NPDES NCC232430 · Clean Water Act
CARY TRIANGLE EXPRESSWAY 230KV GREENFIELD SUBSTATION (T6811) DEVELOPMENT PL, Cary, NC: NPDES NCC232430 discharge permit, effluent exceedances, inspections, penalties
CARY TRIANGLE EXPRESSWAY 230KV GREENFIELD SUBSTATION (T6811) DEVELOPMENT PL, Cary, North Carolina: General permit coverage NCC232430, held by Duke Energy Progress, LLC; Effective; issued April 1, 2024, term to March 31, 2029.
Other permits held by Duke Energy Progress, LLC
- H.F LEE ENERGY COMPLEX INACTIVE BASIN CLOSURE (INACTIVE BASINS 1 AND 2), Goldsboro: NCC204357, issued 2024-04-01
- H.F. LEE ENERGY COMPLEX INACTIVE BASIN CLOSURE (INACTIVE BASIN 3), Goldsboro: NCC204399, issued 2024-04-01
- H.F. LEE ENERGY COMPLEX INACTIVE BASIN CLOSURE (BASINS 1 AND 2), Goldsboro: NCC213476, issued 2024-04-01
- CAPE FEAR 1956 BASIN EXCAVATION, Moncure: NCC213763, issued 2024-04-01
- ENKA 230KV SUBSTATION EXPANSION, Asheville: NCC213864, issued 2024-04-01
- MILBURNIE 230KV - YARD REBUILD, Raleigh: NCC217178, issued 2024-04-01
- 1963 & 1970 BASIN EXCAVATION EROSION & SEDIMENT CONTROL PLAN, Moncure: NCC222708, issued 2024-04-01
- HF LEE BLACK JACK CHURCH ROAD STOCKPILE E&SC PLAN, Goldsboro: NCC223366, issued 2024-04-01
- ATLANTIC 34.5KV OYSTER CREEK, Davis: NCC223526, issued 2024-04-01
- CAPE FEAR 63/70 BASIN HAUL ROAD, Moncure: NCC230214, issued 2024-04-01
CARY TRIANGLE EXPRESSWAY 230KV GREENFIELD SUBSTATION (T6811) DEVELOPMENT PL among its neighbors
32 discharge permits are in the White Oak Creek subwatershed (HUC 030300020608); NCC232430 is one.
Other permits in the White Oak Creek subwatershed (HUC 030300020608)
- APEX GATEWAY PHASE 2A, Apex: NCC251875, minor, term to 2029-03-31
- ARDEN AT SUMMIT PINES, Apex: NCC240461, minor, term to 2029-03-31
- CASTLEBERRY RESERVE, Apex: NCC252152, minor, term to 2029-03-31
- CLOUDBERRY COMMONS, Town Of Cary: NCC241565, minor, term to 2029-03-31
- COURTYARDS ON WIMBERLY, Apex: NCC261936, minor, term to 2029-03-31
- DESTIN III SUBDIVISION, Apex: NCC261329, minor, term to 2029-03-31
- DUKE HEALTH GREEN LEVEL WEST MEDICAL CAMPUS PHASES 3, Cary: NCC260516, minor, term to 2029-03-31
- ELLSWORTH, Apex: NCC202817, minor, term to 2029-03-31
- ESTATES AT WHITE OAK, Apex: NCC242103, minor, term to 2029-03-31
- FREEDOM SQUARE, Apex: NCC191872, minor, term to 2029-03-31
What stands out
- Its term runs 4 years and 364 days, April 1, 2024 to March 31, 2029.
- No dated event in the 365 days to October 14, 2026.
- It is one of 19,518 discharge permits on the register in North Carolina; the file names no program for it, and it is a minor discharger.
Identity
| Facility | CARY TRIANGLE EXPRESSWAY 230KV GREENFIELD SUBSTATION (T6811) DEVELOPMENT PL |
|---|---|
| Permittee | Duke Energy Progress, LLC |
| NPDES ID | NCC232430 |
| Status | Effective |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Issued | April 1, 2024 |
| Expires | March 31, 2029 |
| Address | Cary, NC 27519 |
| Subwatershed | White Oak Creek (HUC 030300020608) |
| SIC | 9999 – Nonclassifiable Establishments |
NPDES NCC232430: effluent limits and exceedances
CARY TRIANGLE EXPRESSWAY 230KV GREENFIELD SUBSTATION (T6811) DEVELOPMENT PL (NPDES NCC232430): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES NCC232430: no pollutant row on file.
NPDES NCC232430: inspections, violations and enforcement
NPDES NCC232430 (CARY TRIANGLE EXPRESSWAY 230KV GREENFIELD SUBSTATION (T6811) DEVELOPMENT PL): no single-event violation, inspection, formal enforcement action and informal enforcement action on file.
Watch NPDES NCC232430
NPDES NCC232430: one email when its EPA record changes — $99/month.
Permits near NPDES NCC232430
NPDES NCC232430: 0 pollutant rows, 0 dated events; ICIS-NPDES download, loaded October 14, 2026.