NPDES NHR10028M · Clean Water Act
Q195 ELECTRIC TRANSMISSION LINE REBUILD PROJECT, Littleton, NH: NPDES NHR10028M discharge permit, effluent exceedances, inspections, penalties
Q195 ELECTRIC TRANSMISSION LINE REBUILD PROJECT, Littleton, New Hampshire: General permit coverage NHR10028M, held by Michels Power, Inc.; Construction stormwater; Effective; issued April 15, 2026, term to February 16, 2027, by U.S. EPA.
New Hampshire holds 1,239 Construction stormwater coverages of this permit type in EPA’s file; 1,064 were issued before NHR10028M. Michels Power, Inc. holds 5 permits in New Hampshire.
Other permits held by Michels Power, Inc.
- T198 LINE MAINTENANCE PROJECT - PHASE 2, Keene, Swanzey, And Troy: 01R10I062, issued 2025-11-27
- 2021 D108 TRANSMISSION LINE STRUCTURE REPLACEMENT PROJECT, Keene: NHR1001B3, issued 2021-08-23
- 2021 379 TRANSMISSION LINE STRUCTURE REPLACEMENT PROJECT, Fitzwilliam: NHR1001D7, issued 2021-11-10
- 3386 SUB-TRANSMISSION LINE ASSET CONDITION REFURBISHMENT PROJECT, Monroe: NHR10027X, issued 2026-03-16
Coverages issued nearest NHR10028M
- 2026-04-09: PROPOSED CONTRACTOR'S YARD, Merrimack: NHR10028G, held by Lynchs Excavation and Landscaping
- 2026-04-10: ANDOVER 20650, Andover: 01R10I083, held by New Hampshire Department of Transportation
- 2026-04-10: GKN AEROSPACE - PROPOSED EXPANSION, Charlestown: NHR10028H, held by GKN Aerospace New England Corporation (Kurt Dermody)
- 2026-04-10: 6 ROUNDSTONE DRIVE, Londonderry: NHR10028I, held by Lansing Melbourne Group
- 2026-04-13: CONTINENTAL PAVING SITE PLAN, Loudon: NHR10028K, held by Continental Paving, Inc.
- 2026-04-15: FECTEAU CORNER, Epping: NHR10028N, held by Fecteau Holdings, LLC
- 2026-04-15: FECTEAU CORNER, Epping: NHR10028O, held by JAFCO Excavation & Trucking
- 2026-04-15: NHDOT PROJECT 20650 ANDOVER, Andover: NHR10028Q, held by R.S.Audley Incorporated
- 2026-04-15: 6 ROUNDSTONE DRIVE, Londonderry: NHR10028R, held by R.S.Audley Incorporated
- 2026-04-15: GKN AEROSPACE - PROPOSED EXPANSION, Charlestown: NHR10028S, held by OSgood
Q195 ELECTRIC TRANSMISSION LINE REBUILD PROJECT among its neighbors
9 discharge permits are in the Comerford Dam Reservoir-Connecticut River subwatershed (HUC 010801030203); NHR10028M is one.
Other permits in the Comerford Dam Reservoir-Connecticut River subwatershed (HUC 010801030203)
- 3386 SUB-TRANSMISSION LINE ASSET CONDITION REFURBISHMENT PROJECT, Monroe: NHR10027C, minor, term to 2027-02-16
- 3386 SUB-TRANSMISSION LINE ASSET CONDITION REFURBISHMENT PROJECT, Monroe: NHR10027X, minor, term to 2027-02-16
- COMERFORD SUBSTATION REBUILD PROJECT, Monroe: NHR1000YF, minor, term to 2022-02-15
- COMERFORD SUBSTATION REBUILD PROJECT, Monroe: NHR1000Z0, minor, term to 2022-02-15
- GREAT RIVER HYDRO, LLC - COMERFORD STATION, Monroe: NHG360003, minor, term to 2014-12-31
- GREAT RIVER HYDRO, LLC - MOORE STATION, Littleton: NHG360004, minor, term to 2014-12-31
- Q195 ELECTRIC TRANSMISSION LINE REBUILD PROJECT, Littleton: NHR100280, minor, term to 2027-02-16
- U199 TRANSMISSION LINE REBUILD AND OPGW PROJECT, Multiple: NHR100210, minor, term to 2027-02-16
What stands out
- Its term runs 307 days, April 15, 2026 to February 16, 2027.
- No dated event in the 365 days to October 14, 2026.
- It is one of 1,994 discharge permits on the register in New Hampshire; 1,239 of them (62%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility | Q195 ELECTRIC TRANSMISSION LINE REBUILD PROJECT |
|---|---|
| Permittee | Michels Power, Inc. |
| NPDES ID | NHR10028M |
| Status | Effective |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Construction stormwater |
| Issued | April 15, 2026 |
| Expires | February 16, 2027 |
| Agency | U.S. EPA |
| Address | Littleton, NH 03561 |
| Subwatershed | Comerford Dam Reservoir-Connecticut River (HUC 010801030203) |
NPDES NHR10028M: effluent limits and exceedances
Q195 ELECTRIC TRANSMISSION LINE REBUILD PROJECT (NPDES NHR10028M): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES NHR10028M: no pollutant row on file.
NPDES NHR10028M: inspections, violations and enforcement
NPDES NHR10028M (Q195 ELECTRIC TRANSMISSION LINE REBUILD PROJECT): no single-event violation, inspection, formal enforcement action and informal enforcement action on file.
Watch NPDES NHR10028M
NPDES NHR10028M: one email when its EPA record changes — $99/month.
Permits near NPDES NHR10028M
NPDES NHR10028M: 0 pollutant rows, 0 dated events; ICIS-NPDES download, loaded October 14, 2026.