NPDES NCC253659 · Clean Water Act
DUKE ENERGY PROGRESS LILESVILLE - OAKBORO 230KV BLACK AND WHITE LINE REBUIL, Lilesville, NC: NPDES NCC253659 discharge permit, effluent exceedances, inspections, penalties
DUKE ENERGY PROGRESS LILESVILLE - OAKBORO 230KV BLACK AND WHITE LINE REBUIL, Lilesville, North Carolina: General permit coverage NCC253659, held by Duke Energy Progress, LLC; Effective; issued December 4, 2025, term to March 31, 2029; Power and Communication Line and Related Structures Construction.
Other permits held by Duke Energy Progress, LLC
- H.F LEE ENERGY COMPLEX INACTIVE BASIN CLOSURE (INACTIVE BASINS 1 AND 2), Goldsboro: NCC204357, issued 2024-04-01
- H.F. LEE ENERGY COMPLEX INACTIVE BASIN CLOSURE (INACTIVE BASIN 3), Goldsboro: NCC204399, issued 2024-04-01
- H.F. LEE ENERGY COMPLEX INACTIVE BASIN CLOSURE (BASINS 1 AND 2), Goldsboro: NCC213476, issued 2024-04-01
- CAPE FEAR 1956 BASIN EXCAVATION, Moncure: NCC213763, issued 2024-04-01
- ENKA 230KV SUBSTATION EXPANSION, Asheville: NCC213864, issued 2024-04-01
- MILBURNIE 230KV - YARD REBUILD, Raleigh: NCC217178, issued 2024-04-01
- 1963 & 1970 BASIN EXCAVATION EROSION & SEDIMENT CONTROL PLAN, Moncure: NCC222708, issued 2024-04-01
- HF LEE BLACK JACK CHURCH ROAD STOCKPILE E&SC PLAN, Goldsboro: NCC223366, issued 2024-04-01
- ATLANTIC 34.5KV OYSTER CREEK, Davis: NCC223526, issued 2024-04-01
- CAPE FEAR 63/70 BASIN HAUL ROAD, Moncure: NCC230214, issued 2024-04-01
DUKE ENERGY PROGRESS LILESVILLE - OAKBORO 230KV BLACK AND WHITE LINE REBUIL among its neighbors
6 discharge permits are in the Island Creek-Pee Dee River subwatershed (HUC 030402010304); NCC253659 is one.
Other permits in the Island Creek-Pee Dee River subwatershed (HUC 030402010304)
- ANSON INDUSTRIAL PARK - PDEMC SOUTHEAST CAMPUS EXPANSION, Lilesville: NCC242297, minor, term to 2029-03-31
- ATLANTIC GATEWAY LOGISTICS PARK, Lilesville: NCC242206, minor, term to 2029-03-31
- CLARK MOUNTAIN ROAD BORROW PIT, Lilesville: NCC203268, minor, term to 2029-03-31
- CLARK MOUNTAIN ROAD BORROW PIT, Lilesville: NCC241012, minor, term to 2029-03-31
- SLUDGE REMOVAL PLAN FOR EXISTING SLUDGE STORAGE SITE ANSON CO., Lilesville: NCC222568, minor, term to 2029-03-31
What stands out
- Its term runs 3 years and 117 days, December 4, 2025 to March 31, 2029.
- No dated event in the 365 days to October 14, 2026.
- It is one of 19,518 discharge permits on the register in North Carolina; the file names no program for it, and it is a minor discharger.
Identity
| Facility | DUKE ENERGY PROGRESS LILESVILLE - OAKBORO 230KV BLACK AND WHITE LINE REBUIL |
|---|---|
| Permittee | Duke Energy Progress, LLC |
| NPDES ID | NCC253659 |
| Status | Effective |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Issued | December 4, 2025 |
| Expires | March 31, 2029 |
| Address | Lilesville, NC 28091 |
| Subwatershed | Island Creek-Pee Dee River (HUC 030402010304) |
| NAICS | 237130 – Power and Communication Line and Related Structures Construction |
| SIC | 1623 – Water, Sewer, And Utility Lines |
NPDES NCC253659: effluent limits and exceedances
DUKE ENERGY PROGRESS LILESVILLE - OAKBORO 230KV BLACK AND WHITE LINE REBUIL (NPDES NCC253659): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES NCC253659: no pollutant row on file.
NPDES NCC253659: inspections, violations and enforcement
NPDES NCC253659 (DUKE ENERGY PROGRESS LILESVILLE - OAKBORO 230KV BLACK AND WHITE LINE REBUIL): no single-event violation, inspection, formal enforcement action and informal enforcement action on file.
Watch NPDES NCC253659
NPDES NCC253659: one email when its EPA record changes — $99/month.
Permits near NPDES NCC253659
NPDES NCC253659: 0 pollutant rows, 0 dated events; ICIS-NPDES download, loaded October 14, 2026.