES MTR000058 discharge permit, effluent exceedances, inspections, penalties
ROSEBUD POWER PLANT, Colstrip, Montana: General permit coverage MTR000058, held by COLSTRIP ENERGY LIMITED PARTNERSHIP; Industrial stormwater; Administratively continued; issued June 1, 2018, term to January 31, 2023; discharges to EAST FORK ARMELLS CREEK.
No violation or effluent exceedance is on file for any of the 1 pollutants listed for NPDES MTR000058.
- Iron, total [as Fe]: 3 limits.
- January 11, 2023: WW Storm Water Non-Construction - Failure to properly install/implement BMPs (ST6).
- January 11, 2023: WW Storm Water Non-Construction - Failure to submit required report (non-DMR) (ST6).
- January 11, 2023: WW Storm Water Non-Construction - Failure to properly operate and maintain BMPs (ST6).
Montana holds 465 Industrial stormwater coverages of this permit type in EPA’s file; 188 were issued before MTR000058. COLSTRIP ENERGY LIMITED PARTNERSHIP holds 3 permits in Montana.
Other permits held by COLSTRIP ENERGY LIMITED PARTNERSHIP
- ROSEBUD POWER PLANT COAL PILE RUNOFF, Colstrip: MT0031780, issued 2015-10-30
- ROSEBUD POWER PLANT, COLSTRIP ENERGY LIMITED PARTNERSHIP, Colstrip: MTX000052, issued 2011-08-25
Coverages issued nearest MTR000058
- 2018-05-24: SUN MOUNTAIN LOGGING, Deer Lodge: MTR000564, held by SUN MOUNTAIN LUMBER
- 2018-05-29: CHS INC - LAUREL REFINERY, Laurel: MTR000099, held by CHS INC
- 2018-05-29: KAMERMAN PIT, Manhattan: MTR000589, held by VANDYKEN TRUCKING & EXCAVATING LLC
- 2018-05-31: JUPITER SULPHUR INC, Billings: MTR000412, held by JUPITER SULPHUR LLC
- 2018-05-31: BORDER STEEL - GLENDIVE, Glendive: MTR000548, held by BORDER STEEL - ERNIE GAWRYLUK
- 2018-06-01: BORDER STEEL - PLENTYWOOD, Plentywood: MTR000550, held by BORDER STEEL - KENT SYME
- 2018-06-01: YODER GRAVEL PIT, Stevensville: MTR000600, held by JAKE YODER
- 2018-06-03: LEWIS AND CLARK COUNTY LANDFILL, Helena: MTR000363, held by LEWIS AND CLARK COUNTY
- 2018-06-03: STERLING RANCH PIT, Vaughn: MTR000599, held by UNITED MATERIALS OF GREAT FALLS INC
- 2018-06-12: YELLOWSTONE ENERGY LIMITED, Billings: MTR000364, held by YELLOWSTONE ENERGY LIMITED PARTNERSHIP
ROSEBUD POWER PLANT among its neighbors
3 discharge permits are in the East Fork Armells Creek-Sevenmile Creek subwatershed (HUC 101000011004); MTR000058 is one. Its county: 64, 1 major; MTR000058 is minor permit.
Other permits in the East Fork Armells Creek-Sevenmile Creek subwatershed (HUC 101000011004)
- CLEARWATER WIND T-LINE PROJECT, Colstrip: MTR108729, minor, term to 2022-12-31
- ROSEBUD POWER PLANT COAL PILE RUNOFF, Colstrip: MT0031780, minor, term to 2020-12-31
What stands out
- Its term runs 4 years and 244 days, June 1, 2018 to January 31, 2023; the term ended 1,323 days before EPA's file was loaded on September 15, 2026, and the file lists the permit as administratively continued.
- Its newest dated event on file is a single-event violation on January 11, 2023, 1,343 days before EPA's file was loaded.
- No dated event in the 365 days to September 15, 2026.
- EPA's file dates 3 events for it, all in 2023.
- It is one of 4,574 discharge permits on the register in Montana; 470 of them (10%) are in its program, Industrial stormwater, and it is a minor discharger.
Identity
| Facility | ROSEBUD POWER PLANT |
|---|---|
| Permittee | COLSTRIP ENERGY LIMITED PARTNERSHIP |
| NPDES ID | MTR000058 |
| Status | Administratively continued |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Industrial stormwater |
| Issued | June 1, 2018 |
| Expires | January 31, 2023 |
| Address | Colstrip, MT 59323 |
| Receiving water | EAST FORK ARMELLS CREEK |
| Receiving water impaired | 303(D) Listed |
| Subwatershed | East Fork Armells Creek-Sevenmile Creek (HUC 101000011004) |
| Other EPA IDs (FRS) | RCRA handler MTR000004879; ICIS-AIR source MT0000003008700007 |
NPDES MTR000058: effluent limits and exceedances
ROSEBUD POWER PLANT (NPDES MTR000058): 1 pollutants on file, 1 limited; 0 with a violation of any kind, 0 with an exceedance.
| Pollutant | Limits | Violations | Exceedances | Latest | Largest, as filed |
|---|---|---|---|---|---|
| Iron, total [as Fe] | 3 | 0 | 0 |
NPDES MTR000058: inspections, violations and enforcement
NPDES MTR000058: 3 single-event violations
| Date | What EPA recorded | Agency |
|---|---|---|
| January 11, 2023 | WW Storm Water Non-Construction - Failure to properly install/implement BMPs | ST6 |
| January 11, 2023 | WW Storm Water Non-Construction - Failure to submit required report (non-DMR) | ST6 |
| January 11, 2023 | WW Storm Water Non-Construction - Failure to properly operate and maintain BMPs | ST6 |
NPDES MTR000058 (ROSEBUD POWER PLANT): no inspection, formal enforcement action and informal enforcement action on file.
Watch NPDES MTR000058
NPDES MTR000058: one email when its EPA record changes — $99/month.
Permits near NPDES MTR000058
NPDES MTR000058: 1 pollutant rows, 3 dated events; ICIS-NPDES download, loaded September 15, 2026.