Velarion Records
Free: one email when NPDES MTR000592 changes. Unsubscribe any time.

NPDES MTR000592 · Clean Water Act

CROELL INCORPORATED HARDIN CONCRETE BATCH PLANT, Hardin, MT: NPDES MTR000592 discharge permit, effluent exceedances, inspections, penalties

CROELL INCORPORATED HARDIN CONCRETE BATCH PLANT, Hardin, Montana: General permit coverage MTR000592, held by CROELL INCORPORATED; Industrial stormwater; Administratively continued; issued May 10, 2018, term to January 31, 2023; discharges to LOWER BIG HORN.

  • Solids, total suspended: 2 limits, 4 violations of any kind.
  • Iron, total [as Fe]: 2 limits, 4 violations of any kind.
  • April 6, 2021: WW Storm Water Non-Construction - Failure to Maintain Records (ST6).
  • April 6, 2021: WW Storm Water Non-Construction - Failure to properly operate and maintain BMPs (ST6).
  • April 6, 2021: WW Storm Water Non-Construction - Failure to Conduct Inspections (ST6).
  • April 6, 2021: WW Storm Water Non-Construction - Failure to develop any or adequate SWPPP/SWMP (ST6).
  • April 6, 2021: WW Storm Water Non-Construction - Failure to properly install/implement BMPs (ST6).

Montana holds 465 Industrial stormwater coverages of this permit type in EPA’s file; 165 were issued before MTR000592. CROELL INCORPORATED holds 8 permits in Montana.

Other permits held by CROELL INCORPORATED

Coverages issued nearest MTR000592

CROELL INCORPORATED HARDIN CONCRETE BATCH PLANT among its neighbors

13 discharge permits are in the Bighorn River-Hardin subwatershed (HUC 100800150704); MTR000592 is one. Its county: 70, 3 major; MTR000592 is minor permit.

Other permits in the Bighorn River-Hardin subwatershed (HUC 100800150704)

What stands out

  • Its term runs 4 years and 266 days, May 10, 2018 to January 31, 2023; the term ended 1,352 days before EPA's file was loaded on October 14, 2026, and the file lists the permit as administratively continued.
  • Its newest dated event on file is a single-event violation on April 6, 2021, 2,017 days before EPA's file was loaded.
  • No dated event in the 365 days to October 14, 2026.
  • EPA's file dates 5 events for it, all in 2021.
  • It is one of 4,574 discharge permits on the register in Montana; 470 of them (10%) are in its program, Industrial stormwater, and it is a minor discharger.

Identity

FacilityCROELL INCORPORATED HARDIN CONCRETE BATCH PLANT
PermitteeCROELL INCORPORATED
NPDES IDMTR000592
StatusAdministratively continued
TypeGeneral permit coverage
ClassMinor
Facility typeNon-POTW
ProgramIndustrial stormwater
IssuedMay 10, 2018
ExpiresJanuary 31, 2023
AddressHardin, MT 59034
Receiving waterLOWER BIG HORN
SubwatershedBighorn River-Hardin (HUC 100800150704)
SIC3273 – Ready-Mixed Concrete

NPDES MTR000592: effluent limits and exceedances

CROELL INCORPORATED HARDIN CONCRETE BATCH PLANT (NPDES MTR000592): 2 pollutants on file, 2 limited; 2 with a violation of any kind, 0 with an exceedance.

How exceedances are counted.

PollutantLimitsViolationsExceedancesLatestLargest, as filed
Solids, total suspended240
Iron, total [as Fe]240

NPDES MTR000592: inspections, violations and enforcement

NPDES MTR000592: 5 single-event violations

DateWhat EPA recordedAgency
April 6, 2021WW Storm Water Non-Construction - Failure to Maintain RecordsST6
April 6, 2021WW Storm Water Non-Construction - Failure to properly operate and maintain BMPsST6
April 6, 2021WW Storm Water Non-Construction - Failure to Conduct InspectionsST6
April 6, 2021WW Storm Water Non-Construction - Failure to develop any or adequate SWPPP/SWMPST6
April 6, 2021WW Storm Water Non-Construction - Failure to properly install/implement BMPsST6

NPDES MTR000592 (CROELL INCORPORATED HARDIN CONCRETE BATCH PLANT): no inspection, formal enforcement action and informal enforcement action on file.

Watch NPDES MTR000592

NPDES MTR000592: one email when its EPA record changes — $99/month.

Billing

Privacy

Permits near NPDES MTR000592

NPDES MTR000592: 2 pollutant rows, 5 dated events; ICIS-NPDES download, loaded October 14, 2026.