NPDES MTR109327 · Clean Water Act
MOREL TO BUTTE PHASE II, Butte, MT: NPDES MTR109327 discharge permit, effluent exceedances, inspections, penalties
MOREL TO BUTTE PHASE II, Butte, Montana: General permit coverage MTR109327, held by NORTHWESTERN ENERGY; Construction stormwater; Administratively continued; issued January 25, 2022, term to December 31, 2022; discharges to SILVER BOW CREEK.
Montana holds 2,848 Construction stormwater coverages of this permit type in EPA’s file; 1,550 were issued before MTR109327. NORTHWESTERN ENERGY holds 34 permits in Montana.
Other permits held by NORTHWESTERN ENERGY
- NORTHWESTERN ENERGY PETERSON FLATS SUBSTATION, Grant: MTB003114
- NORTHWESTERN ENERGY - UNKNOWN WATER 318 PERMIT, Coram: MTB007708, issued 2008-02-19
- NORTHWESTERN ENERGY - BISON CREEK LOOP PIPELINE PROJECT, East Glacier Park: MTR102245, issued 2006-06-28
- NORTHWESTERN ENERGY - STONE CONTAINER PIPELINE MISSOULA REROUTE, Missoula: MTR102246, issued 2006-06-28
- NORTHWESTERN ENERGY - MILL CREEK SUBSTATION, Opportunity: MTR102519, issued 2007-03-19
- NORTHWESTERN ENERGY CUT BANK - MOREL 20 LOOP, Helena: MTR102540, issued 2007-03-29
- NORTHWESTERN ENERGY - 10 HELENA AREA REROUTE, Helena: MTR102541, issued 2007-03-29
- NORTHWESTERN ENERGY - COBB STORAGE NW 16 INCH LINE RPLCMT, Sweetgrass: MTR103674, issued 2010-03-11
- NORTHWESTERN ENERGY - BOZEMAN SERVICE CENTER HCA REROUTE, Bozeman: MTR104184, issued 2011-07-08
- NORTHWESTERN ENERGY - SOUTH BUTTE SUBSTATION, Butte: MTR104305, issued 2011-10-03
Coverages issued nearest MTR109327
- 2022-01-20: EAST OF EAST HELENA - EAST, East Helena: MTR109322, held by RIVERSIDE CONTRACTING INC
- 2022-01-20: BELT N&S BORROW, Belt: MTR109324, held by RIVERSIDE CONTRACTING INC
- 2022-01-20: SOUTH WOLF POINT WEST PHASE 2, Vida: MTR109326, held by MID-RIVERS TELEPHONE COOPERATIVE INC
- 2022-01-20: NAMCHAK RETREAT RANCH WATER SYSTEM IMPROVEMENTS, Hot Springs: MTR10I03Q, held by Dick Anderson Construction
- 2022-01-21: LOT 5 AT THE VILLAGE DOWNTOWN MINOR SUBDIVISION 344, Bozeman: MTR109314, held by Conti Bozeman LLC
- 2022-01-26: JACKSON COURT APARTMENTS, Billings: MTR109311, held by CAYTON EXCAVATION INC
- 2022-01-27: BIG TIMBER – TN FTTH PROJECT 2022, Big Timber: MTR109228, held by TRIANGLE TELEPHONE COOPERATIVE ASSN INC
- 2022-01-27: BIG TIMBER – WP FTTH PROJECT 2022, Big Timber: MTR109229, held by TRIANGLE TELEPHONE COOPERATIVE ASSN INC
- 2022-02-01: BRIDGER HEIGHTS PHASE 3 A-D (SNOWGHOST), Belgrade: MTR109240, held by PV WH Bridger Heights LLC
- 2022-02-01: KALISPELL NORTH TOWN CENTER PH 2, Kalispell: MTR109339, held by LHC INC
MOREL TO BUTTE PHASE II among its neighbors
4 discharge permits are in the Browns Gulch-Bull Run Creek subwatershed (HUC 170102010103); MTR109327 is one. Its county: 103, 3 major; MTR109327 is minor permit.
Other permits in the Browns Gulch-Bull Run Creek subwatershed (HUC 170102010103)
- LOVE'S TRAVEL STOP & COUNTRY STORE WATER LINE, Ramsay: MTR109186, minor, term to 2022-12-31
- LOVES TRAVEL STOPS & COUNTRY STORES INC, Ramsay: MTG580040
- NOT NEEDED, Ramsay: MTR107408
What stands out
- Its term runs 340 days, January 25, 2022 to December 31, 2022; the term ended 1,354 days before EPA's file was loaded on September 15, 2026, and the file lists the permit as administratively continued.
- No dated event in the 365 days to September 15, 2026.
- It is one of 4,574 discharge permits on the register in Montana; 2,849 of them (62%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility | MOREL TO BUTTE PHASE II |
|---|---|
| Permittee | NORTHWESTERN ENERGY |
| NPDES ID | MTR109327 |
| Status | Administratively continued |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Construction stormwater |
| Issued | January 25, 2022 |
| Expires | December 31, 2022 |
| Address | Butte, MT 59701 |
| Receiving water | SILVER BOW CREEK |
| Subwatershed | Browns Gulch-Bull Run Creek (HUC 170102010103) |
NPDES MTR109327: effluent limits and exceedances
MOREL TO BUTTE PHASE II (NPDES MTR109327): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES MTR109327: no pollutant row on file.
NPDES MTR109327: inspections, violations and enforcement
NPDES MTR109327 (MOREL TO BUTTE PHASE II): no single-event violation, inspection, formal enforcement action and informal enforcement action on file.
Watch NPDES MTR109327
NPDES MTR109327: one email when its EPA record changes — $99/month.
Permits near NPDES MTR109327
NPDES MTR109327: 0 pollutant rows, 0 dated events; ICIS-NPDES download, loaded September 15, 2026.